1984-07-31 SP 209
TOWN BOARD MEETING-SPECIAL
JULY 31, 1984 4:30 P.M.
TOWN BOARD MEMBERS
Mr. Daniel Olson-Deputy Supervisor
Dr. Charles Eisenhart-Councilman
Mr. Daniel Morrell-Councilman
Mrs. Betty Monahan-Councilman
ABSENT
y Mrs. Frances Walter-Supervisor
Mr. Wilson Mathias-Town Counsel
PLEDGE OF ALLEGIANCE LED BY Councilman Monahan
PRESS: G.F. Post Star, WBZA
GUESTS: Mr. Paul Cushing
TOWN OFFICIALS: Mr. Thomas Flaherty
------------------------------------------------------------------------------
Deputy Supervisor Daniel Olson- The purpose of this meeting is to see if we had
any bids for the renovation of the Police Office to a Court facility...
Town Clerk, Donald A. Chase- The bids for General Construction and
Heating,ventilating and Air Conditioning were opened at 2:00 P.M. on 7-31-84
GENERAL CONSTRUCTION BIDS
Adirondack Construction - $35,900.00
F.T. Collins Construction - $38,000.00
F.Fisk Construction - $28,500.00
Bid Securities, Non Collusion Certificates and Corp. Resolutions were included
in all bids submitted.
HEATING, VENTILATING AND AIR CONDITIONING
Crisafulli Bros. - $14,544.00
Hollisters - $18,877.00
Latham Heating - $13,400.00
Bid Security, Non Collusion Certificate and Corp. Resolution were included in all
bids received.
Mr. Paul Cushing, Architect- (ltr.) We have reviewed the bids received this date
for General Construction Work and Heating, Ventilating & Air Conditioning Work
for Renovations for Town Court. As the low bidders for each contract are all in
order, we recommend an award to F.Fisk Construction, Inc. in the sum of Twenty
Eight Thousand Five Hundred Dollars ($28,500.00) for General Construction Work;
similarly, we recommend an award to Latham Heating and Air Conditioning Corp.
in the sum of Thirteen Thousand Four Hundred Dollars ($13,400.00) for Heating,
Ventilating & Air Conditioning Work.
Councilman Eisenhart- What does this add up to?
Mr. Paul Cushing- $53,825.00
Deputy Supervisor, Olson- Is that for the completed project?
Mr. Cushing- No, one of the items that we took out of the General Construction
Work was the floor covering. The preliminary costs for that portion will be around
$3400.00.
Deputy Supervisor Olson- These bids are more in line with what the estimates were...
Councilman Monahan- I will abstain from the vote because Fisk Construction does
business with our firm...
214
RESOLUTION TO ACCEPT BID ON GENERAL CONSTRUCTION AND HEATING,
VENTILATING AND AIR CONDITIONING FOR RENOVATION OF POLICE OFFICES
TO COURT FACILITY
RESOLUTION NO. 186, Introduced by Dr. Charles Eisenhart who moved for its adoption,
seconded by Mr. Daniel Morrell:
WHEREAS, the Town Board for the Town of Queensbury did recommend that we
advertise for bids for General Construction and Heating, Ventilating and Air Conditioning
for renovation of Polcie Offices to Court Facility, and
WHEREAS, bids were submitted and received and opened at the specified time
and place by the Director of Purchasing/Town Clerk Donald A. Chase, and such
bids were then turned over to Mr. Paul Cushing, Architect for his recommendation, and
WHEREAS, Mr. Paul Cushing, by letter, has recommended that the bid be awarded
to F. Fisk Construction, Inc. for General Construction and Latham Heating and
Air Conditioning Corp. for Heating, Ventilating and Air Conditioning, NOW, THEREFORE
BE IT
RESOLVED, that the Town Board of the Town of Queensbury hereby accepts the
bid of F. Fisk Construction, Inc. in the amount of $28,500.00 and Latham Heating
in the amount of $13,400.00 , and be it further
RESOLVED, that the financing for such material is included in the 1984 Town Budget.
Duly adopted by the following vote:
Ayes: Dr. Eisenhart, Mr. Morrell, Mr. Olson.
Noes: None
Absent: Mrs. Walter
Abstain: Mrs. Monahan
On motion the meeting was adjourned.
Respectfully submitted,
i
Donald A. Chase, Town Clerk