Signed Inspection Report (Fri Apr 2, 2021 at 1227 PM)INSPECTION WORKSHEET (FDTN-009358-2021)
Town of Queensbury - Building and Codes - Fire Marshal
742 Bay Road - (518) 761-8256 Building (518) 761-8206 Fire Marshal
Case Number:CC-0621-2020 Case Module:Permit
Inspection Date:Fri Apr 2, 2021 Inspection Status:Partial Pass
Inspector:O'Brien, John Inspection Type:Building Foundation
Job Address:Parcel Number:719 BAY RD
Queensbury, NY, 12804
289.19-1-27
Contact Type Company Name Name
Contractor BBL Construction Services Crupi, John
Architect HCP Architects, LLP
Primary Owner Rosetti Acquisitions LLC
Applicant BBL Construction Services Crupi, John
Granted Permission BBL Construction Services Crupi, John
Checklist Item Status
Apr 02, 2021 Page (1)
INSPECTION WORKSHEET (FDTN-009358-2021)
Checklist Item Status
Building Inspector Notes Failed
10/26/20 recieved compaction tests
11/24/20 Footing Partial Approval
T-17 to C-11
12/2/20 Footings Partial Approval - West Elevation from C-11 to stair tower 1 to North of elevator at G16.
12/9/20 Foundation Partial Approval
- Foundation Walls partial approval from F12.5 to T4.5, Elevator #1 and Stair #1.
- Footings Partial Approval from T16 to T29
12/11/20 Foundation Partial Approval
- Foundation Insulation installed from H3 to D9
- Backfill Partial Approval from H3 to D9
12/16/20 Foundation Partial Approval
- Foundation Walls T5 - T19
- Footings T25 - B38
12/16/20 Foundation Partial Approval
- Foundation Insulation D9 - T18
- Backfill D9 - T18
12/18/20 Foundation Partial Approval
- Footings G16 - F24
12/23/20 Foundation Partial Approval
- 8 interior footings at south end of building approved
- First Floor Stair #1 masonry block partial approval( Vertical bars 4-#7s in corners, vertical #4s at 48" oc and #4s
@ 16" oc at shear wall
12/29/20 Foundation Partial Approval
- East Foundation Wall
- West Foundation Wall
- Masonry Wall Bond Beam and Vertical Bar.
Verticals reinforcing in place bond beam reinforcing not in place Terracon on site to witness placement and
concrete grout testing.
12/30/20 Foundation Partial Approval
- West Foundation Wall F12.5 to F21 Foundation Insulation. Ok to backfill!
1/6/21 Foundation Partial Approval
- 2nd Floor Stair #1 masonry block partial approval( Vertical bars 4-#7s in corners, vertical #4s at 48" oc and #4s
@ 16" oc at shear wall
Apr 02, 2021 Page (2)
INSPECTION WORKSHEET (FDTN-009358-2021)
Checklist Item Status
1/8/21 Foundation Partial Approval
- Balance of East Foundation Walls and 12' of North Foundation Walls from NE Corner Approved
1/11/21 2" ridged insulation verified from line 20 T to 38 T at east wall ok to backfill this area only
1/12/21 foundation partial approval
- isolated interior footings at southwest leg of building.
- stairs #2 footings and elevator pit.
1/15/21 Foundation Partial Approval
- Foundation wall west elevation partial approval.
- Exterior Column Footings at NE Corner last two on east wall.
1/19/21 foundation insulation verified at west wall to elevator pit
- vertical reinforcing and bond beam reinforcing verified at final bond beam for elevator shaft.
1/22/21 balance of footings at perimeter of building completed with the exception of a small area at the 25/26/ line
for machine access. 4 spread footings at north end of building verified.
1/28/21 frost walls verified to the #28 line
- 4 spread footings at north end of building verified
-bond beam above elevator door at first floor level and rebar at sheer wall stair/ elevator pit #2 verified, #7 rebar at
shear wall corner verified.
1/29/21 bond beam at elevator/ stair well #2 verified at the 13'7" elevation.
2/5/21 bond beam at the 25' 1" 7/8 elevation of stair/ elevator pit #2 verified
2" ridged insulation at interior of foundation approved to line 28 of west wall, ok to back fill to this point.
2/19/21 bond beam at the 13' 7" elevation of stair well #3 verified, #4 and #7 rebar for sheer wall #4 verified.
2/25/21 Building Foundation Partial Approval - 2nd floor metal deck south half approved. Wire mesh, metal
decking and reinforcing at stair and elevator towers verified and approved.
