inspectionsINSPECTION WORKSHEET (MULT-006061-2018)
Town of Queensbury - Building and Codes - Fire Marshal
742 Bay Road - (518) 761-8256 Building (518) 761-8206 Fire Marshal
Case Number:
Inspection Date:
Inspector:
Case Module:
Inspection Status:
Inspection Type:
CC-000480-2017
08/21/2018
John O'Brien
Permit
Partial Pass
Multi-Dwelling, Hotel, Motel Fin-
al
Job Address:Parcel Number:524 AVIATION RD
Queensbury, NY 12804
302.5-1-96.1
Contact Type Company Name Name
Primary Owner Aviation Hospitality, LLC Jariwala, Bhavik
Applicant Bast Hatfield Construction LLC Fretto, John
Granted Permission Aviation Hospitality, LLC Jariwala, Bhavik
Contractor Bast Hatfield Construction LLC Fretto, John
Architect AIA Architect ,
Checklist Item Passed Comments
Aug 21, 2018 Page (1)
INSPECTION WORKSHEET (MULT-006061-2018)
Checklist Item Passed Comments
Building Inspector Notes YES 6/21/18 Preliminary Final Inspection Not Approved
-Install all interior signage and room numbers
-Adjust all corridor doors to rooms, stair towers and
bathroom doors. Corridor doors must self close and
latch.
-Complete final connections of all plumbing fixtures.
Also adjust drain stoppers for bathroom lavatories so
they drain freely some are draining very slow.
-Electrical Rooms on each floor has firestopping that
needs to be addressed. Specifically electrical conduits
and miscellaneous wire chases from floor to floor. Seal
all wall and ceiling penetrations as discussed.
-Seal gaps at laundry chute doors at each floor as
discussed.
-Seal up holes in 1st floor corridor walls on both sides at
south end of building. Need to verify before corridor
ceiling is closed up.
-Need to inspect elevator shaft to verify all penetrations
have been sealed.
-Final Electrical Inspection
-Blower Door Test
-HVAC Air Balancing Report
-Final approval letters from Architect, Engineer and the
Special Inspections Agency (Construction
Technologies).
-Submit all special inspections reports for soil
compaction, concrete testing, structural steel and
structural wood framing. These can be submitted on a
thumb drive.
-Submit a letter certifying that the building envelope.
Electrical and Mechanicals were installed in accordance
with the approved 2015 IECC COMcheck.
-Submit the Final Survey.
-Complete all site items. Separate inspection!
-Complete all fire marshal's items. Separate inspection!
-Complete parking lot striping and handicapped parking
and no parking signage.
6/26/18 Final Inspection 3rd & 4th Floors Not Approved
-Miscellaneous corridor and room doors need final
adjustments
6/28/18 Final Inspection Not Approved-Temp Co
-See Dave Hatin's remaining items on his inspection
slip.
Note: Final Inspection 9:00 AM Friday for Temp CO!
7/5/18 Final Inspection Partial Approval
TEMPORARY CO APPROVED -OK TO OCCUPY
Conditions:
-Submit certified final survey
-Complete all remaining site items and submit
engineer's site certification.
-Complete all exterior caulking
-Submit As-Built Construction Plans
-Complete remaining Fire Marshal's Items.
Aug 21, 2018 Page (2)
INSPECTION WORKSHEET (MULT-006061-2018)
Checklist Item Passed Comments
Chimney Height / B Vent / Direct Vent Location YES
Plumb Vent Thru Roof Minimum 6 YES
Outside Spigots have Air Gap YES
Roof Complete YES
Ext Finish /Grade Complete/6 in 10ft or Equivalent YES
Interior/Exterior Railings 34 into 38 inch YES
Interior Handrails Stairs 1 or More Risers YES
Guardrails 42", Balusters 4 Minimum Spacing YES
Vestibules for Exit doors greater than 3000 sq. ft YES
Doors 36 Lever Handles YES -Adjust all corridor doors to rooms, stair towers and
bathroom doors. Corridor doors must self close and
latch.
Headroom 6ft 8 on Stairs YES
Bathroom / Kitchen Watertight YES
Low flow toilet 1.3 gal/flushing cycle -
showerhead/faucet
YES
Safety glazing: w/in 5' of tub/shower - stairwell win/adj to
drs
YES
Smoke Detectors 3' from Kitchens & Baths R314 YES
Dryer Duct Max Length 35', Labeled Over 35'YES
Bathroom Fans Plumbing Fixtures Complete YES -Complete final connections of all plumbing fixtures.
Also adjust drain stoppers for bathroom lavatories so
they drain freely some are draining very slow.
