RC-000334-2016 TOWN OF QUEENSBURY
742 Bay Road,Queensbury,NY 12804-5904 (518)761-8201
--- Community Development-Building&Codes (518)761-8256
CERTIFICATE OF OCCUPANCY
Permit Number: RC-000334-2016 Date Issued: Tuesday,November 22, 2016
This is to certify that work requested to be done as shown by Permit Number RC-000334-2016
has been completed.
Tax Map Number: 296.14-2-9
Location: 53 DEVIN CT
Owner: CERRONE BUILDERS, INC.
Applicant: CERRONE BUILDERS, INC.
This structure may be occupied as a: SFD 1376 s.f.,garage 430 s.f., 1-FP
Village at Sweet Road,Lot 9 By Order of Town Board
TOWN OF QUEENNSBURY
j4k--
Issuance of this Certificate of Occupancy DOES NOT relieve the
property owner of the responsibility for compliance with Site Plan,
Variance,or other issues and conditions as a result of approvals by the Director of Building&Code Enforcement
Planning Board or Zoning Board of Appeals.
� r z TOWN OF QUEENSBURY
742 Bay Road,Queensbury,NY 12804-5904 (518)761-8201
- Community Development - Building& Codes (518) 761-8256
BUILDING PERMIT
Permit Number. RC-000334-2016
Tax Map No: 296.14-2-9
Permission is hereby granted to: CERRONE BUILDERS, INC.
For property located at: 53 DEVIN CT
In the Town of Queensbury,to construct or place at the above location in accordance with application together
with plot plans and other infonnation hereto filed and approved and in compliance with the NYS Uniform
Building Codes and the Queensbury Zoning Ordinance
jWe of Construction
Owner Name: CERRONE BUILDERS,INC. Single Family-New $295,000.00
Owner Address: 1589 State Route 9 Total Value $295,000.00
Fort Edward,NY 12828
Contractor or Builder's Name/Address Electrical Inspection Agency
CERRONE BUILDERS,INC.
1589 State Route 9
Fort Edward,NY 12828
Plans&Specifications
SFD 1376 s.f.,garage 430 s.f., 1-FP
Village at Sweet Road,Lot 9
$ 1,239.70 PERMIT FEE PAID -THIS PERMIT EXPIRES: Saturday,June 10, 2017
(If a longer period is required,an application for an extension must be made to the code Enforcement Officer
of the Town of Queensbury before the expiration date.)
Dated at the Townsbury; Wed d June 15, 2016
SIGNED BY: for the Town of Queensbury.
Director of Building&Code Enforcement
PRINCIPAL STRUCTURE APPLICATION Office Use Only
DATE Z-, {1 Received
Tax Map I D
TAX MAP ID Permit No. �-� t to
Permit Fee8
ZONING Rec Fee _B r
Site Plan#
HISTORIC SITE Yes /No Subdivision #
SUBDIVISION NAME / A� Lelp-Lot#
TOWN BD.RESOLUTION 86-2013: $850 RECREATION FEE FOR NEW DWELLING UNITS,INCLUDING SINGLE FAMILY DWELLINGS,DUPLEXES
OR TWO FAMILY DWELLINGS, MULTIPLE FAMILY DWELLINGS, APARTMENTS, CONDOMINIUMS, TOWNHOUSES, AND/0R MANUFACTURED &
MODULAR HOMES, BUT NOT MOBILE HOMES_ THIS IS IN ADDITION TO THE PERMIT FEE.
APPLICANT � � �,I/��J OWNER
ADDRESS ADDRESS
tlzosl
PHONE/E-MAIL 7 / ✓ �''� PHONE/E-MAIL
CONTRACTOR COST OF CONSTRUCTION ESTIMATED :
ADDRESS: BUILDING ADDRESS:
PHONE/E-MAIL f
CONTACT PERSON FOR BUILDING& CODES COMPLIANCE: t� �='""" """ PHONE
� � E_LT
TYPE OF CONSTRUCTION 4 i
JUN (� 2 2016
Check all that apply PI ase indicate measurements as r quired below
New Addition Alteration 152 flog sq ft, 2"d.floor sq.ft Tatai sq.ft. Height
Single Family
Two-Family
Multi-Family
(# of units )
Townhouse
Business Office
Retail - Mercantile
Factory- Industrial
Attached Garage
0 0�0
Other
Town of Queensbury Building&Codes Principal Structure Application July 2014
If commercial or industrial indicate name of business
Proposed use of building or addition lG49 .
