JB201133.0109.Masonry Observations.2021-02-17.Rpt.0109MASONRY OBSERVATIONS REPORT
Report Number:JB201133.0109
Service Date:02/17/21 30 Corporate Cir Ste 201
Report Date:02/19/21 Albany, NY 12203-5169
518-266-0310
Client Project
Rosetti Acquisitions LLC Fowler Square SI and CMT
Attn: Christopher Falvey Bay Road and Blind Rock Road
427 New Karner Rd Queensbury, NY 12804
Albany, NY 12205
Project Number: JB201133
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to
the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
CT0001, 6-30-11, Rev.9 Page 1 of 3
DOCUMENTS USED FOR INSPECTION: Structural, Bearing Shop.
LOCATION OF THE WORK PERFORMED: Mixed Use Bldg. Stair 3 CMU walls.
REMARKS: The contractor was laying course 5 at North, East and West walls, course 3 at South wall. A small
amount of cantilever to the inside of the structure was observed at East and (North portion) of West wall (shear
wall); about 0.25” where observed. SOG placement will likely be supporting the small amount of cantilever when
the floor is placed. Mortar was sampled for compressive strength testing, see report.
☒ CONFORMANCE STATEMENT: Based on our observations, masonry construction activities at the above referenced
locations appeared to be in general conformance with the project plans and specifications.
☐ WITH THE FOLLOWING EXCEPTIONS:
A. MATERIAL VERIFICATION General
Conformance
Non-
Conformance
N/A
1. Verify the use of approved CMU Block: Type, Size ☐☐☐
2. Verify the mortar type and strength ☐☐☐
3. Verify the reinforcing steel size and grade ☐☐☐
4. Verify the type and gauge of horizontal joint reinforcement ☐☐☐
REMARKS: Same materials in use as previously observed and reported.
B. WORKMANSHIP General
Conformance
Non-
Conformance
N/A
1. Verify the webs containing grout are confined by mortar ☒☐☐
2. Verify the horizontal and vertical joint thickness conforms to 3/8” ± 1/8”☒☐☐
3. Verify the mortar consistency, mixing, and working time ☐☐☐
4. Verify the cover for horizontal joint reinforcement in the mortar bed ☒☐☐
REMARKS: Where observed.
MASONRY OBSERVATIONS REPORT
Report Number:JB201133.0109
Service Date:02/17/21 30 Corporate Cir Ste 201
Report Date:02/19/21 Albany, NY 12203-5169
518-266-0310
Client Project
Rosetti Acquisitions LLC Fowler Square SI and CMT
Attn: Christopher Falvey Bay Road and Blind Rock Road
427 New Karner Rd Queensbury, NY 12804
Albany, NY 12205
Project Number: JB201133
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to
the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
CT0001, 6-30-11, Rev.9 Page 2 of 3
C. GROUTING General
Conformance
Non-
Conformance
N/A
1. Verify that cores containing reinforcement are clean and free from debris ☒☐☐
2. Verify the spacing of vertical reinforcement and location in the cell ☒☐☐
3. Verify low lift grouting height ☐☐☐
4. Check for the presence of clean out if high lift grouting is being used ☐☐☐
5. Grout consolidated using vibratory methods ☐☐☐
6. Verify the slump of grout is between 8 and 11 inches ☐☐☐
REMARKS: Where observed. No grouting during site visit.
D. COLD WEATHER REQUIREMENTS General
Conformance
Non-
Conformance
N/A
1.Verify /measure the CMU's temperature and condition ☒☐☐
2.Verify that the mortar temperature is between 40 F and 120 F ☒☐☐
3. Verify that the grout temperature is minimum of 70F at the time of placement if the
ambient temperature in enclosure is below 32F ☐☐☒
4.Check protection arrangements for installed masonry and grout ☒☐☐
REMARKS: Work was enclosed and external heat sources were running.
MASONRY OBSERVATIONS REPORT
Report Number:JB201133.0109
Service Date:02/17/21 30 Corporate Cir Ste 201
Report Date:02/19/21 Albany, NY 12203-5169
518-266-0310
Client Project
Rosetti Acquisitions LLC Fowler Square SI and CMT
Attn: Christopher Falvey Bay Road and Blind Rock Road
427 New Karner Rd Queensbury, NY 12804
Albany, NY 12205
Project Number: JB201133
Services: Observe masonry construction activities as requested in general accordance with project specifications and/or client
request(s).
Dente Group - A Terracon Co. Rep.: J. Canonico
Reported To:BBL Superintendent
Contractor:BBL
Report Distribution:
(1) Rosetti Acquisitions LLC, Christopher
Falvey
(1) 260 Structural Engineering, Dan
Thomas(1) BBL Construction Services, Bobby
Chatterton
(1) BBL Construction Services, Eric
Weatherwax Reviewed By:____________________________________
(1) BBL Construction Services, Ryan Etue (1) Galusha & Sons LLC, Drew Stevens Jared Hall
(1) Galusha & Sons LLC, James
Campagnone
Staff Geologist
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to
the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
CT0001, 6-30-11, Rev.9 Page 3 of 3
E. MORTAR/GROUT TESTING General
Conformance
Non-
Conformance
N/A
1. Was mortar testing performed? (YES): Select Y/N.☒☐☐
2. Indicate number of sample cubes and temperature at point of placement:
Number = 6 Temperature = 44 F.
☒☐☐
3. Was grout testing performed? (NO): Select Y/N.☐☐☒
4. Indicate number of grout prisms and temperature at point of placement:
Number = Temperature =
☐☐☒
5. Slump of grout at point of placement in inches:☐☐☒
6. Forecasted mean temperature for 24 hours (F):☐☐☐
7. Ambient air temperature (F): 17 out/48 inside ☒☐☐
REMARKS: See mortar test report.