6/27/18 complete plumbing issues on second floor
Foundation Insulation YES
Bollard Protection: 15" footings & 3' below grade YES
Bollard Protection:4' on ctr/3' abv grd, gas meter YES
Aug 21, 2018 Page (3)
INSPECTION WORKSHEET (MULT-006061-2018)
Checklist Item Passed Comments
Fire Separation, ¾, 1, 2 hr.YES -Electrical Rooms on each floor has firestopping that
needs to be addressed. Specifically electrical conduits,
miscellaneous wire chases from floor to floor. Seal all
wall and ceiling penetrations as discussed.
-Seal gaps at laundry chute doors at each floor as
discussed.
-Seal up holes in 1st floor corridor walls on both sides at
south end of building. Need to verify before corridor
ceiling is closed up.
-Seal electrical conduit sleeves at ceilings of each
electrical room
Fire Walls 1, 2, 3 Hour / Fire Door ¾, 1 ½, 2 Hour YES Elevator Chase
20 Minute Fire Door/Self-Closing Hardware YES -Adjust all corridor doors to rooms, stair towers and
bathroom doors. Corridor doors must self close and
latch.
H/C Accessibility Parking Signage YES -Stripe handicapped parking spaces at south end exit.
Universal Symbol of Access displayed - on all H/C
signs
YES
Hydraulic Elevators: Non-comb. Plumbing REQUIRED YES
Elevator Operation and Signage Shaft Sealed YES -Need to inspect elevator shaft to verify all penetrations
have been sealed.
Gas Shut-off Exposed & Regulator (18) Above Grade YES
Furnace Hot Water Heater operating YES
Low Water Shut-Off for Boiler YES
Blower Door Test Certification YES Test failed needs to be redone.
BLOWER DOOR TEST RECEIVED AND PASSED.
Relief Valve ,Heat Trap/Water Temp 110 deg or less YES -Relief Valve downspouts not installed on two heating
units in 1st floor mechanical room as discussed.
Light Ventilation per Room Safety Glazing YES
Attic Access 30 x 20 x 30 (h)YES Roof Access
Aug 21, 2018 Page (4)
INSPECTION WORKSHEET (MULT-006061-2018)
Checklist Item Passed Comments
Final Electrical YES
Site Plan / Variance required NO -Complete all site items and submit engineer's site
certification.
Final Survey Plot Plan NO -Submit the Final Survey
Public Sewer Sign-Off YES November 2017
Building/Apartment Num on Bldg or Driveway YES -Address at road
Bldg Access All Sides 20ft Drivable Surface YES
Handicapped Ramps YES
Handicapped Units YES
Engineer or Architect Approval YES -Submit final approval letter from Tom Joslin at
Construction Technologies
RECEIVED!
Aug 21, 2018 Page (5)
INSPECTION WORKSHEET (MULT-006061-2018)
Checklist Item Passed Comments
Okay To Issue Temp CO or Permanent CO YES 6/28/18 Final Inspection Not Approved-Temp Co
-See Dave Hatin's remaining items on his inspection
slip.
Note: Final Inspection 9:00 AM Friday for Temp CO!
6/30/18 Final Inspection Approved - Temporary CO
Conditions:
-Complete All Open Items
-Complete All Outstanding Fire Marshal's Items
-Complete All Outstanding
Site Items
NOTE: ALL LIFE SAFETY ITEMS HAVE BEEN
ADDRESSED!
7/3/18 Final inspection Partial Approval !
-Address at road
-Complete all site items.
-Submit the Final Survey
-Stripe handicapped parking spaces at south end exit.
-Complete all fire marshal's items.
7/5/18 Final Inspection Partial Approval
TEMPORARY CO APPROVED -OK TO OCCUPY
Conditions:
-Submit certified final survey
-Complete all remaining site items and submit
engineer's site certification.
-Complete all exterior caulking
-Submit As-Built Construction Plans
-Complete all remaining Fire Marshal's Items.
8/21/18 Final Inspection Not Approved
Temp CO is still active.
Remaining Items:
-Submit As-Built Construction Plans
-Submit certified final survey
-Complete all remaining site items and submit
engineer's site certification.
