SRA Field Observation Report 2Evergreen Professional Park
453 Dixon Road, Ste. 7, Bldg. 3
Queensbury, NY 12804
Tel. (518) 761-0417
Fax (518) 761-0513
DATE of VISIT: 7-17-20
PROJECT: South Queensbury Fire Department – Storage Building
PROJECT NO.: 18-389
WEATHER: Cloudy 70’s
PRESENT ON SITE: Shaun M. Rivers - Schoder Rivers
Kevin Guilfoyle - Ridgewood Homes Inc.
FIELD OBSERVATION REPORT NO. 2
ITEM
NO.
OBSERVATION
ACTION TO BE TAKEN (BOLD TYPE)
DATE
COMPLETED
1.Rough framing is pretty much complete. Walls and roof are sheathed.
Truss tie downs are installed. Modified fly rafter detail was installed.
Remaining items are noted below and were reviewed with Kevin.
NA
2.The two overhead door openings only have single king studs instead of
the two specified.Talked to Kevin about this and this was being
corrected as I left.
Completed 7-14.
3.The gable end wall bracing at the approximate ¼ points of the wall length
were not installed. The center bracing was installed. The bracing at the
¼ points does not require a strongback since it is shorter.Install the
bracing at these locations per the detail on Drawing S-2.
4.The two hold-downs at the north shear wall need to be installed.
5.The web bracing installed on the two center truss diagonals need to be
terminated.Install two diagonal 2x6’s equally spaced at each
location per the Typical Diagonal Bracing Detail to Stabilize Truss
Compression Members on Drawing S-3.
Distribution: Via Email:
John O’Brien – Town of Queensbury
Marcus Young – Rozell Industries