IM Inspection Worksheet_04-01-2024_11-12-05INSPECTION WORKSHEET (FRM-000009-2024)
RC-0235-2023Case Number:Case Module:Permit Management
01/04/2024 Partial PassInspection Status:Inspection Date:
Building FramingInspection Type:Inspector:Charles Dyer
Job Address:Parcel Number:35 Mountainview Ter
Lake George, NY 12845
289.6-1-7.4
Company Name NameContact Type
Applicant John Hoffman
Architect Gary Hughes
Contractor Top Notch Builders
Granted Permission John Hoffman
Primary Owner John Hoffman
Checklist Item CommentsPassed
Building Inspector Notes False
Insulation under bow & bay window(s)False
Air Seal all Plates and Sills False
Joist hangers False
Exterior wall outlets sealed False
20 in. (W)False
Draft stopping 1,000 sq. ft. floor trusses False
5.0 sf grade False
Design Professional Sign-off, if required False
24 in. (H)False
Air Seal All Registers at Floor False
<4:12 pitch double layer of ice/snow underlayment False
Anchor Bolts 6 ft. or less on center False
Ice and water shield 24 inches from wall True For ice and water barrier only 1/4/24
Bath fans connected to exterior vent False
12 O.C.False
Air Sealing all Joints Before Insulation False
Notches Holes Bearing Walls False
5.7 sf above below grade False
>1000 s.f. then firestop must be installed False
Truss Specification Provided False
Windows Habitable Space Bedrooms False
Metal Strapping for Notches Top Plate False
Bracing Bridging False
Garage portal framing False
Deck (post beam connections hex head bolts)False
Jack Studs Headers False
Jack Posts Main Beams False
Attic Access 22 x 30 minimum False
January 04, 2024 Page 1 of 2
INSPECTION WORKSHEET (FRM-000009-2024)
Checklist Item CommentsPassed
Soffits-Insulation Baffel False
Exterior sheeting nailed properly False
Hurricane Clips/Uplift Screws/Nail Holes Filled False
Permit Card Visible From Road True
Framing False
Headroom 6 ft. 8 in.False
January 04, 2024 Page 2 of 2