Aug 21, 2018 Page (6)
O'Brien, John (Inspector)
INSPECTION WORKSHEET (MULT-004730-2018)
Town of Queensbury - Building and Codes - Fire Marshal
742 Bay Road - (518) 761-8256 Building (518) 761-8206 Fire Marshal
Case Number:CC-000480-2017Case Module:Permit
Inspection Date:06/29/2018Inspection Status:Partial Pass
Inspector:John O'BrienInspection Type:Multi-Dwelling, Hotel, Motel Fin-
al
Job Address:524 AVIATION RDParcel Number:302.5-1-96.1
Queensbury, NY 12804
Contact TypeCompany NameName
Granted Permission\[Aviation Hospitality, LLC\]Jariwala, Bhavik
Primary Owner\[Aviation Hospitality, LLC\]Jariwala, Bhavik
Applicant\[Bast Hatfield Construction LLC\]Fretto, John
Contractor\[Bast Hatfield Construction LLC\]Fretto, John
Architect\[AIA Architect\],
Checklist ItemPassedComments
Jun 29, 2018Page (1)
INSPECTION WORKSHEET (MULT-004730-2018)
Checklist ItemPassedComments
Building Inspector NotesNO6/21/18 Preliminary Final Inspection Not Approved
-Install all interior signage and room numbers
-Adjust all corridor doors to rooms, stair towers and
bathroom doors. Corridor doors must self close and
latch.
-Complete final connections of all plumbing fixtures.
Also adjust drain stoppers for bathroom lavatories so
they drain freely some are draining very slow.
-Electrical Rooms on each floor has firestopping that
needs to be addressed. Specifically electrical conduits
and miscellaneous wire chases from floor to floor. Seal
all wall and ceiling penetrations as discussed.
-Seal gaps at laundry chute doors at each floor as
discussed.
-Seal up holes in 1st floor corridor walls on both sides at
south end of building. Need to verify before corridor
ceiling is closed up.
-Need to inspect elevator shaft to verify all penetrations
have been sealed.
-Final Electrical Inspection
-Blower Door Test
-HVAC Air Balancing Report
-Final approval letters from Architect, Engineer and the
Special Inspections Agency (Construction
Technologies).
-Submit all special inspections reports for soil
compaction, concrete testing, structural steel and
structural wood framing. These can be submitted on a
thumb drive.
-Submit a letter certifying that the building envelope.
Electrical and Mechanicals were installed in accordance
with the approved 2015 IECC COMcheck.
-Submit the Final Survey.
-Complete all site items. Separate inspection!
-Complete all fire marshal's items. Separate inspection!
-Complete parking lot striping and handicapped parking
and no parking signage.
6/26/18 Final Inspection 3rd & 4th Floors Not Approved
-Miscellaneous corridor and room doors need final
adjustments
6/28/18 Final Inspection Not Approved-Temp Co
-See Dave Hatin's remaining items on his inspection
slip.
Note: Final Inspection 9:00 AM Friday for Temp CO!
Chimney Height / B Vent / Direct Vent LocationYES
Plumb Vent Thru Roof Minimum 6YES
Outside Spigots have Air GapYES
Roof CompleteYES
Ext Finish /Grade Complete/6 in 10ft or EquivalentYES
Jun 29, 2018Page (2)
INSPECTION WORKSHEET (MULT-004730-2018)
Checklist ItemPassedComments
Interior/Exterior Railings 34 into 38 inchYES
Interior Handrails Stairs 1 or More RisersYES
Guardrails 42", Balusters 4 Minimum SpacingYES
Vestibules for Exit doors greater than 3000 sq. ftYES
Doors 36 Lever HandlesYES-Adjust all corridor doors to rooms, stair towers and
bathroom doors. Corridor doors must self close and
latch.
Headroom 6ft 8 on StairsYES
Bathroom / Kitchen WatertightYES
Low flow toilet 1.3 gal/flushing cycle -YES
showerhead/faucet
Safety glazing: w/in 5' of tub/shower - stairwell win/adj toYES
drs
Smoke Detectors 3' from Kitchens & Baths R314YES
Dryer Duct Max Length 35', Labeled Over 35'YES
Bathroom Fans Plumbing Fixtures CompleteNO-Complete final connections of all plumbing fixtures.
Also adjust drain stoppers for bathroom lavatories so
they drain freely some are draining very slow.
6/27/18 complete plumbing issues on second floor
Foundation InsulationYES
Bollard Protection: 15" footings & 3' below gradeYES
Bollard Protection:4' on ctr/3' abv grd, gas meterYES
Fire Separation, ¾, 1, 2 hr.NO-Electrical Rooms on each floor has firestopping that
needs to be addressed. Specifically electrical conduits,
miscellaneous wire chases from floor to floor. Seal all
wall and ceiling penetrations as discussed.
-Seal gaps at laundry chute doors at each floor as
discussed.
-Seal up holes in 1st floor corridor walls on both sides at
south end of building. Need to verify before corridor
ceiling is closed up.
