Signed Inspection Report (Fri Jan 29, 2021 at 929 AM)INSPECTION WORKSHEET (RPLUM-007976-2021)
Town of Queensbury - Building and Codes - Fire Marshal
742 Bay Road - (518) 761-8256 Building (518) 761-8206 Fire Marshal
Case Number:CC-0793-2020 Case Module:Permit
Inspection Date:Fri Jan 29, 2021 Inspection Status:Partial Pass
Inspector:Dyer, Charles Inspection Type:Rough Plumbing
Job Address:Parcel Number:75 CAREY RD
Queensbury, NY, 12804
308.20-1-3.3
Contact Type Company Name Name
Engineer Bergeron, Mark
Applicant O'Connor, Mike
Granted Permission Alltek Energy Systems Inc
Primary Owner Okie Properties, LLC
Contractor Alltek Energy Systems Inc
Checklist Item Status
Building Inspector Notes Failed
1/15/21 Plumbing Under Slab Partial Approval
- The new location of the handicapped bathroom and laundry drain is approved
- An infloor oil separator will be required due to the installation of trench drains at the original location of the
handicapped bathroom.
Once the oil separator is installed call for inspection and also send the specifications on the unit to be installed
Plumbing Under Slab Passed
1/15/21 Plumbing Under Slab Partial Approval
- The new location of the handicapped bathroom and laundry drain is approved
- An infloor oil separator will be required due to the installation of trench drains at the original location of the
handicapped bathroom.
Once the oil separator is installed call for inspection and also send the specifications on the unit to be installed.
1/29/21 verified trench drains/oil separator, provide specifications as noted from previous inspection.
Rough Plumbing / Nail Plates Failed
Jan 29, 2021 Page (1)
INSPECTION WORKSHEET (RPLUM-007976-2021)
Checklist Item Status
Plumbing Vent Vents in Place Failed
3" Vent Through Roof Failed
1 ½ inch minimum Drain Size Failed
Shower liner test (2" of water)Failed
Washing Machine Drain 2 inch minimum Failed
Washing Machine Trap: 18"-42" discharge Failed
Cleanout every 100 feet change of direction Failed
Pressure Test Passed
Head test
Drain Vent Failed
Air Head Passed
Head
5 psi or 10 ft. above highest conn. for 15 minutes Passed
Jan 29, 2021 Page (2)
INSPECTION WORKSHEET (RPLUM-007976-2021)
Checklist Item Status
Pressure Test Failed
Water Supply Piping Failed
Air Head Failed
50 P.S.I for 15 minutes Failed
Air Test Gas Piping 10 psi for 10 Minutes Failed
All Return Air Hard Duct Work Failed
Duct Insulation - if required in unheated spaces Failed
Duct Testing Outside Conditioned Space Failed
Duct work sealed properly Failed
Jan 29, 2021 Page (3)
Dyer, Charles