2/26/21 Building Foundation Partial Approval
- Balance of exterior footings north of Stair Tower #4 approved
- Balance of interior pier and column footings at north end approved.
3/2/21 Building Foundation Partial Approval
- Balance of exterior walls north of stair tower #4 approved.
- Balance of interior piers at north end approved.
3/11/21 2" ridged insulation at interior of frost walls completed, ok to backfill
3/24/21 Building Foundation Partial Approval
Apr 02, 2021 Page (3)
INSPECTION WORKSHEET (FDTN-009358-2021)
Checklist Item Status
- Garage Slab from south end of building to column line 18 approved. Slab edge foundation insulation, wire mesh,
reinforced haunches approved.
4/02/21 Building Foundation Partial Approval - Balance of 2nd floor metal deck approved. Wire mesh, metal
decking and reinforcing at stair and elevator towers verified and approved.
Apr 02, 2021 Page (4)
INSPECTION WORKSHEET (FDTN-009358-2021)
Checklist Item Status
Footings Passed
Vertical 11/24/20 Footing Partial Approval
T-17 to C-11
12/2/20 Footings Partial Approval
12/2/20 Footings Partial Approval - West Elevation from C-11 to stair tower 1 to North of elevator at G16.
12/9/20 Foundation Partial Approval
- Footings Partial Approval from T16 to T29
12/16/20 Foundation Partial Approval
- Foundation Walls T5 - T19
- Footings T25 - B38
12/18/20 Foundation Partial Approval
- Footings G16 - F24
12/23/20 Foundation Partial Approval
- 8 interior footings at south end of building approved
- First Floor Stair #1 masonry block partial approval( Vertical bars 4-#7s in corners, vertical #4s at 16" oc and #4s
@ 48" oc at shear wall
12/31/20 Foundation Partial Approval
- Interior Column and Pier Footings at lines R and K 12-20.
1/12/21 foundation partial approval
- isolated interior footings at southwest leg of building.
- stairs #2 footings and elevator pit.
1/15/21 Foundation Partial Approval
- Exterior Column Footings at NE Corner last two on east wall.
1/22/21 balance of footings at perimeter of building completed with the exception of a small area at the 25/26/ line
for machine access. 4 spread footings at north end of building verified.
2/26/21 Building Foundation Partial Approval
- Balance of exterior footings north of Stair Tower #4 approved
- Balance of interior pier and column footings at north end approved.
3/24/21 Building Foundation Partial Approval
- Garage Slab from south end of building to column line 18 approved. Slab edge foundation insulation, wire mesh,
reinforced haunches approved.
Apr 02, 2021 Page (5)
INSPECTION WORKSHEET (FDTN-009358-2021)
Checklist Item Status
Piers Passed
1/4/21 porch piers front and rear of building
Rebar per plans 6 front and 5 rear
3/2/21 Building Foundation Partial Approval
- Balance of exterior walls north of stair tower #4 approved.
- Balance of interior piers at north end approved.
Monolithic Slab Passed
2/25/21 Building Foundation Partial Approval - 2nd floor metal deck south half approved. Wire mesh, metal
decking and reinforcing at stair and elevator towers verified and approved.
4/02/21 Building Foundation Partial Approval - Balance of 2nd floor metal deck approved. Wire mesh, metal
decking and reinforcing at stair and elevator towers verified and approved.
Apr 02, 2021 Page (6)
INSPECTION WORKSHEET (FDTN-009358-2021)
Checklist Item Status
Reinforcement in Place Passed
11/24/20 Footing Partial Approval
T-17 to C-11
12/2/20 Footings Partial Approval - West Elevation from C-11 to stair tower 1 to North of elevator at G16.
12/9/20 Foundation Partial Approval
- Footings Partial Approval fromT16 to T29
12/16/20 Foundation Partial Approval
- Foundation Walls T5 - T19
- Footings T25 - B38
12/18/20 Foundation Partial Approval
- Footings G16 - F24
12/23/20 Foundation Partial Approval
- 8 interior footings at south end of building approved
- First Floor Stair #1 masonry block partial approval( Vertical bars 4-#7s in corners, vertical #4s at 16" oc and #4s
@ 48" oc at shear wall
12/31/20 Foundation Partial Approval
- Interior Column and Pier Footings at lines R and K 12-20.
1/12/21 foundation partial approval
- isolated interior footings at southwest leg of building.
- stairs #2 footings and elevator pit.
1/15/21 Foundation Partial Approval
- Exterior Column Footings at NE Corner last two on east wall.