-Seal electrical conduit sleeves at ceilings of each
electrical room
Fire Walls 1, 2, 3 Hour / Fire Door ¾, 1 ½, 2 HourYESElevator Chase
20 Minute Fire Door/Self-Closing HardwareYES-Adjust all corridor doors to rooms, stair towers and
bathroom doors. Corridor doors must self close and
latch.
H/C Accessibility Parking SignageNO-Stripe handicapped parking spaces at south end exit.
Universal Symbol of Access displayed - on all H/CYES
signs
Hydraulic Elevators: Non-comb. Plumbing REQUIREDYES
Jun 29, 2018Page (3)
INSPECTION WORKSHEET (MULT-004730-2018)
Checklist ItemPassedComments
Elevator Operation and Signage Shaft SealedYES-Need to inspect elevator shaft to verify all penetrations
have been sealed.
Gas Shut-off Exposed & Regulator (18) Above GradeYES
Furnace Hot Water Heater operatingYES
Low Water Shut-Off for BoilerYES
Blower Door Test CertificationNOTest failed needs to be redone.
Relief Valve ,Heat Trap/Water Temp 110 deg or lessYES-Relief Valve downspouts not installed on two heating
units in 1st floor mechanical room as discussed.
Light Ventilation per Room Safety GlazingYES
Attic Access 30 x 20 x 30 (h)YESRoof Access
Final ElectricalYES
Site Plan / Variance requiredNO-Complete all site items. Separate inspection!
Final Survey Plot PlanNO-Submit the Final Survey.qq
Public Sewer Sign-OffYESNovember 2017
Building/Apartment Num on Bldg or DrivewayNOAddress at road
Bldg Access All Sides 20ft Drivable SurfaceYES
Handicapped RampsYES
Handicapped UnitsYES
Engineer or Architect ApprovalYES-Submit final approval letter from Tom Joslin at
Construction Technologies
Okay To Issue Temp CO or Permanent COYES6/28/18 Final Inspection Not Approved-Temp Co
-See Dave Hatin's remaining items on his inspection
slip.
Note: Final Inspection 9:00 AM Friday for Temp CO!
6/30/18 Final Inspection Approved - Temporary CO
Conditions:
-Complete All Open Items
-Complete All Outstanding Fire Marshal's Items
-Complete All Outstanding
Site Items
NOTE: ALL LIFE SAFETY ITEMS HAVE BEEN
ADDRESSED!
O'Brien, John (Inspector)
Jun 29, 2018Page (4)
INSPECTION WORKSHEET (MULT-004689-2018)
Town of Queensbury - Building and Codes - Fire Marshal
742 Bay Road - (518) 761-8256 Building (518) 761-8206 Fire Marshal
Case Number:CC-000480-2017Case Module:Permit
Inspection Date:06/28/2018Inspection Status:Partial Pass
Inspector:John O'BrienInspection Type:Multi-Dwelling, Hotel, Motel Fin-
al
Job Address:524 AVIATION RDParcel Number:302.5-1-96.1
Queensbury, NY 12804
Contact TypeCompany NameName
Granted Permission\[Aviation Hospitality, LLC\]Jariwala, Bhavik
Primary Owner\[Aviation Hospitality, LLC\]Jariwala, Bhavik
Applicant\[Bast Hatfield Construction LLC\]Fretto, John
Architect\[AIA Architect\],
Contractor\[Bast Hatfield Construction LLC\]Fretto, John
Checklist ItemPassedComments
Jun 28, 2018Page (2)
INSPECTION WORKSHEET (MULT-004689-2018)
Checklist ItemPassedComments
Building Inspector NotesNO6/21/18 Preliminary Final Inspection Not Approved
-Install all interior signage and room numbers
-Adjust all corridor doors to rooms, stair towers and
bathroom doors. Corridor doors must self close and
latch.
-Complete final connections of all plumbing fixtures.
Also adjust drain stoppers for bathroom lavatories so
they drain freely some are draining very slow.
-Electrical Rooms on each floor has firestopping that
needs to be addressed. Specifically electrical conduits
and miscellaneous wire chases from floor to floor. Seal
all wall and ceiling penetrations as discussed.
-Seal gaps at laundry chute doors at each floor as
discussed.
-Seal up holes in 1st floor corridor walls on both sides at
south end of building. Need to verify before corridor
ceiling is closed up.
-Need to inspect elevator shaft to verify all penetrations
have been sealed.
-Final Electrical Inspection
-Blower Door Test
-HVAC Air Balancing Report
-Final approval letters from Architect, Engineer and the
Special Inspections Agency (Construction
Technologies).
-Submit all special inspections reports for soil
compaction, concrete testing, structural steel and
structural wood framing. These can be submitted on a
thumb drive.
-Submit a letter certifying that the building envelope.