Source of heat(circle one) Gas Oil Propane Solar Other
Fireplace: complete a separate application for Fuel Burning Appliances& G� 1A&"A&
Chimneys
Are there structures not shown on plot plan?
Are there easements on the property? A10
Site Information
a. Dimensions or acreage of lot (� 1
b. Is this a comer lot? (j
c. Will the grade be changed as a result of construction Yes No
d. Public water or Private well v 1" �J
e. Sewer or Private Septic System f 45;W6/�,,.
Value of all work to be performed (labor or materials) $ M;;ooa�"'
DECLARATION:
1. 1 acknowledge no construction shall be commenced prior to issuance of a valid permit and will be completed
Within a 12 month period.
2. If work is not complete by the 1 year expiration date the permit may be renewed,subject to fees and department
approval.
3. 1 certify that the application, plans and supporting materials are a true and complete statement/description of
the work proposed,that all work will be performed in accordance with the NY State Building Codes,local building
laws and ordinances,and in conformance with local zoning regulations.
4. 1 acknowledge that prior to occupying the facilities proposed, I or my agents will obtain a certificate of occupancy.
5. 1 also understand,that I/we,are required to provide an as-built survey by a licensed land surveyor of all newly
constructed facilities prior to issuance of a certificate of occupancy.
I have read and agree to the above: PRINT NAME: ' r71 DATEb"17-111%
SIGNATURE: DATE !�
FOR OPME USrE ONLY
Operating Permit Issued: Yes No
Occupancy Type
Construction Classification
Assembly Occupancy Umit
Special Conditions
2
Town of Queensbury Building&Codes Principal Structure Application July 2014
L�
296.14-2-9 RC-000334-2016
Cerrone Builders
53 Devin Court
SFD 1376 s.f., garage 430 s.f., 1-FP
YUN PEIMlj r,
-� I HAVE Pff SONALLY t; ,
ti-�,Jly b 4 ll�� � �� . F
EASUrRED THE DS1 A�dCE
E31j�LU11V--iRGPERTY L; T( HE
PRO �JE' �
TFRUCTURE(S) OR
D 7
10 T 0?
7
IV
i
i
Fuel Burning Appliance & Chimney Application Office Use Only
// Received
DATE: 1i /�lo __ = v•. Tax Map 1D
. .. .: `
TAX MAP ID: 4 p Permit No.
Permit Fee 5 I)
ZONE: '�
JUN a 2 2016
OWNER lJ . 4-.-.�__ .( U_c - �PH`ONE E-MAIL
VVPd OF ..:t ,. l Z�
ADDRESS �" ,, �`
INSTALLER/ 171rPHONE/E-MAIL
BUILDER ]j r aalce__
CONTACT PERSON FOR BUILDING&CODE COMPLIANCE:
PHONE/E-MAIL � + � BUILDING ADDRESS f,dl
ROOM OF INSTALL: i Y PLANNED INSTALL DATE: 2�[1&
^ t
FUEL BURNING APPLIANCE INFORMATION WOOD COAL PELLET GAS OIL NOTE: ROUGH-IN&
STOVE FINAL INSPECTION ARE
FIREPLACE INSERT
REQUIRED.
FIREPLACE,FACTORY BUILT* NOTE:
MANUFACTURER'S
FIREPLACE,MASONRY
INSTALLATION MANUAL
FURNACE GARAGE ONLY) MUST BE AVAILABLE AT
TIME OF INSPECTION
*If factory built provide manufacturer name: le5,11L ; Model#:
Listed by: Number:
CHIMNEY INFORMATION
Masonry** (check one) BLOCK BRICK STONE
Flue TIE STEEL Size in inches
Material DOUBLE WALL TRIPLE WALL INSULATED
** If non-masonry provide manufacturer name: o ;Model#:
DECLARATION: Construction/installation must conform to NYS Fire Prevention & Building Code and/or
manufacturer requirements. The applicant or owner agrees to comply With all applicable laws, ordinances,
regulations, and all conditions that are part of these requirements and also will allow inspector's to enter premises
to perform required inspections.
I HAVE READ AND AGREE TO THE ABOVE:
PRINT NAME: DATE:
SIGNATURE: DATE:
Town of Queensbury Building&Codes Principal Structure Application Revised September 2014
Town of Queensbury Thomas R. Van Ness
Highway Department Highway Superintendent
742 Bay Road, Queensbury, NY 12804 Home: (518) 745-0929
Phone. (518) 761-8211
Fax: (518)745-4466 David Duell
Deputy Highway Superintendent
Home: (518)745-0938
DRIVEWAY PERMIT
Date:
Applicant Name: 2
Telephone No.: l
Address to Be Inspected:
Return Address:
Applicant must show exact location and width of driveway(s) to be connected to the highway by
placing stakes at the specified location.
