Signed Inspection Report (Fri Jan 8, 2021 at 1103 AM)INSPECTION WORKSHEET (FDTN-007564-2021)
Town of Queensbury - Building and Codes - Fire Marshal
742 Bay Road - (518) 761-8256 Building (518) 761-8206 Fire Marshal
Case Number:CC-0621-2020 Case Module:Permit
Inspection Date:Fri Jan 8, 2021 Inspection Status:Partial Pass
Inspector:O'Brien, John Inspection Type:Building Foundation
Job Address:Parcel Number:719 BAY RD
Queensbury, NY, 12804
289.19-1-27
Contact Type Company Name Name
Applicant BBL Construction Services
Primary Owner Rosetti Acquisitions LLC
Granted Permission BBL Construction Services
Contractor BBL Construction Services
Architect HCP Architects, LLP
Checklist Item Status
Jan 08, 2021 Page (1)
INSPECTION WORKSHEET (FDTN-007564-2021)
Checklist Item Status
Building Inspector Notes Failed
10/26/20 recieved compaction tests
11/24/20 Footing Partial Approval
T-17 to C-11
12/2/20 Footings Partial Approval - West Elevation from C-11 to stair tower 1 to North of elevator at G16.
12/9/20 Foundation Partial Approval
- Foundation Walls partial approval from F12.5 to T4.5, Elevator #1 and Stair #1.
- Footings Partial Approval from T16 to T29
12/11/20 Foundation Partial Approval
- Foundation Insulation installed from H3 to D9
- Backfill Partial Approval from H3 to D9
12/16/20 Foundation Partial Approval
- Foundation Walls T5 - T19
- Footings T25 - B38
12/16/20 Foundation Partial Approval
- Foundation Insulation D9 - T18
- Backfill D9 - T18
12/18/20 Foundation Partial Approval
- Footings G16 - F24
12/23/20 Foundation Partial Approval
- 8 interior footings at south end of building approved
- First Floor Stair #1 masonry block partial approval( Vertical bars 4-#7s in corners, vertical #4s at 48" oc and #4s
@ 16" oc at shear wall
12/29/20 Foundation Partial Approval
- East Foundation Wall
- West Foundation Wall
- Masonry Wall Bond Beam and Vertical Bar.
Verticals reinforcing in place bond beam reinforcing not in place Terracon on site to witness placement and
concrete grout testing.
12/30/20 Foundation Partial Approval
- West Foundation Wall F12.5 to F21 Foundation Insulation. Ok to backfill!
1/6/21 Foundation Partial Approval
- 2nd Floor Stair #1 masonry block partial approval( Vertical bars 4-#7s in corners, vertical #4s at 48" oc and #4s
@ 16" oc at shear wall
Jan 08, 2021 Page (2)
INSPECTION WORKSHEET (FDTN-007564-2021)
Checklist Item Status
1/8/21 Foundation Partial Approval
- Balance of East Foundation Walls and 12' of North Foundation Walls from NE Corner Approved
Footings Passed
11/24/20 Footing Partial Approval
T-17 to C-11
12/2/20 Footings Partial Approval
12/2/20 Footings Partial Approval - West Elevation from C-11 to stair tower 1 to North of elevator at G16.
12/9/20 Foundation Partial Approval
- Footings Partial Approval from T16 to T29
12/16/20 Foundation Partial Approval
- Foundation Walls T5 - T19
- Footings T25 - B38
12/18/20 Foundation Partial Approval
- Footings G16 - F24
12/23/20 Foundation Partial Approval
- 8 interior footings at south end of building approved
- First Floor Stair #1 masonry block partial approval( Vertical bars 4-#7s in corners, vertical #4s at 16" oc and #4s
@ 48" oc at shear wall
12/31/20 Foundation Partial Approval
- Interior Column and Pier Footings at lines R and K 12-20.
Piers Passed
1/4/21 porch piers front and rear of building
Rebar per plans 6 front and 5 rear
Monolithic Slab Failed
Jan 08, 2021 Page (3)
INSPECTION WORKSHEET (FDTN-007564-2021)
Checklist Item Status
Reinforcement in Place Passed
11/24/20 Footing Partial Approval
T-17 to C-11
12/2/20 Footings Partial Approval - West Elevation from C-11 to stair tower 1 to North of elevator at G16.
12/9/20 Foundation Partial Approval
- Footings Partial Approval fromT16 to T29
12/16/20 Foundation Partial Approval
- Foundation Walls T5 - T19
- Footings T25 - B38
12/18/20 Foundation Partial Approval
- Footings G16 - F24
12/23/20 Foundation Partial Approval
- 8 interior footings at south end of building approved
- First Floor Stair #1 masonry block partial approval( Vertical bars 4-#7s in corners, vertical #4s at 16" oc and #4s
@ 48" oc at shear wall
12/31/20 Foundation Partial Approval
- Interior Column and Pier Footings at lines R and K 12-20.
Foundation / Wallpour Passed
12/9/20 Foundation Partial Approval
- Foundation Walls partial approval from F12.5 to T4.5, Elevator #1 and Stair #1.