Electrical and Mechanicals were installed in accordance
with the approved 2015 IECC COMcheck.
-Submit the Final Survey.
-Complete all site items. Separate inspection!
-Complete all fire marshal's items. Separate inspection!
-Complete parking lot striping and handicapped parking
and no parking signage.
6/26/18 Final Inspection 3rd & 4th Floors Not Approved
-Miscellaneous corridor and room doors need final
adjustments
6/28/18 Final Inspection Not Approved-Temp Co
-See Dave Hatin's remaining items on his inspection
slip.
Note: Final Inspection 9:00 AM Friday for Temp CO!
Chimney Height / B Vent / Direct Vent LocationYES
Plumb Vent Thru Roof Minimum 6YES
Outside Spigots have Air GapYES
Roof CompleteYES
Ext Finish /Grade Complete/6 in 10ft or EquivalentYES
Jun 28, 2018Page (3)
INSPECTION WORKSHEET (MULT-004689-2018)
Checklist ItemPassedComments
Interior/Exterior Railings 34 into 38 inchYES
Interior Handrails Stairs 1 or More RisersYES
Guardrails 42", Balusters 4 Minimum SpacingYES
Vestibules for Exit doors greater than 3000 sq. ftYES
Doors 36 Lever HandlesYES-Adjust all corridor doors to rooms, stair towers and
bathroom doors. Corridor doors must self close and
latch.
Headroom 6ft 8 on StairsYES
Bathroom / Kitchen WatertightYES
Low flow toilet 1.3 gal/flushing cycle -YES
showerhead/faucet
Safety glazing: w/in 5' of tub/shower - stairwell win/adj toYES
drs
Smoke Detectors 3' from Kitchens & Baths R314YES
Dryer Duct Max Length 35', Labeled Over 35'YES
Bathroom Fans Plumbing Fixtures CompleteNO-Complete final connections of all plumbing fixtures.
Also adjust drain stoppers for bathroom lavatories so
they drain freely some are draining very slow.
6/27/18 complete plumbing issues on second floor
Foundation InsulationYES
Bollard Protection: 15" footings & 3' below gradeYES
Bollard Protection:4' on ctr/3' abv grd, gas meterYES
Fire Separation, ¾, 1, 2 hr.NO-Electrical Rooms on each floor has firestopping that
needs to be addressed. Specifically electrical conduits,
miscellaneous wire chases from floor to floor. Seal all
wall and ceiling penetrations as discussed.
-Seal gaps at laundry chute doors at each floor as
discussed.
-Seal up holes in 1st floor corridor walls on both sides at
south end of building. Need to verify before corridor
ceiling is closed up.
-Seal electrical conduit sleeves at ceilings of each
electrical room
Fire Walls 1, 2, 3 Hour / Fire Door ¾, 1 ½, 2 HourYESElevator Chase
20 Minute Fire Door/Self-Closing HardwareYES-Adjust all corridor doors to rooms, stair towers and
bathroom doors. Corridor doors must self close and
latch.
H/C Accessibility Parking SignageNO-Stripe handicapped parking spaces at south end exit.
Universal Symbol of Access displayed - on all H/CYES
signs
Hydraulic Elevators: Non-comb. Plumbing REQUIREDYES
Jun 28, 2018Page (4)
INSPECTION WORKSHEET (MULT-004689-2018)
Checklist ItemPassedComments
Elevator Operation and Signage Shaft SealedYES-Need to inspect elevator shaft to verify all penetrations
have been sealed.
Gas Shut-off Exposed & Regulator (18) Above GradeYES
Furnace Hot Water Heater operatingYES
Low Water Shut-Off for BoilerYES
Blower Door Test CertificationNOTest failed needs to be redone.
Relief Valve ,Heat Trap/Water Temp 110 deg or lessYES-Relief Valve downspouts not installed on two heating
units in 1st floor mechanical room as discussed.
Light Ventilation per Room Safety GlazingYES
Attic Access 30 x 20 x 30 (h)YESRoof Access
Final ElectricalYES
Site Plan / Variance requiredNO-Complete all site items. Separate inspection!
Final Survey Plot PlanNO-Submit the Final Survey.
Public Sewer Sign-OffYESNovember 2017
Building/Apartment Num on Bldg or DrivewayNOAddress at road
Bldg Access All Sides 20ft Drivable SurfaceYES
Handicapped RampsYES
Handicapped UnitsYES
Engineer or Architect ApprovalNO-Submit final approval letter from Tom Joslin at
Construction Technologies
Okay To Issue Temp CO or Permanent CONO6/28/18 Final Inspection Not Approved-Temp Co
-See Dave Hatin's remaining items on his inspection
slip.