The Superintendent of Highways of the Town of Queensbury has reviewed this application. The
following action has been taken:
STEP 1: { } Preliminary approval
NEED Slight Swale JUN 02
{ } Deep Swale
{ } Level with the road 75754 O'� { d `NSSUPY
( } Level with the top of the paved wing
Bt4lLv4�G ''�C��-ES
Size culvert pipe to be used (if necessary)
( ) 12" ( ) 15" ( ) 18" ( ) 24» ( ) 36„
Preliminary inspection completed by, Date:
Approval by Highway Supt.: (or) Deputy Supt.:
Upon completion please resubmit this approval permit for a final approval.
STEP 2: ( ) Final Approval ( ) Rejected
Date:
Thomas R. Van Ness, Highway Superintendent David Duell, Deputy Highway Superintendent
7
Town of Queensbury Building&Codes Principal Structure Application July 2014
10
(Ao
Lo V-10
WIV-w
77
REScheck Software Version 4.6.2
Compliance Certificate
Project Cerrone Builders Inc �L W.
Energy Code: 2010 New York Energy Conservation
Location; Warren County, New York
rt,
Construction Type: Single-family
Project Type: New ConstructionQJ
3 I. ri
Conditioned Floor Area: 1,376 ft2
Glazing Area 9%
Climate Zone: 6 (7635 HDD) nq
Permit Date: JUN 0 2 2016
Permit Number: TOWN OF QUEE
Construction Site: Owner/Abent: BUILDING s CODESDesi„g.nir/Contractor:
53 Devin Court "� "` a T VISION Engineering, LLC
Lot 9 206 Glen Street
Queensbury, NY 12804 Ste 56
Glens Falls, NY 12801
Compliance: Passes using LIA trade-off
Compliance: 9.4%Better Than Code Maximum UA: 260 Your UA: 246
The%Better or Worse Than Code Index reflects how close to compliance the house is based on code trade-off rules.
It DOES NOT provide an estimate of energy use or cost relative to a minimum-code home.
Envelope Assemblies
Assembly Gross Area Cavity Cont.
Perimeter
Ceiling 1: Raised or Energy Truss 1,376 38.0 0.0 0.025 34
Wall 1: Wood Frame, 16" o.c. 1,640 21.0 0.0 0.057 83
Window 1:Vinyl/Fiberglass Frame:Double Pane with Law-E 119 0.340 40
Door 1: Solid 18 0.140 3
Door 2: Solid 20 0.220 4
Door 3: Glass 20 0.250 5
Basement Wall 1: Solid Concrete or Masonry 1,248 0.0 11.0 0.059 73
Wall height: 7.8'
Depth below grade: 6.5'
Insulation depth: 7.8'
Window 2: Vinyl/Fiberglass Frame:Double Pane with Low-E 9 0.400 4
Compliance Statement: The proposed building designdescrire
here is consistent with the building plans, specifications, and other
calculations submitted with the permit application.The propbuilding has been designed to et the 2010 New York Energy
Conservation Construction Code requirements in REScheck Von 4.6.2 and to co a mandatory require ents listed in
he E heck I spection.Checklist. [
Na e T tf Signature Date
296.14-2-9 RC-000334-2016
Project Title: Cerrone Builders Inc Cerrone Builders t date: 05/26/16
Data filename: CAUsersllrobision\Dropbox\V 53 Devin Court
Page 1 of 7
Cerrone Lot: 9 Devin Court11138 CER Resche
SFD 1376 s.f., garage 430 s.f., 14P
Project Title: Cerrone Builders Inc Report date: 05/26/16
Data filename: C:\Users\lrobision\DropboxWISION Engineering, LLC\Active Projects VE11138- DES- Page 2 of 7
Cerrone Lot 9 Devin Court\1138 CER Rescheck.rck
REScheck Software Version 4.6.2
Inspection Checklist
Energy Code: 2010 New York Energy Conservation Construction Code
Requirements: 0.0% were addressed directly in the REScheck software
Text in the "Comments/Assumptions" column is provided by the user in the REScheck Requirements screen. For each
requirement, the user certifies that a code requirement will be met and how that is documented, or that an exception
is being claimed. Where compliance is itemized in a separate table, a reference to that table is provided.
