Signed Inspection Report (03-09-2020).pdfINSPECTION WORKSHEET (RPLUM-001210-2020)
Town of Queensbury - Building and Codes - Fire Marshal
742 Bay Road - (518) 761-8256 Building (518) 761-8206 Fire Marshal
Case Number:RC-0625-2018 Case Module:Permit
Inspection Date:Mon Mar 9, 2020 Inspection Status:Failed
Inspector:Mark Smith Inspection Type:Rough Plumbing
Job Address:Parcel Number:154 CLEVERDALE RD
Queensbury, NY, 12804
227.17-2-30
Contact Type Company Name Name
Architect McLaughlin, Tim
Concrete Contractor R. C. Springer Concrete
Contractor Stonewood Development of
Northeastern NY Inc
Applicant HOFFMAN, JEAN
Granted Permission HOFFMAN, JEAN
Framing Contractor Top Notch Builders
Primary Owner Stonewood Development of
Northeastern NY Inc
Engineer Environmental Design Partnership, LLC
Checklist Item Status
Building Inspector Notes Failed
3/9/20 rough plumbing not approved:
All connections and fittings for sanitary piping must be made at time of inspection. 3" vent must be through the
roof, or install dandy T type fitting so the connection can be verified at a later date. Sanitary lines should be
capped outside the foundation, or install dandy T type fitting so the connection can be verified at a later date. All
tub traps need to be in place at time of inspection. All connections from foundation to roof should be installed and
pressurized at time of inspection.
Supply piping connections must be completed before inspection. All shower valves and fittings should be
completed at time of inspection. 65 psi for 15 minutes.
Mar 09, 2020 Page (1)
INSPECTION WORKSHEET (RPLUM-001210-2020)
Checklist Item Status
Plumbing Under Slab Failed
Rough Plumbing / Nail Plates Failed
Plumbing Vent Vents in Place Failed
3" Vent Through Roof Failed
1 ½ inch minimum Drain Size Failed
Shower liner test (2" of water)Failed
Washing Machine Drain 2 inch minimum Failed
Washing Machine Trap: 18"-42" discharge Failed
Cleanout every 100 feet change of direction Failed
Pressure Test Failed
Drain Vent Failed
Air Head Failed
Mar 09, 2020 Page (2)
INSPECTION WORKSHEET (RPLUM-001210-2020)
Checklist Item Status
5 psi or 10 ft. above highest conn. for 15 minutes Failed
Pressure Test Failed
Water Supply Piping Failed
Air Head Failed
50 P.S.I for 15 minutes Failed
Air Test Gas Piping 10 psi for 10 Minutes Failed
All Return Air Hard Duct Work Failed
Duct Insulation - if required in unheated spaces Failed
Duct Testing Outside Conditioned Space Failed
Duct work sealed properly Failed
Mar 09, 2020 Page (3)
Smith, Mark