IM Inspection Worksheet_27-07-2023_12-10-51INSPECTION WORKSHEET (PTI-026869-2023)
PT-0200-2022Case Number:Case Module:Permit Management
07/27/2023 PassedInspection Status:Inspection Date:
Property Transfer InspectionsInspection Type:Inspector:John O'Brien
Job Address:Parcel Number:2483 Ridge Rd
Queensbury, NY 12804
240.6-1-10
Company Name NameContact Type
Contractor IBS Septic
Primary Owner Robert Gilchrist
Checklist Item CommentsPassed
Building Inspector Notes True 4/29/22 Property Transfer Inspection Failed
- During the repairs of the pump station it was discovered that the
absorption field was in failure. Mr. Gilchrist will need a new septic
system.
4/24/23 Property Transfer Inspection Partial Approval
Remaining items:
- Need to verify pump, alarms and dosing of pump tank to raised
manifold pressure bed systems.
- Need to verify Final Electrical Inspection.
- Submit Final approval letter and certified septic system as-built.
- Provide maintenance agreement contract for the Norweco ETU
Unit.
- 5/5/23 partial approval for property transfer inspection
- pumps and alarms verified.
Items remaining
- proof of final electrical inspection
- maintenance agreement for enhanced treatment system.
- submit asbuilt drawing and letter of completion from design
engineer.
6/27/23 Property Transfer Inspection Not Approved
Remaining Items:
- proof of final electrical inspection
- provide maintenance agreement for enhanced treatment system.
7/27/23 Property Transfer Inspection Approved
- Received Maintenance Agreement
Maintenance Agrmnt/Srvc contract (required)True - Provide maintenance agreement contract for the Norweco ETU
Unit.
7/27/23 Property Transfer Inspection Approved
- Received Maintenance Agreement
Capacity in gallons True 1300
Is there a high water alarm?True
Roof gutters don't discharge over leach field True
Temperature (Fahrenheit)True 45
Visible scum layer True New system
Septic tank (include # of tanks)True 1
Number of tank compartments True 3
Plumbing fixtures tested & confirmed True
July 27, 2023 Page 1 of 2
INSPECTION WORKSHEET (PTI-026869-2023)
Checklist Item CommentsPassed
Stormwater True
Septic tank for bdrms/whrlpl/grndr w/in 250 gal True
Tank cover True
System passes all function testing True
Does the pump(s) appear to be operating properly?True
Depth below grade to top of tank True 8"-12"
Access riser? (if yes, depth to cover)True
Inlet baffle True
Aerobic system True Norweco Singulair Green Enhanced Treatment Unit
As-built provided is accurate True
Model True Norweco Singulair Green Enhanced Treatment Unit
Test each fixture flow to septic tank True
Liquid level AT/ABOVE/BELOW (one) discharge invert True New system
Type True Norweco Singulair Green Enhanced Treatment Unit
Are both switch and alarm operable?True
Outlet baffle True
Weather True Cloudy
Main tank cleanout size and location True
Manufacturer True Norweco Singulair Green Enhanced Treatment Unit
Plastic tank True Norweco Singulair Green Enhanced Treatment Unit
Dosing or pump tank sealed True
Leaking water fixtures True
Cracked, corroded or deformed?True
Water tight tank True
Sump pump(s)True
Raised system True Manifold pressure bed system
July 27, 2023 Page 2 of 2