Section Plans Verified Field Verifled
# Pre-Inspection/Plan Review Value Value Complies? Comments/Assumptions
& Req.ID
103.2 Construction drawings and ❑Complies
[PR1]1 documentation sufficiently ❑Does Not
4 demonstrates energy code
compliance for the building ❑Not Observable
envelope. ❑Not Applicable
103.2, Construction drawings and ❑Complies
403.7 documentation sufficiently ❑Does Not
[PR311 demonstrates energy code
compliance for lighting and -]Not Observable
mechanical systems.Systems ❑Not Applicable
serving multiple dwelling units
must demonstrate compliance
with the commercial code.
403.6 Heating and cooling equipment is Heating: Heating: ❑Complies
[PR2]2 sized per ACCA Manual 5 based Btu/hr Btu/hr ❑Does Not
B, on loads per ACCA Manual J or Cooling: Cooling:
other approved methods. Btu/hr Btu/hr ❑Not Observable
❑Not Applicable
Additional Comments/Assumptions:
111 High Impact(Tier 1) 12 IMedium Impact(Tier 2) 3 Low Impact(Tier 3)
Project Title: Cerrone Builders Inc Report date: 05/26/16
Data filename: C:\Users\lrobision\Dropbox\VISION Engineering, LLC\Active Projects VE\1138- DES- Page 3 of 7
Cerrone Lot 9 Devin Court\1138 CER Rescheck.rck
Section
# Foundation Inspection Complies? Comments/Assumptions
& Req.ID
303.2.1 Exposed foundation insulation ❑Complies
[FO11]2 protection. ❑Does Not
144) ❑Not Observable
❑Not Applicable_
403.8 Snow melt controls. ❑Complies
[FO12]2 ❑Does Not
-' []Not Observable
❑Not Applicable
Additional Comments/Assumptions:
11 High Impact(Tier 1) 2 Medium Impact(Tier 2} T31Low Impact(Tier 3)
Project Title: Cerrone Builders Inc Report date: 05/26/16
Data filename: C:\Users\lrobision\Dropbox\VISION Engineering, LLC\Active Projects VE\1138- DES- Page 4 of 7
Cerrone Lot 9 Devin Court\1138 CER Rescheck.rck
Section Plans Verified Field Verified
# Framing/Rough-In Inspection Value Value Complies? Comments/Assumptions
& Req.ID
402.4.4 Fenestration that is not site built ❑Complies
[FR20]1 is listed and labeled as meeting ❑Does Not
My AAMA/WOMA/CSA 101(I.S.2/A440
or has infiltration rates per NFRC []Not Observable
400 that do not exceed code ❑Not Applicable
limits.
402.4.5 IC-rated recessed lighting fixtures ❑Complies
[FR16]2 sealed at housing/interior finish ❑Does Not
4 and labeled to indicate&It;= 2.0 -
cfm leakage at 75 Pa. ❑Not Observable
ONot Applicable _
403.2.2 All joints and seams of air ducts, ❑Complies
[FR13]1 air handlers,filter boxes,and ❑Does Not
�, building cavities used as return
ducts are sealed. ❑Not Observable
ONot Applicable
403.2.3 Building cavities are not used as ❑Complies
[FR15]3 ducts or plenums. ❑Does Not
❑Not Observable
❑Not Applicable
403.3 HVAC piping conveying fluids R- R- ❑Complies
[FR17]2 above 105 OF or chilled fluids ❑Does Not
Ab below 55 OF are insulated to R-3.
