JB201133.0062.Reinforcing Steel Observations.2021-01-05.Rpt.0062REINFORCING STEEL OBSERVATIONS REPORT
Report Number:JB201133.0062
Service Date:01/05/21 30 Corporate Cir Ste 201
Report Date:01/07/21 Albany, NY 12203-5169
518-266-0310
Client Project
Rosetti Acquisitions LLC Fowler Square SI and CMT
Attn: Christopher Falvey Bay Road and Blind Rock Road
427 New Karner Rd Queensbury, NY 12804
Albany, NY 12205
Project Number: JB201133
Services: Observe the placement of reinficing steel and/or embedded elements as requested in general accordance with project
specifications and/or client request(s).
Dente Group - A Terracon Co. Rep.: Bryan Smith
Reported To:Bobby w/ BBL & Galusha Reps
Contractor:
Report Distribution:
(1) Rosetti Acquisitions LLC, Christopher
Falvey
(1) 260 Structural Engineering, Dan
Thomas(1) BBL Construction Services, Eric
Weatherwax
(1) BBL Construction Services, Ryan Etue Reviewed By:____________________________________
(1) BBL Construction Services, Scott
Lounsbury
(1) Galusha & Sons LLC, Drew Stevens M. McHenry
(1) Galusha & Sons LLC, James
Campagnone
Materials Department Manager
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to
the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
CT0001, 10-16-13, Rev.10 Page 1 of 1
☐ SPREAD FOUNDATION ☐ GRADE BEAM
☐ FOUNDATION WALL ☐ STRUCTURAL SLAB
☐ CLASSIFICATION ☒ OTHER Exterior Piers
REFERENCE DRAWINGS S-1
LOCATION Piers at points (15.5,T.5), (16.2,T.5), (16.66,T.5), (17.66,T.2), (18.1,T.2), (18.5,T.2), (16.75,E), (17.2,E),
(17.5,E), (18.5,E), and (19,E)
☒ REQUIRED BAR SIZE
☒ REQUIRED GRADE STEEL
☒ REQUIRED BAR SPACING
☒ REQUIRED BAR CLEARANCE
☒ REQUIRED SPLICES
☒ CONFORMS TO DRAWING
☐ DOES NOT CONFORM
☐ REMARKS
Photo No. 1 Pier located on the east side of the structure,
that was poured on this date.Photo No. 2
One of the exterior piers located on the west
side of the structure, that was poured on this
date.
Photo No. 3 The detail for “Type F” Piers, which
encompasses all the piers poured on this date.
Rosetti Acquisitions LLC Project Number:JB201133
Attn: Christopher Falvey Report Number: JB201133.0062
427 New Karner Rd Technician: Bryan Smith 30 Corporate Cir Ste 201
Albany, NY 12205 Date: 01/05/21 Albany, NY 12203-5169
Scale: Not to Scale 518-266-0310