Signed Inspection Report (Tue May 4, 2021 at 146 PM)INSPECTION WORKSHEET (FDTN-010105-2021)
Town of Queensbury - Building and Codes - Fire Marshal
742 Bay Road - (518) 761-8256 Building (518) 761-8206 Fire Marshal
Case Number:CC-0014-2021 Case Module:Permit
Inspection Date:Tue May 4, 2021 Inspection Status:Failed
Inspector:O'Brien, John Inspection Type:Building Foundation
Job Address:Parcel Number:170 CAREY RD
Queensbury, NY, 12804
309.13-2-31.113
Contact Type Company Name Name
Primary Owner Boldstar LLC
Granted Permission Bonacio Construction Inc
Contractor Bonacio Construction Inc
Applicant Bonacio Construction Inc
Checklist Item Status
May 04, 2021 Page (1)
INSPECTION WORKSHEET (FDTN-010105-2021)
Checklist Item Status
Building Inspector Notes Failed
2/3/21 Foundation Partial Approval - Footings
- Footings Partial Approval except for 12' of East wall line at NE corner.
2/11/21 Foundation Partial Approval - Foundation Walls
- Foundation walls partial Approval.
East Wall from G10 to 6' passed F10, South Wall, West Wall and North Wall from C1 to 3' before C10.
2/19/21 partial approval for foundation insulation, 2.5" ridged insulation at interior of frost walls, east wall not
completed.
3/3/21 Building Foundation Partial Approval
- Balance of exterior footings approved
- 12 interior column footings approved
3/8/21 Building Foundation Partial Approval
- Balance of Exterior Foundation Walls and 2 exterior piers on north side of building approved.
3/22/21 Building Foundation Partial Approval
- P3 Extension at 5.5A & 5.5B Approved
- Shear Wall Footings at 2 locations approved.
Stamped detail to follow from engineer. Reinforcing installed as per detailed email from engineer.
5/4/21 Building Foundation Not Approved
- Monolithic Slab not approved. 2" foam insulation not installed at steel column locations and 24" section of south
shear wall location. Provide a detail from architect addressing energy code compliant frost break. Call for recheck
before placement of concrete.
Footings Passed
2/3/21 Foundation Partial Approval - Footings
- Footings Partial Approval except for 12' of East wall line at NE corner.
3/3/21 Building Foundation Partial Approval
- Balance of exterior footings approved
- 12 interior column footings approved
3/22/21 Building Foundation Partial Approval
- P3 Extension at 5.5A & 5.5B Approved
- Shear Wall Footings at 2 locations approved.
Stamped detail to follow from engineer. Reinforcing installed as per detailed email from engineer.
May 04, 2021 Page (2)
INSPECTION WORKSHEET (FDTN-010105-2021)
Checklist Item Status
Piers Passed
3/8/21 Building Foundation Partial Approval
- Balance of Exterior Foundation Walls and 2 exterior piers on north side of building approved.
3/22/21 Building Foundation Partial Approval
- P3 Extension at 5.5A & 5.5B Approved
- Shear Wall Footings at 2 locations approved.
Stamped detail to follow from engineer. Reinforcing installed as per detailed email from engineer.
Monolithic Slab Failed
5/4/21 Building Foundation Not Approved
- Monolithic Slab not approved. 2" foam insulation not installed at steel column locations and 24" section of south
shear wall location. Provide a detail from architect addressing energy code compliant frost break. Call for recheck
before placement of concrete.
Reinforcement in Place Passed
2/3/21 Foundation Partial Approval - Footings
- Footings Partial Approval except for 12' of East wall line at NE corner.
3/3/21 Building Foundation Partial Approval
- Balance of exterior footings approved
- 12 interior column footings approved
3/22/21 Building Foundation Partial Approval
- P3 Extension at 5.5A & 5.5B Approved
- Shear Wall Footings at 2 locations approved.
Stamped detail to follow from engineer. Reinforcing installed as per detailed email from engineer.
Foundation / Wallpour Passed
2/11/21 Foundation Partial Approval - Foundation Walls
- Foundation walls partial Approval.
East Wall from G10 to 6' passed F10, South Wall, West Wall and North Wall from C1 to 3' before C10.
3/8/21 Building Foundation Partial Approval
- Balance of Exterior Foundation Walls and 2 exterior piers on north side of building approved.
May 04, 2021 Page (3)
INSPECTION WORKSHEET (FDTN-010105-2021)
Checklist Item Status
Reinforcement in Place Passed
2/11/21 Foundation Partial Approval - Foundation Walls
- Foundation walls partial Approval.
East Wall from G10 to 6' passed F10, South Wall, West Wall and North Wall from C1 to 3' before C10.
3/8/21 Building Foundation Partial Approval
- Balance of Exterior Foundation Walls and 2 exterior piers on north side of building approved.
Masonry Wall Failed
Reinforcement in Place Failed
Footing Dowels or Keyway in place Passed
2/3/21 Foundation Partial Approval - Footings
- Footings Partial Approval except for 12' of East wall line at NE corner.
2/11/21 Foundation Partial Approval - Foundation Walls
- Foundation walls partial Approval.
East Wall from G10 to 6' passed F10, South Wall, West Wall and North Wall from C1 to 3' before C10.
3/3/21 Building Foundation Partial Approval
- Balance of exterior footings approved
- 12 interior column footings approved
Foundation Dampproofing Failed
Foundation Waterproofing Failed
Footing Drain Daylight or Sump Failed
Footing Drain Stone - 12 inch width Failed
May 04, 2021 Page (4)
INSPECTION WORKSHEET (FDTN-010105-2021)
Checklist Item Status
Footing Drain Stone - 6 inches above footing Failed
Footing Drain stone - 6 mil poly Failed
Backfill Approval Failed
Plumbing Under Slab Failed
PVC / Cast / Copper Failed
Foundation Insulation Interior / Exterior Failed
2/19/21 partial approval for foundation insulation, 2.5" ridged insulation at interior of frost walls, east wall not
completed.
Rough Grade 6 inch drop within 10 ft.Failed
Poly Under Slab Failed