as built ENVIRONMENTAL DESIGN
PARTNERSHIP, LLP. 900 Route 146 Clifton Park,NY 12065
(P)518.371.7621 (F)518.371.9540 edplip.com
Shaping the physical environment
June 18, 2020
DE
G 1E0I
Town of Queensbury Building&Codes
742 Bay Road J rr-
UN 13 20
Queensbury, NY 12804 ___
Attn: Dave Hatin TOWN OF OUEE_N
BUILDING&
Re: Freihofer JMason)-Residence Wastewater—300 Cleverdale Road.
Dear Dave:
In compliance with application approvals granted by the Town of Queensbury I offer the following
regarding the referenced project. As you are aware the Mason residence transferred to the
ownership of the Freihofer family after the permit was issued.
The design plans, prepared by this office and reviewed and approved by the Town as associated
with the wastewater system application,are as follows:
Proposed Wastewater Improvements For The Mason Residence
• Sheet S-1 Cover Sheet AS 7
LT
Sheet S-2 Existing Conditions a'
Sheet W-3 Wastewater Variance Plan
• Sheet W-4 Wastewater Details
Dated:April 30, 2019
During the course of construction I was on the job site to observe key components of the system
installation culminating with the start-up/programming of the pump assembly and control panel
system on June 18,2020. The field location of the septic tank, pump tank,the wastewater
absorption system and D-Box have been installed as per the approved design plan so no further`As-
built' plan is provided. I have provided a print of the Design Plan marked as `As-Built'for your file.
Based on my inspection of the system start-up it is my opinion that the wastewater system is in
compliance with the intent of the approved design plan and is ready for operation.
Sincerely,
Dennis MacElroy, PE
cc:Al Freihofer