Signed Inspection Report (Thu Mar 25, 2021 at 1104 AM)INSPECTION WORKSHEET (FDTN-009104-2021)
Town of Queensbury - Building and Codes - Fire Marshal
742 Bay Road - (518) 761-8256 Building (518) 761-8206 Fire Marshal
Case Number:RC-0261-2020 Case Module:Permit
Inspection Date:Thu Mar 25, 2021 Inspection Status:Partial Pass
Inspector:Dyer, Charles Inspection Type:Building Foundation
Job Address:Parcel Number:12 SHORE ACRES RD
Queensbury, NY, 12804
227.17-1-11
Contact Type Company Name Name
Granted Permission J. Clarke Construction
Architect Phinney Design Group
Applicant Frazier, Daniel
Primary Owner Frazier, Daniel
Contractor J. Clarke Construction
Applicant Frazier, Meghan
Primary Owner Frazier, Meghan
Checklist Item Status
Building Inspector Notes Passed
9/21/20 call from B.Springer looking for footing inspection for main portion of home.
10/13/20 foundation walls approved for main house only.
11/12/20 to check for vertical dowels @ garage footings-slab/poly for house verified.
Garage walls verified for rebar with north portico footings 11/18/20
12/8/20 plumbing under slab at garage for radiant heating verified, holding 20 psi for 15 minutes, poly under slab
verified, with 6x6 welded wire mesh
1/25/21 frost walls for patio lake side of house approved, see plans for specifications.
1/28/21 foundation walls at porch extension approved.
Mar 25, 2021 Page (1)
INSPECTION WORKSHEET (FDTN-009104-2021)
Checklist Item Status
2/1/21 partial approval for the 4 piers lake side of house, provide an updated plan or letter of approval from the
design engineer for the change from CMU to poured concrete at these piers.
Footings Passed
For main portion of home only approved 9/21/20
Footings for garage verified and approved with #5 bar continuous, wet sticking dowels 11/4/20
Portico @ north corner with 2 rows # 5, grids with # 4
See specs pg S203
1/20/21 for lakeside porch with # 4&5 grids wet sticking # 6 verticals
3/25/21 for footings at portico entry, with #4 & #5 grids approved
Piers Passed
10/30/20 haunches with #4 grids for placement of steel columns
1/20/21 for lakeside fireplace pier and column
2/1/21 partial approval for the 4 piers lake side of house, provide an updated plan or letter of approval from the
design engineer for the change from CMU to poured concrete at these piers.
Reinforcement in Place Passed
With 2 rows #5 continuous, #5 grids @ piers
Foundation / Wallpour Passed
10/13/20.
11/18/20 for garage walls approved
1/28/21 foundation walls at porch extension approved.
2/1/21 partial approval for the 4 piers lake side of house, provide an updated plan or letter of approval from the
design engineer for the change from CMU to poured concrete at these piers.
Reinforcement in Place Passed
10' walls have 5 rows of #5 rebar horizontal spaced equally two pieces at top and bottom of wall. One #5 below
shelf, continuous.
Frost walls have #5 rebar continuous 2 rows at top and two at bottom of wall, one #5 below shelf
Garage walls with 6 rows continuous, above and beyond specs from pg s203
2/23/21 for northeast slab patio, with #4&5 bar grid with foam and poly, above and beyond specs
Mar 25, 2021 Page (2)
INSPECTION WORKSHEET (FDTN-009104-2021)
Checklist Item Status
Footing Dowels or Keyway in place Passed
# 5 dowels to be wet setting
#5 dowels 2' above footings at 12" o.c. For foundation and frost walls.
11/12/20 dowels for garage frost walls
Foundation Dampproofing Passed
Foundation Waterproofing Passed
Partial only, not completed at roadside of foundation 10/20/20-call when ready for remainder
11/4/20 remainder of waterproofing verified
Footing Drain Daylight or Sump Passed
Footing drain installed 6" 10/20/20
Footing Drain Stone - 12 inch width Passed
Partial only, for roadside (cleverdale rd)
Verified remainder of stone
Footing Drain Stone - 6 inches above footing Passed
Partial only, roadside of foundation only 10/21/20
For remainder of stone and pipe 10/27/20
Footing Drain stone - 6 mil poly Passed
With fabric over stone, roadside of foundation (cleverdale road) 10/21/20
Backfill Approval Passed
Approved 11/4/20
Plumbing Under Slab Passed
For 4" SCHD 40-2" DWV 10/28/20
12/8/20 radiant heat at garage slab verified.
2/12/21 for hydronic heat lines
2/23/21 for hydronic heat for northeast slab/patio holding air
Mar 25, 2021 Page (3)
INSPECTION WORKSHEET (FDTN-009104-2021)
Checklist Item Status
PVC / Cast / Copper Passed
PVC
Foundation Insulation Interior / Exterior Passed
Exterior 1 1/2" pink foam board R 10
11/4/20 remainder of exterior foam board verified
2/12/21 2" foam at lakeside patio
Rough Grade 6 inch drop within 10 ft.Failed
Poly Under Slab Passed
With hydronic heat lines holding 20+ psi-verified 11/6 /20
Garage slab will be with hydronic lines
12/8/20 garage slab verified with 6x6 welded wire mesh
Mar 25, 2021 Page (4)
Dyer, Charles