Signed Inspection Report (Mon Aug 1, 2022 at 311 PM)INSPECTION WORKSHEET (FDTN-019964-2022)
Town of Queensbury - Building and Codes - Fire Marshal
742 Bay Road - (518) 761-8256 Building (518) 761-8206 Fire Marshal
Case Number:CC-0237-2022 Case Module:Permit
Inspection Date:Mon Aug 1, 2022 Inspection Status:Partial Pass
Inspector:Smith, Mark Inspection Type:Building Foundation
Job Address:Parcel Number:27 SILVER CIR
Queensbury, NY, 12804
309.17-1-17.2
Contact Type Company Name Name
Contractor JAG I, LLC
Architect Rucinski-Hall Architecture
Primary Owner 27 Silver Circle LLC
Granted Permission 27 Silver Circle LLC
Applicant 27 Silver Circle LLC
Checklist Item Status
Permit Card Visible From Road Failed
Aug 01, 2022 Page (1)
INSPECTION WORKSHEET (FDTN-019964-2022)
Checklist Item Status
Building Inspector Notes Failed
6/17/22 partial approval for foundation
Footing partially completed, from line 16 to 19 on A line, lines a A thru E and 15 to 19 on E line, see page F-2 of
approved plans
6/22/22 partial approval for foundation
- foundation walls completed at the same area as listed above.
6/24/22 partial approval for foundation
- footings approved: E line from 15 line to 5 line and line 11 and 9 from E to D line, from page F-2 of approved
plans
6/28/22 partial approval for foundation
- 2" ridged insulation at interior of frost walls verified 16 to 19 on A line, lines A thru E, and 15 thru 19 on E line,
page F-2 of approved plans
6/30/29 partial approval for foundation walls
- foundation walls approved from E line, 14 line thru 6 line.
- 9 line E thru D, and 11 line E thru D page F-2 of approved plans
7/5/22 partial approval for foundation
- 2" ridged insulation at interior of frost walls verified, E line, from 13 line to 6 line, page F-2 of approved plans. Ok
to back fill this area only.
7/5/22 partial approval for foundation
- footings approved, E line 4 thru 1, A line 1 thru 5, all of 1 line. Page F-2 of approved
plans
7/8/22 partial approval for foundation
- foundation walls approved E line 5 thru A line #3, all of 1 line A thru E page F -2 of approved plans
7/11/22 partial approval for foundation
-2" ridged insulation verified at the remainder of south wall, west wall, and to the first pier at the north wall
7/12/22 partial approval for foundation
- footings approved, A line 11 to 15 line, 11 line E to C line, and C line 11 to 10 line.
7/18/22 partial approval for foundation
- foundation walls approved, A line 11 line thru 15 line, 11 line H thru C line and half of C line.
7/21/22 partial approval for foundation
- remainder of 2"ridged insulation verified at east warehouse.
7/22/22 partial approval for foundation
-foundation walls approved A line 4 thru 5 line
Aug 01, 2022 Page (2)
INSPECTION WORKSHEET (FDTN-019964-2022)
Checklist Item Status
-footings approved 9 line A thru C line,C line9 thru10 and A line 9 thru 8
7/27/22 partial approval for foundation
- remaining foundation walls at loading dock area completed.
7/28/22 partial approval for foundation
- remaining footings approved
8/1/22 partial approval for foundation
-foundation walls approved, front side of west building from loading dock to first pier.
- 2"ridged insulation at interior of frost walls verified at west warehouse at loading dock walls.
Footings Passed
6/17/22 partial approval for foundation
Footing partially completed, from line 16 to 19 on A line, lines a A thru E and 15 to 19 on E line, see page F-2 of
approved plans
6/24/22 partial approval for foundation
- footings approved: E line from 15 line to 5 line and line 11 and 9 from E to D line, from page F-2 of approved
plans
7/5/22 partial approval for foundation
- footings approved, E line 4 thru 1, A line 1 thru 5, all of 1 line. Page F-2 of approved plans
7/12/22 partial approval for foundation
- footings approved, A line 11 to 15 line, 11 line E to C line, and C line 11 to 10 line.