1/19/21 foundation insulation verified at west wall to elevator pit
- vertical reinforcing and bond beam reinforcing verified at final bond beam for elevator shaft.
2/26/21 Building Foundation Partial Approval
- Balance of exterior footings north of Stair Tower #4 approved u
- Balance of interior pier and column footings at north end approved.pj,7jk
3/24/21 Building Foundation Partial Approval
- Garage Slab from south end of building to column line 18 approved. Slab edge foundation insulation, wire mesh,
reinforced haunches approved.
4/02/21 Building Foundation Partial Approval - Balance of 2nd floor metal deck approved. Wire mesh, metal
decking and reinforcing at stair and elevator towers verified and approved.
Apr 02, 2021 Page (7)
INSPECTION WORKSHEET (FDTN-009358-2021)
Checklist Item Status
Foundation / Wallpour Passed
12/9/20 Foundation Partial Approval
- Foundation Walls partial approval from F12.5 to T4.5, Elevator #1 and Stair #1.
12/16/20 Foundation Partial Approval
- Foundation Walls T5 - T19
- Footings T25 - B38
12/29/20 Foundation Partial Approval
- East Foundation Wall T19 to T22
- West Foundation Wall F12.5 to F21
- Masonry Wall Bond Beam and Vertical Bar.
Verticals reinforcing in place bond beam reinforcing not in place Terracon on site to witness placement and
concrete grout testing.
1/8/21 Foundation Partial Approval
- Balance of East Foundation Walls and 12' of North Foundation Walls from NE Corner Approved
1/15/21 Foundation Partial Approval
- Foundation wall west elevation partial approval
1/28/21 frost walls verified to the #28 line
- 4 spread footings at north end of building verified
-bond beam above elevator door at first floor level and rebar at sheer wall stair/ elevator pit #2 verified, #7 rebar at
shear wall corner verified.
3/2/21 Building Foundation Partial Approval
- Balance of exterior walls north of stair tower #4 approved.
- Balance of interior piers at north end approved.
Apr 02, 2021 Page (8)
INSPECTION WORKSHEET (FDTN-009358-2021)
Checklist Item Status
Reinforcement in Place Passed
12/9/20 Foundation Partial Approval
- Foundation Walls partial approval from F12.5 to T4.5, Elevator #1 and Stair #1.
12/16/20 Foundation Partial Approval
- Foundation Walls T5 - T19
- Footings T25 - B38
12/29/20 Foundation Partial Approval
- East Foundation Wall T19 to T22
- West Foundation Wall F12.5 to F21
- Masonry Wall Bond Beam and Vertical Bar.
Verticals reinforcing in place bond beam reinforcing not in place Terracon on site to witness placement and
concrete grout testing.
1/8/21 Foundation Partial Approval
- Balance of East Foundation Walls and 12' of North Foundation Walls from NE Corner Approved
1/15/21 Foundation Partial Approval
- Foundation walls west elevation partial approval
1/19/21 foundation insulation verified at west wall to elevator pit
- vertical reinforcing and bond beam reinforcing verified at final bond beam for elevator shaft.
1/28/21 frost walls verified to the #28 line
- 4 spread footings at north end of building verified
-bond beam above elevator door at first floor level and rebar at sheer wall stair/ elevator pit #2 verified, #7 rebar at
shear wall corner verified.
2/5/21 bond beam at the 25' 1" 7/8 elevation of stair/ elevator pit #2 verified
2" ridged insulation at interior of foundation approved to line 28 of west wall, ok to back fill to this point.
3/2/21 Building Foundation Partial Approval
- Balance of exterior walls north of stair tower #4 approved.
- Balance of interior piers at north end approved.
Apr 02, 2021 Page (9)
INSPECTION WORKSHEET (FDTN-009358-2021)
Checklist Item Status
Masonry Wall Passed
12/23/20 Foundation Partial Approval
- First Floor Stair #1 masonry block partial approval( Vertical bars 4-#7s in corners, vertical #4s at 48" oc and #4s
@ 16" oc at shear wall
12/29/20 Foundation Partial Approval
- Masonry Wall Bond Beam and Vertical Bar.
Verticals reinforcing in place bond beam reinforcing not in place Terracon on site to witness placement and
concrete grout testing.
1/6/21 Foundation Partial Approval
- 2nd Floor Stair #1 masonry block partial approval( Vertical bars 4-#7s in corners, vertical #4s at 48" oc and #4s
@ 16" oc at shear wall
- Dente on site verifying masonry vertical reinforcing, bond beam reinforcing and testing mortar and grout.
