Signed Inspection Report (Fri Dec 3, 2021 at 948 AM)INSPECTION WORKSHEET (COMFIN-015155-2021)
Town of Queensbury - Building and Codes - Fire Marshal
742 Bay Road - (518) 761-8256 Building (518) 761-8206 Fire Marshal
Case Number:CC-0034-2021 Case Module:Permit
Inspection Date:Fri Dec 3, 2021 Inspection Status:Passed
Inspector:O'Brien, John Inspection Type:Commercial Final Inspection
Job Address:Parcel Number:170 CAREY RD
Queensbury, NY, 12804
309.13-2-31.113
Contact Type Company Name Name
Applicant Bonacio Construction Inc
Contractor Bonacio Construction Inc
Architect Hyman Hayes Associates
Primary Owner 170 Carey Rd LLC
Granted Permission Adirondack Radiology
Checklist Item Status
Dec 03, 2021 Page (1)
INSPECTION WORKSHEET (COMFIN-015155-2021)
Checklist Item Status
Building Inspector Notes Passed
8/18/21 Commercial Final Inspection Not Approved
Remaining Items:
- Submit a final approval letters on the building from the architect and engineer. The letter will state that the
building has been built in accordance with the approved plans and specifications.
- Submit Special Inspection Report( third party) for structural framing.
- Perform and submit a blower door test on the entire building.
- Perform an HVAC Air Balancing Test on occupied space only.
- Install all doors with specified door hardware.
- Install permanent aluminum front entrance.
- Install all handicapped signs in designated bathrooms and dressing rooms as per the approved plans.
- Complete all plumbing fixtures
- Need to verify hot water.
- Verify Final Electrical Inspection
- Complete all counters in reception area. Need to verify HC counter heights of 34" max.
- Vacant space sprinkler room hot water boiler missing downspout to floor drain for pressure relief valve. Also pipe
condensate line on tank to floor drain.
- Install fiberglass insulation in exterior wall and box area of roof trusses in fire sprinkler room.
- Install handicapped parking signs and no parking signs in designated locations as per the approved site plan.
- Complete handicapped parking striping and access aisles as designated on the approved site plan.
- Complete installing ceiling tile and 2'x4' ceiling lights(secured to structure above).
- Install MRI Machine and complete building envelope at access location.
- Cover all exterior walls with spray foam in vacant lease space with 1/2" gypsum board.
- Caulk bottom plate of exterior walls of vacant space.
- Witness gas piping pressure test 10 psi for 10 minutes
- Submit certified Final Survey.
- install door to vacant space from main entrance.
- Complete demise wall on occupied space side to under side of roof decks.
- Code Compliance Inspection by Bruce Frank in planning and zoning.
- Address items from Fire Marshal's inspection.
9/3/21 Commercial Final Inspection Not Approved - Adirondack Radiology
Remaining Items:
- Complete installing all doors and lever handle hardware.
- Complete MRI Imaging Area
- Install all ceiling tiles.
- Complete hard ceiling above reception area.
- Perform HVAC Air balancing and submit report.
- Complete installing all reception area counters(HC height 34" FF).
- Verify hot water and downspout on hot water tank relief valve is within 6" from floor.
- Witness gas piping pressure test 10 psi for 10 minutes.
- Submit a final approval letters on the Adirondack Radiology Tenant Fit-Up from the architect and engineer. The
letter will state that tenant fit-up has been built in accordance with the approved plans and specifications.
- Complete all Fire Marshal's Items.
Dec 03, 2021 Page (2)
INSPECTION WORKSHEET (COMFIN-015155-2021)
Checklist Item Status
10/4/21 Commercial Final Inspection Not Approved
- Complete MRI Imaging Area(Temp CO)
- Install all missing ceiling tiles above mop sink.
- Complete hard ceiling above reception area.
- Perform HVAC Air balancing and submit report.
- Witness gas piping pressure test 10 psi for 10 minutes.
- Submit a final approval letters on the Adirondack Radiology Tenant Fit-Up from the architect and engineer. The
letter will state that tenant fit-up has been built in accordance with the approved plans and specifications.