❑Not Observable
❑Not Applicable
403.4 Circulating service hot water R- R- ❑Complies
[FR18]2 pipes are insulated to R-2. ❑Does Not
❑Not Observable
ONot Applicable
403.5 :Automatic or gravity dampers are ❑Complies
[FR19]2 ,installed on all outdoor air ❑Does Not
intakes and exhausts. ❑Not Observable
❑Not Applicable
Additional Comments/Assumptions:
1 I High Impact(Tier 1) 2 Medium Impact(Tier 2) 3 1 Low Impact(Tier 3)
Project Title: Cerrone Builders Inc Report date: 05/26/16
Data filename: C:\Users\lrobision\Dropbox\VISION Engineering, LLC\Active Projects VE\1138- DES- Page 5 of 7
Cerrone Lot 9 Devin Court\1138 CER Rescheck.rck
Section
# Insulation Inspection Complies? Comments/Assumptions
& Req.1IJ
303.1 All installed insulation labeled or ❑Complies
[IN13}2 installed R-values provided. ❑Does Not
❑Not Observable
❑Not Applicable
Additional Comments/Assumptions:
------- - ----
11 High Impact{Tier 1} -12[144um Impact{Tier 2} - 3Low Impact{Tier 3}
Project Title: Cerrone Builders Inc Report date: 05/26/16
Data filename: C:\Users\lrobision\Dropbox\VISION Engineering, LLC\Active Projects VE\1138- DES- Page 6 of 7
Cerrone Lot 9 Devin Court\1138 CER Rescheck.rck
Section
# Final Inspection Provisions Plans Verified Field Verified Value Value Complies? Comments/Assumptions
& Req.ID
402.4.2, Building envelope tightness ACH 50= ACH 50= ❑Complies
402.4.2.1 verified by blower door test result ❑Does Not
[FI1711 of<:7 ACH at 50 Pa.This
requirement may instead be met []Not Observable
via visual inspection,in which ❑Not Applicable
case verification may need to
occur during Insulation
Inspection.
403.2.2 Duct tightness via post- cfm cfm ❑Complies
[FI411 construction with maximum ❑Does Not
leakage of 8 cfm to outdoors,or
12 cfm across systems.For ❑Nat Observable
rough-in tests,verification may ❑Not Applicable
need to occur during Framing
Inspection,with maximum
leakage of 6 cfm across systems
and 4 cfm without air handler.
403.1.1 Programmable thermostats
❑Complies
[F19]2 installed on forced air furnaces. ❑Does Not
Ito ❑Not Observable
❑Not Applicable
403.1.2 Heat pump thermostat installed ❑Complies
[FI10]2 on heat pumps. ❑Does Not
❑Not Observable
❑Not Applicable
403.4 Circulating service hot water ❑Complies
[FI11]2 systems have automatic or ❑Does Not
accessible manual controls. ❑Not Observable
❑Not Applicable
401.3 Compliance certificate posted. ❑Complies
[F17]2 ❑Does Not
110) ❑Not Observable
❑Nat Applicable
-----------------
303.3 Manufacturer manuals for ❑Complies
[FI18]3 mechanical and water heating ❑Does Not
equipment have been provided.
❑Nat Observable
❑Nat Applicable
Additional Comments/Assumptions:
11 High Impact(Tier 1) 2 Medium Impact(Tier 2) 3 Low Impact(Tier 3]
Project Title: Cerrone Builders Inc Report date: 05/26/16
Data filename: CAUsers\Irobision\Dropbox\VISION Engineering, LLC\Active Projects VE\1138- DES- Page 7 of 7
Cerrone Lot 9 Devin Court\1138 CER Rescheck.rck
2010 New York
Energy Conservation
Construction Code
Energy Efficiency
certificate
Insulation Rating R-Value
Above-Grade Wall 21.00
Below-Grade Wall 11,00
Floor 0.00
Ceiling 1 Roof 3800
Ductwork (unconditioned spaces):
Glass&Door Rating a
Window 0.34
Door 0.22
Heating&Cooling Equipment Effie!
ency
Heating System:
Cooling System:
Water Heater:
Name• Date:
Comments
ECTRICAL INSPECTORS
The following electrical inspection agencies are certified by the Town of Queensbury
to perform electrical inspections:
Business Inspector Contact Number(s)
Commonwealth Electrical Inspection Donald Loveland 800-562-9934
Services
176 Doe Run Road Ron Mumblo 518-798-0905
tM im PA 17545
Middle Department Main Office 800-873-6342
143 Troy Schenectady Road Local Office 800-479-4504
Watervliet, NY 12189 518-273-0862
Ray Novak 518-369-6614
Joseph Holmes 518-854-9290
The Inspector, LLC Douglas R. Hull .8004870535
4755 McConchie Road Brian D. met
Galway, NY. 12074
__. David*J. Irwin
Atlantic-Inland Inc. New York Devin Pratt 518-857-6235
8 Pinewood Road dpratt760mail.com
Queensbury, NY 12804 atlantic-inland.com
RESIDENTIAL ONLY
Northeast Electrical Inspections, LLC Dave Near P: 518-852-0826
65 Albermarle Road dave@neillc.com F: 518-370-1927
`Scotia, NY 12302 Steven Reynolds
www.neilic.com (residentlal only)
Daniel Valls
(residential only)
Please Note: We cannot recommend an inspector. .
Please ask your contractor which agency they prefer to inspect
their work.