1/28/21 frost walls verified to the #28 line
- 4 spread footings at north end of building verified
-bond beam above elevator door at first floor level and rebar at sheer wall stair/ elevator pit #2 verified, #7 rebar at
shear wall corner verified.
1/29/21 bond beam at elevator/ stair well #2 verified at the 13'7" elevation
2/5/21 bond beam at the 25' 1" 7/8 elevation of stair/ elevator pit #2 verified
2" ridged insulation at interior of foundation approved to line 28 of west wall, ok to back fill to this point.
2/19/21 bond beam at the 13' 7" elevation of stair well #3 verified, #4 and #7 rebar for sheer wall #4 verified.
Apr 02, 2021 Page (10)
INSPECTION WORKSHEET (FDTN-009358-2021)
Checklist Item Status
Reinforcement in Place Passed
12/23/20 Foundation Partial Approval
- First Floor Stair #1 masonry block partial approval( Vertical bars 4-#7s in corners, vertical #4s at 48" oc and #4s
@ 16" oc at shear wall
12/29/20 Foundation Partial Approval
- Masonry Wall Bond Beam and Vertical Bar.
Verticals reinforcing in place bond beam reinforcing not in place Terracon on site to witness placement and
concrete grout testing.
1/6/21 Foundation Partial Approval
- 2nd Floor Stair #1 masonry block partial approval( Vertical bars 4-#7s in corners, vertical #4s at 48" oc and #4s
@ 16" oc at shear wall
- Dente on site verifying masonry vertical reinforcing, bond beam reinforcing and testing mortar and grout.
Footing Dowels or Keyway in place Passed
11/24/20 Footing Partial Approval
T-17 to C-11
12/2/20 Footings Partial Approval - West Elevation from C-11 to stair tower 1 to North of elevator at G16.
12/9/20 - Footings Partial Approval fromT16 to T29
12/16/20 Foundation Partial Approval
- Foundation Walls T5 - T19
- Footings T25 - B38
12/18/20 Foundation Partial Approval
- Footings G16 - F24
2/26/21 Building Foundation Partial Approval
- Balance of exterior footings north of Stair Tower #4 approved
- Balance of interior pier and column footings at north end approved.
Foundation Dampproofing Failed
Apr 02, 2021 Page (11)
INSPECTION WORKSHEET (FDTN-009358-2021)
Checklist Item Status
Foundation Waterproofing Failed
Footing Drain Daylight or Sump Failed
Footing Drain Stone - 12 inch width Failed
Footing Drain Stone - 6 inches above footing Failed
Footing Drain stone - 6 mil poly Failed
Backfill Approval Passed
12/11/20 Foundation Partial Approval
- Foundation Insulation installed from H3 to D9
- Backfill Partial Approval from H3 to D9
12/16/20 Foundation Partial Approval
- Foundation Insulation D9 - T18
- Backfill D9 - T18
12/30/20 Foundation Partial Approval
- West Foundation Wall F12.5 to F21 Foundation Insulation. Ok to backfill!
1/11/21 2" ridged insulation verified at east wall line 20 T to 38 T ok to backfill this area only.
2/5/21 bond beam at the 25' 1" 7/8 elevation of stair/ elevator pit #2 verified
2" ridged insulation at interior of foundation approved to line 28 of west wall, ok to back fill to this point.3/11/21 2"
ridged insulation at interior of frost walls completed, ok to backfill
3/11/21 2" ridged insulation at interior of frost walls completed, ok to backfill
Apr 02, 2021 Page (12)
INSPECTION WORKSHEET (FDTN-009358-2021)
Checklist Item Status
Plumbing Under Slab Passed
PVC / Cast / Copper Passed
Foundation Insulation Interior / Exterior Passed
12/11/20 Foundation Partial Approval
- Foundation Insulation installed from H3 to D9
- Backfill Partial Approval from H3 to D9
12/16/20 Foundation Partial Approval
- Foundation Insulation D9 - T18
- Backfill D9 - T18
12/30/20 Foundation Partial Approval
- West Foundation Wall F12.5 to F21 Foundation Insulation. Ok to backfill!
3/11/21 2" ridged insulation at interior of frost walls completed, ok to backfill.
3/24/21 Building Foundation Partial Approval
- Garage Slab from south end of building to column line 18 approved. Slab edge foundation insulation, wire mesh,
reinforced haunches approved.
Rough Grade 6 inch drop within 10 ft.Failed
Poly Under Slab Passed
Apr 02, 2021 Page (13)
O'Brien, John