- Complete additional seeding as per Bruce Frank's request.(Temp CO)
- Install handicapped signage for 2 ADA changing rooms.
- Repair leak in copper elbow of mechanical room.
- Submit Final Construction As-Builts electronically. (Temp CO)
- Perform and submit blower door test(Temp CO)
- Caulk bottom plate of exterior walls of vacant space.
- Submit Special Inspection Report( third party) for structural framing.
10/5/21 Commercial Final Inspection Partial Approval
Remaining Items:
- Ok to issue Temporary Certificate of Occupancy once the fee of $165.00 is paid and the Temp CO Invoice is
signed.
- NFPA 13 Letter
- Submit Special Inspection Report( third party) for structural framing.
TEMPORARY CERTIFICATE OF OCCUPANCY CONDITIONS:
- Perform and submit a blower door test on the entire building.
- Complete MRI Imaging Area.
- Complete additional seeding as per Bruce Frank's request.
- Submit Certified Final Survey
- Submit Final Construction As-Builts electronically.
- Submit Final Approval Letter from Architect stating that the Adirondack Imaging tenant fit up has been
completed in accordance with the approved plans, specifications and 2020 COMcheck for lighting and
mechanicals.- Install address number on building facing Carey Rd.
The address is 170 Carey Rd. You only need to install the number 170 and the numbers must be a minimum of 4"
high.
- Caulk bottom plate of exterior walls of vacant space.
- Complete hard ceiling above reception area.
10/6/21 Commercial Final Inspection Partial Approval
Note: Ok to issue Temporary Certificate of Occupancy for Adirondack Imaging Tenant Fit - Up once the fee of
$165.00 is paid and the Temp CO is signed.
TEMPORARY CERTIFICATE OF OCCUPANCY CONDITIONS:
1) Perform and submit the blower door test for the whole building.
2) Complete all work associated with MRI Imaging Room.
3) Submit Certified Final Survey.
4) Submit Final Approval Letter from Architect/Engineer stating that the Adirondack Imaging Tenant Fit-Up has
been completed in accordance with the approved plans , specifications and 2020 COMcheck for lighting and
mechanicals.
Dec 03, 2021 Page (3)
INSPECTION WORKSHEET (COMFIN-015155-2021)
Checklist Item Status
5) Install the permanent address number 170 on the building or a free standing approved sign facing Carey Road.
You only need to install the number 170 and it must be a minimum of 4" high.
- A temporary sign has been installed with the number 170 on it facing Carey Road.
6) Install handicapped signage at designated handicapped changing rooms.
7) Complete hard ceiling above receptionist counters.
12/3/21 Commercial Final Inspection Approved
- Ok to issue permanent certificate of occupancy!
Relief Valve ,Heat Trap/Water Temp 110 deg or less Passed
- Vacant space sprinkler room hot water boiler missing downspout to floor drain for pressure relief valve. Also pipe
condensate line on tank to floor drain.
- Verify hot water and downspout on hot water tank relief valve is within 6" from floor.
Attic Access 30 x 20 x 30 (h)Passed
Roof access
H/C mirrors 40" above floor Passed
.
Handicapped Service Counters 34 inch Passed
- Complete installing all reception area counters(HC height 34" FF).
Handicapped Ramps Passed
Curb ramp
Dec 03, 2021 Page (4)
INSPECTION WORKSHEET (COMFIN-015155-2021)
Checklist Item Status
Engineer or Architect Approval Passed
- Submit a final approval letters on the Adirondack Radiology Tenant Fit-Up from the architect and engineer. The
letter will state that tenant fit-up has been built in accordance with the approved plans and specifications.
10/4/21 Commercial Final Inspection Not Approved
- Complete MRI Imaging Area(Temp CO)
- Install all missing ceiling tiles above mop sink.
- Complete hard ceiling above reception area.
- Perform HVAC Air balancing and submit report.
- Witness gas piping pressure test 10 psi for 10 minutes.
- Submit a final approval letters on the Adirondack Radiology Tenant Fit-Up from the architect and engineer. The
letter will state that tenant fit-up has been built in accordance with the approved plans and specifications.