Note: Final Inspection 9:00 AM Friday for Temp CO!
O'Brien, John (Inspector)
Jun 28, 2018Page (5)
INSPECTION WORKSHEET (MULT-004410-2018)
Town of Queensbury - Building and Codes - Fire Marshal
742 Bay Road - (518) 761-8256 Building (518) 761-8206 Fire Marshal
Case Number:CC-000480-2017Case Module:Permit
Inspection Date:06/21/2018Inspection Status:Failed
Inspector:John O'BrienInspection Type:Multi-Dwelling, Hotel, Motel Fin-
al
Job Address:524 AVIATION RDParcel Number:302.5-1-96.1
Queensbury, NY 12804
Contact TypeCompany NameName
Granted Permission\[Aviation Hospitality, LLC\]Jariwala, Bhavik
Architect\[AIA Architect\],
Applicant\[Bast Hatfield Construction LLC\]Fretto, John
Primary Owner\[Aviation Hospitality, LLC\]Jariwala, Bhavik
Contractor\[Bast Hatfield Construction LLC\]Fretto, John
Checklist ItemPassedComments
Jun 21, 2018Page (1)
INSPECTION WORKSHEET (MULT-004410-2018)
Checklist ItemPassedComments
Building Inspector NotesNO6/21/18 Preliminary Final Inspection Not Approved
-Install all interior signage and room numbers
-Adjust all corridor doors to rooms, stair towers and
bathroom doors. Corridor doors must self close and
latch.
-Complete final connections of all plumbing fixtures.
Also adjust drain stoppers for bathroom lavatories so
they drain freely some are draining very slow.
-Electrical Rooms on each floor has firestopping that
needs to be addressed. Specifically electrical conduits
and miscellaneous wire chases from floor to floor. Seal
all wall and ceiling penetrations as discussed.
-Seal gaps at laundry chute doors at each floor as
discussed.
-Seal up holes in 1st floor corridor walls on both sides at
south end of building. Need to verify before corridor
ceiling is closed up.
-Need to inspect elevator shaft to verify all penetrations
have been sealed.
-Final Electrical Inspection
-Blower Door Test
-HVAC Air Balancing Report
-Final approval letters from Architect, Engineer and the
Special Inspections Agency (Construction
Technologies).
-Submit all special inspections reports for soil
compaction, concrete testing, structural steel and
structural wood framing. These can be submitted on a
thumb drive.
-Submit a letter certifying that the building envelope.
Electrical and Mechanicals were installed in accordance
with the approved 2015 IECC COMcheck.
-Submit the Final Survey.
-Complete all site items. Separate inspection!
-Complete all fire marshal's items. Separate inspection!
-Complete parking lot striping and handicapped parking
and no parking signage.
Chimney Height / B Vent / Direct Vent LocationNO
Plumb Vent Thru Roof Minimum 6YES
Outside Spigots have Air GapYES
Roof CompleteYES
Jun 21, 2018Page (2)
INSPECTION WORKSHEET (MULT-004410-2018)
Checklist ItemPassedComments
Ext Finish /Grade Complete/6 in 10ft or EquivalentYES
Interior/Exterior Railings 34 into 38 inchYES
Interior Handrails Stairs 1 or More RisersYES
Guardrails 42", Balusters 4 Minimum SpacingYES
Vestibules for Exit doors greater than 3000 sq. ftNO
Doors 36 Lever HandlesNO-Adjust all corridor doors to rooms, stair towers and
bathroom doors. Corridor doors must self close and
latch.
Headroom 6ft 8 on StairsYES
Bathroom / Kitchen WatertightYES
Low flow toilet 1.3 gal/flushing cycle -YES
showerhead/faucet
Safety glazing: w/in 5' of tub/shower - stairwell win/adj toYES
drs
Smoke Detectors 3' from Kitchens & Baths R314NO
Dryer Duct Max Length 35', Labeled Over 35'NO
Bathroom Fans Plumbing Fixtures CompleteNO-Complete final connections of all plumbing fixtures.
Also adjust drain stoppers for bathroom lavatories so
they drain freely some are draining very slow.
Foundation InsulationYES
Bollard Protection: 15" footings & 3' below gradeNO
Bollard Protection:4' on ctr/3' abv grd, gas meterNO
Fire Separation, ¾, 1, 2 hr.NO-Electrical Rooms on each floor has firestopping that
needs to be addressed. Specifically electrical conduits,
miscellaneous wire chases from floor to floor. Seal all
wall and ceiling penetrations as discussed.
-Seal gaps at laundry chute doors at each floor as
discussed.
