engineer's report SCHODER RIVERS Evergreen Professional Park
453 Dixon Road, Ste. 7, Bldg. 3
ASSOCIATES Queensbury, NY 12804
Consulting Engineers, P.C. Tel. (518) 761 -0417
Fax (518) 761-0513
DATE of VISIT: 7-21-20 with Follow Up 7-28-20
PROJECT: South Queensbury Fire Department—Storage Building and Pavilion
PROJECT NO.: 18-389
WEATHER: Sunny 80's 7-21
Rain Cloudy 70's 7-28
PRESENT ON SITE: Shaun M. Rivers- Schoder Rivers
iv \�
rVTR ��IO - Z_UZI
FIELD OBSERVATION REPORT NO. 3
ITEM OBSERVATION DATE
NO. ACTION TO BE TAKEN (BOLD TYPE) COMPLETED
1. Rough framing is complete. NA
2. The two overhead door openings only have single king studs instead of Completed 7-14.
the two specified. Talked to Kevin about this and this was being
corrected as I left.
3. The gable end wall bracing at the approximate 'A points of the wall length Completed 7-21.
were not installed. The center bracing was installed. The bracing at the
'/<points does not require a strongback since it is shorter. Install the
bracing at these locations per the detail on Drawing S-2.
4. The two hold-downs at the north shear wall need to be installed. Completed 7-21
5. The web bracing installed on the two center truss diagonals need to be Completed 7-28
terminated. Install two diagonal 2x6's equally spaced at each
location per the Typical Diagonal Bracing Detail to Stabilize Truss
Compression Members on Drawing S-3.
6. All Items pertaining to the Storage Building framing are complete and
erected per the Structural Plans.
7. Pavilion column splice details were reviewed. These have been installed
per the Structural Plans.
Distribution: Via Email:
John O'Brien—Town of Queensbury
Marcus Young—Rozell Industries
John Harrington—South Queensbury Fire Department