- Complete additional seeding as per Bruce Frank's request.(Temp CO)
- Install handicapped signage for 2 ADA changing rooms.
- Repair leak in copper elbow of mechanical room.
- Submit Final Construction As-Builts electronically. (Temp CO)
- Perform and submit blower door test(Temp CO)
- Caulk bottom plate of exterior walls of vacant space.
- Submit Special Inspection Report( third party) for structural framing.
Dec 03, 2021 Page (5)
INSPECTION WORKSHEET (COMFIN-015155-2021)
Checklist Item Status
OK to Issue Temporary C/O Passed
8/18/21 Commercial Final Inspection Not Approved
Remaining Items:
- Submit a final approval letters on the building from the architect and engineer. The letter will state that the
building has been built in accordance with the approved plans and specifications.
- Submit Special Inspection Report( third party) for structural framing.
- Perform and submit a blower door test on the entire building.
- Perform an HVAC Air Balancing Test on occupied space only.
- Install all doors with specified door hardware.
- Install permanent aluminum front entrance.
- Install all handicapped signs in designated bathrooms and dressing rooms as per the approved plans.
- Complete all plumbing fixtures
- Need to verify hot water.
- Verify Final Electrical Inspection
- Complete all counters in reception area. Need to verify HC counter heights of 34" max.
- Vacant space sprinkler room hot water boiler missing downspout to floor drain for pressure relief valve. Also pipe
condensate line on tank to floor drain.
- Install fiberglass insulation in exterior wall and box area of roof trusses in fire sprinkler room.
- Install handicapped parking signs and no parking signs in designated locations as per the approved site plan.
- Complete handicapped parking striping and access aisles as designated on the approved site plan.
- Complete installing ceiling tile and 2'x4' ceiling lights(secured to structure above).
- Install MRI Machine and complete building envelope at access location.
- Cover all exterior walls with spray foam in vacant lease space with 1/2" gypsum board.
- Caulk bottom plate of exterior walls of vacant space.
- Witness gas piping pressure test 10 psi for 10 minutes
- Submit certified Final Survey.
- install door to vacant space from main entrance.
- Complete demise wall on occupied space side to under side of roof decks.
- Code Compliance Inspection by Bruce Frank in planning and zoning.
- Address items from Fire Marshal's inspection.
9/3/21 Commercial Final Inspection Not Approved - Adirondack Radiology
Remaining Items:
- Complete installing all doors and lever handle hardware.
- Complete MRI Imaging Area
- Install all ceiling tiles.
- Complete hard ceiling above reception area.
- Perform HVAC Air balancing and submit report.
- Complete installing all reception area counters(HC height 34" FF).
- Verify hot water and downspout on hot water tank relief valve is within 6" from floor.
- Witness gas piping pressure test 10 psi for 10 minutes.
- Submit a final approval letters on the Adirondack Radiology Tenant Fit-Up from the architect and engineer. The
letter will state that tenant fit-up has been built in accordance with the approved plans and specifications.
- Complete all Fire Marshal's Items.
Dec 03, 2021 Page (6)
INSPECTION WORKSHEET (COMFIN-015155-2021)
Checklist Item Status
10/4/21 Commercial Final Inspection Not Approved
- Complete MRI Imaging Area(Temp CO)
- Install all missing ceiling tiles above mop sink.
- Complete hard ceiling above reception area.
- Perform HVAC Air balancing and submit report.
- Witness gas piping pressure test 10 psi for 10 minutes.
- Submit a final approval letters on the Adirondack Radiology Tenant Fit-Up from the architect and engineer. The
letter will state that tenant fit-up has been built in accordance with the approved plans and specifications.
- Complete additional seeding as per Bruce Frank's request.(Temp CO)
- Install handicapped signage for 2 ADA changing rooms.
- Repair leak in copper elbow of mechanical room.
- Submit Final Construction As-Builts electronically. (Temp CO)
- Perform and submit blower door test(Temp CO)
- Caulk bottom plate of exterior walls of vacant space.
- Submit Special Inspection Report( third party) for structural framing.
10/5/21 Commercial Final Inspection Partial Approval
Remaining Items:
- Ok to issue Temporary Certificate of Occupancy once the fee of $165.00 is paid and the Temp CO Invoice is
signed.
