Signed Inspection Report (06-15-2020) (22).pdfINSPECTION WORKSHEET (COMFIN-002684-2020)
Town of Queensbury - Building and Codes - Fire Marshal
742 Bay Road - (518) 761-8256 Building (518) 761-8206 Fire Marshal
Case Number:CC-0675-2019 Case Module:Permit
Inspection Date:Mon Jun 15, 2020 Inspection Status:Partial Pass
Inspector:O'Brien, John Inspection Type:Commercial Final Inspection
Job Address:Parcel Number:578 AVIATION RD
Queensbury, NY, 12804
302.5-1-92.12
Contact Type Company Name Name
Primary Owner Target Corporation
Applicant Target Corporation
Architect Sargenti Architects
Granted Permission Target Corporation
Contractor Groom Construction
Checklist Item Status
Building Inspector Notes Passed
4/10/20 Final Inspection Not Approved
- Customer Bathrooms
Remaining Items:
- Install 18" grab bars in handicapped stalls of all 3 bathrooms as per plan.
- Provide proof of Final Electrical Inspection for Customer Bathrooms
- Install handicapped bathroom signage for all three bathrooms.
Note: I will reinspect on Monday 4/13/20 at 9:00 am.
4/13/20 Final Inspection Partial Approval
- Customer Bathrooms Final Inspection Approved
Note: Ok to occupy customer bathrooms all other work remains under ban of non-essential work.
5/11/20 Final Inspection Partial Approval - Ok to occupy and open Guest Services.
- Final Electrical for Guest Services approved.
6/15/20 Final Inspection Partial Approval
Remaining Items:
- Planning and Zoning Final Inspection(Bruce Frank)
Jun 15, 2020 Page (1)
INSPECTION WORKSHEET (COMFIN-002684-2020)
Checklist Item Status
- Verification that fire alarm system is tied into HVAC Unit on roof.
Final Electrical / Flex Gas Piping Bonded Passed
- Customer Bathrooms Only!
6/15/20 Final Electrical Inspection Approved for balance of alterations.
Special Inspections Passed
Received Air Balancing Report for HVAC System.
OK to Issue Temporary C/O Passed
4/10/20 Final Inspection Not Approved
- Customer Bathrooms
Remaining Items:
- Install 18" grab bars in handicapped stalls of all 3 bathrooms as per plan.
- Provide proof of Final Electrical Inspection for Customer Bathrooms
- Install handicapped bathroom signage for all three bathrooms.
Note: I will reinspect on Monday 4/13/20 at 9:00 am.
4/13/20 Final Inspection Partial Approval
- Customer Bathrooms Final Inspection Approved
Note: Ok to occupy customer bathrooms all other work remains under ban of non-essential work.
5/11/20 Final Inspection Partial Approval - Ok to occupy and open Guest Services.
- Final Electrical for Guest Services approved.
6/15/20 Final Inspection Partial Approval
Remaining Items:
- Planning and Zoning Final Inspection(Bruce Frank)
- Verification that fire alarm system is tied into HVAC Unit on roof.
Jun 15, 2020 Page (2)
INSPECTION WORKSHEET (COMFIN-002684-2020)
Checklist Item Status
OK to Issue C/O Failed
4/10/20 Final Inspection Not Approved
- Customer Bathrooms
Remaining Items:
- Install 18" grab bars in handicapped stalls of all 3 bathrooms as per plan.
- Provide proof of Final Electrical Inspection for Customer Bathrooms
- Install handicapped bathroom signage for all three bathrooms.
Note: I will reinspect on Monday 4/13/20 at 9:00 am.
5/11/20 Final Inspection Partial Approval - Ok to occupy and open Guest Services.
- Final Electrical for Guest Services approved.
6/15/20 Final Inspection Partial Approval
Remaining Items:
- Planning and Zoning Final Inspection(Bruce Frank)
- Verification that fire alarm system is tied into HVAC Unit on roof.
Jun 15, 2020 Page (3)
O'Brien, John