-Seal up holes in 1st floor corridor walls on both sides at
south end of building. Need to verify before corridor
ceiling is closed up.
Fire Walls 1, 2, 3 Hour / Fire Door ¾, 1 ½, 2 HourNO
20 Minute Fire Door/Self-Closing HardwareNO-Adjust all corridor doors to rooms, stair towers and
bathroom doors. Corridor doors must self close and
latch.
H/C Accessibility Parking SignageNO
Universal Symbol of Access displayed - on all H/CNO
signs
Hydraulic Elevators: Non-comb. Plumbing REQUIREDNO
Hydraulic Elevators: Oil Seperator REQUIREDNO
Jun 21, 2018Page (3)
INSPECTION WORKSHEET (MULT-004410-2018)
Checklist ItemPassedComments
Elevator Operation and Signage Shaft SealedNO-Need to inspect elevator shaft to verify all penetrations
have been sealed.
Elevator Hoistways PressurizedNO
Gas Log In Sealed or Glass EnclosureNO
Gas Furn Shut-Off W/in 30 ft. or W/in Line SiteNO
Gas Shut-off Exposed & Regulator (18) Above GradeYES
Furnace Hot Water Heater operatingNO
Low Water Shut-Off for BoilerNO
Blower Door Test CertificationNO
Relief Valve ,Heat Trap/Water Temp 110 deg or lessNO-Relief Valve downspouts not installed on two heating
units in 1st floor mechanical room as discussed.
Light Ventilation per Room Safety GlazingYES
Attic Access 30 x 20 x 30 (h)YESRoof Access
Final ElectricalNO
Site Plan / Variance requiredNO-Complete all site items. Separate inspection!
Final Survey Plot PlanNO-Submit the Final Survey.
Public Sewer Sign-OffNO
Building/Apartment Num on Bldg or DrivewayNO
Bldg Access All Sides 20ft Drivable SurfaceYES
Handicapped RampsNO
Handicapped UnitsNO
Engineer or Architect ApprovalNO
Okay To Issue Temp CO or Permanent CONO
Okay To Issue CCNO
O'Brien, John (Inspector)
Jun 21, 2018Page (4)
INSPECTION WORKSHEET (MULT-000148-2019)
Town of Queensbury - Building and Codes - Fire Marshal
742 Bay Road - (518) 761-8256 Building (518) 761-8206 Fire Marshal
CC-000480-2017Permit
Case Number:Case Module:
Mon Jan 7, 2019Passed
Inspection Date:Inspection Status:
John O'BrienMulti-Dwelling, Hotel, Motel Final
Inspector:Inspection Type:
524 AVIATION RD302.5-1-96.1
Job Address:Parcel Number:
Queensbury, NY 12804
Contact TypeCompany NameName
Granted PermissionAviation Hospitality, LLCJariwala, Bhavik
ContractorBast Hatfield Construction LLCFretto, John
ApplicantBast Hatfield Construction LLCFretto, John
Primary OwnerAviation Hospitality, LLCJariwala, Bhavik
ArchitectAIA Architect
Checklist ItemPassedComments
Jan 07, 2019Page (1)
INSPECTION WORKSHEET (MULT-000148-2019)
Checklist ItemPassedComments
Building Inspector NotesYES6/21/18 Preliminary Final Inspection Not Approved
-Install all interior signage and room numbers
-Adjust all corridor doors to rooms, stair towers and bathroom
doors. Corridor doors must self close and latch.
-Complete final connections of all plumbing fixtures. Also
adjust drain stoppers for bathroom lavatories so they drain
freely some are draining very slow.
-Electrical Rooms on each floor has firestopping that needs
to be addressed. Specifically electrical conduits and
miscellaneous wire chases from floor to floor. Seal all wall
and ceiling penetrations as discussed.
-Seal gaps at laundry chute doors at each floor as discussed.
-Seal up holes in 1st floor corridor walls on both sides at
south end of building. Need to verify before corridor ceiling is
closed up.
-Need to inspect elevator shaft to verify all penetrations have
been sealed.
-Final Electrical Inspection
-Blower Door Test
-HVAC Air Balancing Report
-Final approval letters from Architect, Engineer and the
Special Inspections Agency (Construction Technologies).
-Submit all special inspections reports for soil compaction,
concrete testing, structural steel and structural wood framing.
These can be submitted on a thumb drive.
-Submit a letter certifying that the building envelope.
Electrical and Mechanicals were installed in accordance with
the approved 2015 IECC COMcheck.
-Submit the Final Survey.
-Complete all site items. Separate inspection!
-Complete all fire marshal's items. Separate inspection!
-Complete parking lot striping and handicapped parking and
no parking signage.