- NFPA 13 Letter
- Submit Special Inspection Report( third party) for structural framing.
TEMPORARY CERTIFICATE OF OCCUPANCY CONDITIONS:
- Perform and submit a blower door test on the entire building.
- Complete MRI Imaging Area.
- Complete additional seeding as per Bruce Frank's request.
- Submit Certified Final Survey
- Submit Final Construction As-Builts electronically.
- Submit Final Approval Letter from Architect stating that the Adirondack Imaging tenant fit up has been
completed in accordance with the approved plans, specifications and 2020 COMcheck for lighting and
mechanicals.- Install address number on building facing Carey Rd.
The address is 170 Carey Rd. You only need to install the number 170 and the numbers must be a minimum of 4"
high.
- Caulk bottom plate of exterior walls of vacant space.
- Complete hard ceiling above reception area.
10/6/21 Commercial Final Inspection Partial Approval
Note: Ok to issue Temporary Certificate of Occupancy for Adirondack Imaging Tenant Fit - Up once the fee of
$165.00 is paid and the Temp CO is signed.
TEMPORARY CERTIFICATE OF OCCUPANCY CONDITIONS:
1) Perform and submit the blower door test for the whole building.
2) Complete all work associated with MRI Imaging Room.
3) Submit Certified Final Survey.
4) Submit Final Approval Letter from Architect/Engineer stating that the Adirondack Imaging Tenant Fit-Up has
been completed in accordance with the approved plans , specifications and 2020 COMcheck for lighting and
mechanicals.
Dec 03, 2021 Page (7)
INSPECTION WORKSHEET (COMFIN-015155-2021)
Checklist Item Status
5) Install the permanent address number 170 on the building or a free standing approved sign facing Carey Road.
You only need to install the number 170 and it must be a minimum of 4" high.
- A temporary sign has been installed with the number 170 on it facing Carey Road.
6) Install handicapped signage at designated handicapped changing rooms.
7) Complete hard ceiling above receptionist counters.
12/3/21 Commercial Final Inspection Approved
- Ok to issue permanent certificate of occupancy!
Dec 03, 2021 Page (8)
INSPECTION WORKSHEET (COMFIN-015155-2021)
Checklist Item Status
OK to Issue C/O Passed
8/18/21 Commercial Final Inspection Not Approved
Remaining Items:
- Submit a final approval letters on the building from the architect and engineer. The letter will state that the
building has been built in accordance with the approved plans and specifications.
- Submit Special Inspection Report( third party) for structural framing.
- Perform and submit a blower door test on the entire building.
- Perform an HVAC Air Balancing Test on occupied space only.
- Install all doors with specified door hardware.
- Install permanent aluminum front entrance.
- Install all handicapped signs in designated bathrooms and dressing rooms as per the approved plans.
- Complete all plumbing fixtures
- Need to verify hot water.
- Verify Final Electrical Inspection
- Complete all counters in reception area. Need to verify HC counter heights of 34" max.
- Vacant space sprinkler room hot water boiler missing downspout to floor drain for pressure relief valve. Also pipe
condensate line on tank to floor drain.
- Install fiberglass insulation in exterior wall and box area of roof trusses in fire sprinkler room.
- Install handicapped parking signs and no parking signs in designated locations as per the approved site plan.
- Complete handicapped parking striping and access aisles as designated on the approved site plan.
- Complete installing ceiling tile and 2'x4' ceiling lights(secured to structure above).
- Install MRI Machine and complete building envelope at access location.
- Cover all exterior walls with spray foam in vacant lease space with 1/2" gypsum board.
- Caulk bottom plate of exterior walls of vacant space.
- Witness gas piping pressure test 10 psi for 10 minutes
- Submit certified Final Survey.
- install door to vacant space from main entrance.
- Complete demise wall on occupied space side to under side of roof decks.
- Code Compliance Inspection by Bruce Frank in planning and zoning.
- Address items from Fire Marshal's inspection.
9/3/21 Commercial Final Inspection Not Approved - Adirondack Radiology
Remaining Items:
- Complete installing all doors and lever handle hardware.