7/22/22 partial approval for foundation
-foundation walls approved A line 4 thru 5 line
-footings approved 9 line A thru C line,C line9 thru10 and A line 9 thru 8
7/28/22 partial approval for foundation
- remaining footings approved
Piers Failed
Monolithic Slab Failed
Aug 01, 2022 Page (3)
INSPECTION WORKSHEET (FDTN-019964-2022)
Checklist Item Status
Reinforcement in Place Passed
6/17/22 partial approval for foundation
Footing partially completed, from line 16 to 19 on A line, lines a A thru E and 15 to 19 on E line, see page F-2 of
approved plans
Foundation / Wallpour Passed
Foundation walls approved from line 16 to 19 on A line, lines a A thru E and 15 to 19 on E line, see page F-2 of
approved plans
6/30/29 partial approval for foundation walls
- foundation walls approved from E line, 14 line thru 6 line.
- 9 line E thru D, and 11 line E thru D page F-2 of approved plans
7/8/22 partial approval for foundation
- foundation walls approved E line 5 thru A line #3, all of 1 line A thru E page F -2 of approved plans
7/18/22 partial approval for foundation
- foundation walls approved, A line 11 line thru 15 line, 11 line H thru C line and half of C line.
7/22/22 partial approval for foundation
-foundation walls approved A line 4 thru 5 line
-footings approved 9 line A thru C line,C line9 thru10 and A line 9 thru 8
7/27/22 partial approval for foundation
- remaining foundation walls at loading dock area completed.
8/1/22 partial approval for foundation
-foundation walls approved, front side of west building from loading dock to first pier.
- 2"ridged insulation at interior of frost walls verified at west warehouse at loading dock walls.
Reinforcement in Place Passed
Foundation walls approved from line 16 to 19 on A line, lines a A thru E and 15 to 19 on E line, see page F-2 of
approved plans
6/30/29 partial approval for foundation walls
- foundation walls approved from E line, 14 line thru 6 line.
- 9 line E thru D, and 11 line E thru D page F-2 of approved plans
7/18/22 partial approval for foundation
- foundation walls approved, A line 11 line thru 15 line, 11 line H thru C line and half of C line.
Aug 01, 2022 Page (4)
INSPECTION WORKSHEET (FDTN-019964-2022)
Checklist Item Status
Masonry Wall Failed
Reinforcement in Place Failed
Footing Dowels or Keyway in place Failed
Foundation Dampproofing Failed
Foundation Waterproofing Failed
Footing Drain Daylight or Sump Failed
Footing Drain Stone - 12 inch width Failed
Footing Drain Stone - 6 inches above footing Failed
Footing Drain stone - 6 mil poly Failed
Aug 01, 2022 Page (5)
INSPECTION WORKSHEET (FDTN-019964-2022)
Checklist Item Status
Backfill Approval Passed
7/5/22 partial approval for foundation
- 2" ridged insulation at interior of frost walls verified, E line, from 13 line to 6 line, page F-2 of approved plans. Ok
to back fill this area only.
7/21/22 partial approval for foundation
- remainder of 2"ridged insulation verified at east warehouse.
8/1/22 partial approval for foundation
-foundation walls approved, front side of west building from loading dock to first pier.
- 2"ridged insulation at interior of frost walls verified at west warehouse at loading dock walls.
Plumbing Under Slab Failed
PVC / Cast / Copper Failed
Foundation Insulation Interior / Exterior Passed
6/28/22 partial approval for foundation
- 2" ridged insulation at interior of frost walls verified 16 to 19 on A line, lines A thru E, and 15 thru 19 on E line,
page F-2 of approved plans
7/5/22 partial approval for foundation
- 2" ridged insulation at interior of frost walls verified, E line, from 13 line to 6 line, page F-2 of approved plans. Ok
to back fill this area only.
7/11/22 partial approval for foundation
-2" ridged insulation verified at the remainder of south wall, west wall, and to the first pier at the north wall
7/21/22 partial approval for foundation
- remainder of 2"ridged insulation verified at east warehouse.
8/1/22 partial approval for foundation
-foundation walls approved, front side of west building from loading dock to first pier.
- 2"ridged insulation at interior of frost walls verified at west warehouse at loading dock walls.
Rough Grade 6 inch drop within 10 ft.Failed
Aug 01, 2022 Page (6)
INSPECTION WORKSHEET (FDTN-019964-2022)
Checklist Item Status
Poly Under Slab Failed
Aug 01, 2022 Page (7)
Smith, Mark