6/26/18 Final Inspection 3rd & 4th Floors Not Approved
-Miscellaneous corridor and room doors need final
adjustments
6/28/18 Final Inspection Not Approved-Temp Co
-See Dave Hatin's remaining items on his inspection slip.
Note: Final Inspection 9:00 AM Friday for Temp CO!
7/5/18 Final Inspection Partial Approval
TEMPORARY CO APPROVED -OK TO OCCUPY
Conditions:
-Submit certified final survey
-Complete all remaining site items and submit engineer's site
certification.
-Complete all exterior caulking
Jan 07, 2019Page (2)
INSPECTION WORKSHEET (MULT-000148-2019)
Checklist ItemPassedComments
-Submit As-Built Construction Plans
-Complete remaining Fire Marshal's Items.
Doors 36 Lever HandlesYES-Adjust all corridor doors to rooms, stair towers and bathroom
doors. Corridor doors must self close and latch.
Bathroom Fans Plumbing Fixtures CompleteYES-Complete final connections of all plumbing fixtures. Also
adjust drain stoppers for bathroom lavatories so they drain
freely some are draining very slow.
6/27/18 complete plumbing issues on second floor
Fire Separation, ¾, 1, 2 hr.YES-Electrical Rooms on each floor has firestopping that needs
to be addressed. Specifically electrical conduits,
miscellaneous wire chases from floor to floor. Seal all wall
and ceiling penetrations as discussed.
-Seal gaps at laundry chute doors at each floor as discussed.
-Seal up holes in 1st floor corridor walls on both sides at
south end of building. Need to verify before corridor ceiling is
closed up.
-Seal electrical conduit sleeves at ceilings of each electrical
room
Fire Walls 1, 2, 3 Hour / Fire Door ¾, 1 ½, 2 HourYESElevator Chase
20 Minute Fire Door/Self-Closing HardwareYES-Adjust all corridor doors to rooms, stair towers and bathroom
doors. Corridor doors must self close and latch.
H/C Accessibility Parking SignageYES-Stripe handicapped parking spaces at south end exit.
Elevator Operation and Signage Shaft SealedYES-Need to inspect elevator shaft to verify all penetrations have
been sealed.
Jan 07, 2019Page (3)
INSPECTION WORKSHEET (MULT-000148-2019)
Checklist ItemPassedComments
Blower Door Test CertificationYESTest failed needs to be redone.
BLOWER DOOR TEST RECEIVED AND PASSED.
Relief Valve ,Heat Trap/Water Temp 110 deg orYES-Relief Valve downspouts not installed on two heating units in
less1st floor mechanical room as discussed.
Attic Access 30 x 20 x 30 (h)YESRoof Access
Site Plan / Variance requiredYES-Complete all site items and submit engineer's site
certification.
Final Survey Plot PlanYES-Submit the Final Survey
Public Sewer Sign-OffYESNovember 2017
Building/Apartment Num on Bldg or DrivewayYES-Address at road
Engineer or Architect ApprovalYES-Submit final approval letter from Tom Joslin at Construction
Technologies
RECEIVED!
Jan 07, 2019Page (4)
INSPECTION WORKSHEET (MULT-000148-2019)
Checklist ItemPassedComments
Okay To Issue Temp CO or Permanent COYES6/28/18 Final Inspection Not Approved-Temp Co
-See Dave Hatin's remaining items on his inspection slip.
Note: Final Inspection 9:00 AM Friday for Temp CO!
6/30/18 Final Inspection Approved - Temporary CO
Conditions:
-Complete All Open Items
-Complete All Outstanding Fire Marshal's Items
-Complete All Outstanding
Site Items
NOTE: ALL LIFE SAFETY ITEMS HAVE BEEN
ADDRESSED!
7/3/18 Final inspection Partial Approval !
-Address at road
-Complete all site items.
-Submit the Final Survey
-Stripe handicapped parking spaces at south end exit.
-Complete all fire marshal's items.
7/5/18 Final Inspection Partial Approval
TEMPORARY CO APPROVED -OK TO OCCUPY
Conditions:
-Submit certified final survey
-Complete all remaining site items and submit engineer's site
certification.
-Complete all exterior caulking
-Submit As-Built Construction Plans
-Complete all remaining Fire Marshal's Items.
8/21/18 Final Inspection Not Approved
Temp CO is still active.
Remaining Items:
-Submit As-Built Construction Plans
-Submit certified final survey
-Complete all remaining site items and submit engineer's site
certification.
1/7/19 Final Inspection Approved - Ok to Issue CO!
O'Brien, John (Inspector)
Jan 07, 2019Page (5)