- Complete MRI Imaging Area
- Install all ceiling tiles.
- Complete hard ceiling above reception area.
- Perform HVAC Air balancing and submit report.
- Complete installing all reception area counters(HC height 34" FF).
- Verify hot water and downspout on hot water tank relief valve is within 6" from floor.
- Witness gas piping pressure test 10 psi for 10 minutes.
- Submit a final approval letters on the Adirondack Radiology Tenant Fit-Up from the architect and engineer. The
letter will state that tenant fit-up has been built in accordance with the approved plans and specifications.
- Complete all Fire Marshal's Items.
Dec 03, 2021 Page (9)
INSPECTION WORKSHEET (COMFIN-015155-2021)
Checklist Item Status
10/4/21 Commercial Final Inspection Not Approved
- Complete MRI Imaging Area(Temp CO)
- Install all missing ceiling tiles above mop sink.
- Complete hard ceiling above reception area.
- Perform HVAC Air balancing and submit report.
- Witness gas piping pressure test 10 psi for 10 minutes.
- Submit a final approval letters on the Adirondack Radiology Tenant Fit-Up from the architect and engineer. The
letter will state that tenant fit-up has been built in accordance with the approved plans and specifications.
- Complete additional seeding as per Bruce Frank's request.(Temp CO)
- Install handicapped signage for 2 ADA changing rooms.
- Repair leak in copper elbow of mechanical room.
- Submit Final Construction As-Builts electronically. (Temp CO)
- Perform and submit blower door test(Temp CO)
- Caulk bottom plate of exterior walls of vacant space.
- Submit Special Inspection Report( third party) for structural framing.
10/5/21 Commercial Final Inspection Partial Approval
Remaining Items:
- Ok to issue Temporary Certificate of Occupancy once the fee of $165.00 is paid and the Temp CO Invoice is
signed.
- NFPA 13 Letter
- Submit Special Inspection Report( third party) for structural framing.
TEMPORARY CERTIFICATE OF OCCUPANCY CONDITIONS:
- Perform and submit a blower door test on the entire building.
- Complete MRI Imaging Area.
- Complete additional seeding as per Bruce Frank's request.
- Submit Certified Final Survey
- Submit Final Construction As-Builts electronically.
- Submit Final Approval Letter from Architect stating that the Adirondack Imaging tenant fit up has been
completed in accordance with the approved plans, specifications and 2020 COMcheck for lighting and
mechanicals.- Install address number on building facing Carey Rd.
The address is 170 Carey Rd. You only need to install the number 170 and the numbers must be a minimum of 4"
high.
- Caulk bottom plate of exterior walls of vacant space.
- Complete hard ceiling above reception area.
10/6/21 Commercial Final Inspection Partial Approval
Note: Ok to issue Temporary Certificate of Occupancy for Adirondack Imaging Tenant Fit - Up once the fee of
$165.00 is paid and the Temp CO is signed.
TEMPORARY CERTIFICATE OF OCCUPANCY CONDITIONS:
1) Perform and submit the blower door test for the whole building.
2) Complete all work associated with MRI Imaging Room.
3) Submit Certified Final Survey.
4) Submit Final Approval Letter from Architect/Engineer stating that the Adirondack Imaging Tenant Fit-Up has
been completed in accordance with the approved plans , specifications and 2020 COMcheck for lighting and
mechanicals.
Dec 03, 2021 Page (10)
INSPECTION WORKSHEET (COMFIN-015155-2021)
Checklist Item Status
5) Install the permanent address number 170 on the building or a free standing approved sign facing Carey Road.
You only need to install the number 170 and it must be a minimum of 4" high.
- A temporary sign has been installed with the number 170 on it facing Carey Road.
6) Install handicapped signage at designated handicapped changing rooms.
7) Complete hard ceiling above receptionist counters.
12/3/21 Commercial Final Inspection Approved
- Ok to issue permanent certificate of occupancy!
Dec 03, 2021 Page (11)
INSPECTION WORKSHEET (COMFIN-015155-2021)
Checklist Item Status
Dec 03, 2021 Page (12)
O'Brien, John