12/16/20 Foundation Partial Approval
- Foundation Walls T5 - T19
- Footings T25 - B38
12/29/20 Foundation Partial Approval
- East Foundation Wall T19 to T22
- West Foundation Wall F12.5 to F21
- Masonry Wall Bond Beam and Vertical Bar.
Verticals reinforcing in place bond beam reinforcing not in place Terracon on site to witness placement and
concrete grout testing.
1/8/21 Foundation Partial Approval
- Balance of East Foundation Walls and 12' of North Foundation Walls from NE Corner Approved
Jan 08, 2021 Page (4)
INSPECTION WORKSHEET (FDTN-007564-2021)
Checklist Item Status
Reinforcement in Place Passed
12/9/20 Foundation Partial Approval
- Foundation Walls partial approval from F12.5 to T4.5, Elevator #1 and Stair #1.
12/16/20 Foundation Partial Approval
- Foundation Walls T5 - T19
- Footings T25 - B38
12/29/20 Foundation Partial Approval
- East Foundation Wall T19 to T22
- West Foundation Wall F12.5 to F21
- Masonry Wall Bond Beam and Vertical Bar.
Verticals reinforcing in place bond beam reinforcing not in place Terracon on site to witness placement and
concrete grout testing.
1/8/21 Foundation Partial Approval
- Balance of East Foundation Walls and 12' of North Foundation Walls from NE Corner Approved
Masonry Wall Passed
12/23/20 Foundation Partial Approval
- First Floor Stair #1 masonry block partial approval( Vertical bars 4-#7s in corners, vertical #4s at 48" oc and #4s
@ 16" oc at shear wall
12/29/20 Foundation Partial Approval
- Masonry Wall Bond Beam and Vertical Bar.
Verticals reinforcing in place bond beam reinforcing not in place Terracon on site to witness placement and
concrete grout testing.
1/6/21 Foundation Partial Approval
- 2nd Floor Stair #1 masonry block partial approval( Vertical bars 4-#7s in corners, vertical #4s at 48" oc and #4s
@ 16" oc at shear wall
- Dente on site verifying masonry vertical reinforcing, bond beam reinforcing and testing mortar and grout.
Jan 08, 2021 Page (5)
INSPECTION WORKSHEET (FDTN-007564-2021)
Checklist Item Status
Reinforcement in Place Passed
12/23/20 Foundation Partial Approval
- First Floor Stair #1 masonry block partial approval( Vertical bars 4-#7s in corners, vertical #4s at 48" oc and #4s
@ 16" oc at shear wall
12/29/20 Foundation Partial Approval
- Masonry Wall Bond Beam and Vertical Bar.
Verticals reinforcing in place bond beam reinforcing not in place Terracon on site to witness placement and
concrete grout testing.
1/6/21 Foundation Partial Approval
- 2nd Floor Stair #1 masonry block partial approval( Vertical bars 4-#7s in corners, vertical #4s at 48" oc and #4s
@ 16" oc at shear wall
- Dente on site verifying masonry vertical reinforcing, bond beam reinforcing and testing mortar and grout.
Footing Dowels or Keyway in place Passed
11/24/20 Footing Partial Approval
T-17 to C-11
12/2/20 Footings Partial Approval - West Elevation from C-11 to stair tower 1 to North of elevator at G16.
12/9/20 - Footings Partial Approval fromT16 to T29
12/16/20 Foundation Partial Approval
- Foundation Walls T5 - T19
- Footings T25 - B38
12/18/20 Foundation Partial Approval
- Footings G16 - F24
Foundation Dampproofing Failed
Jan 08, 2021 Page (6)
INSPECTION WORKSHEET (FDTN-007564-2021)
Checklist Item Status
Foundation Waterproofing Failed
Footing Drain Daylight or Sump Failed
Footing Drain Stone - 12 inch width Failed
Footing Drain Stone - 6 inches above footing Failed
Footing Drain stone - 6 mil poly Failed
Backfill Approval Passed
12/11/20 Foundation Partial Approval
- Foundation Insulation installed from H3 to D9
- Backfill Partial Approval from H3 to D9
12/16/20 Foundation Partial Approval
- Foundation Insulation D9 - T18
- Backfill D9 - T18
12/30/20 Foundation Partial Approval
- West Foundation Wall F12.5 to F21 Foundation Insulation. Ok to backfill!
Plumbing Under Slab Failed
PVC / Cast / Copper Failed
Jan 08, 2021 Page (7)
INSPECTION WORKSHEET (FDTN-007564-2021)
Checklist Item Status
Foundation Insulation Interior / Exterior Passed
12/11/20 Foundation Partial Approval
- Foundation Insulation installed from H3 to D9
- Backfill Partial Approval from H3 to D9
12/16/20 Foundation Partial Approval
- Foundation Insulation D9 - T18
- Backfill D9 - T18
12/30/20 Foundation Partial Approval
- West Foundation Wall F12.5 to F21 Foundation Insulation. Ok to backfill!
Rough Grade 6 inch drop within 10 ft.Failed
Poly Under Slab Failed
Jan 08, 2021 Page (8)
O'Brien, John