IM Inspection Worksheet_18-01-2024_11-26-49INSPECTION WORKSHEET (RPLUM-000286-2024)
CC-0013-2023Case Number:Case Module:Permit Management
01/18/2024 Partial PassInspection Status:Inspection Date:
Rough PlumbingInspection Type:Inspector:Mark Smith
Job Address:Parcel Number:80 Main St
Queensbury, NY 12804
309.10-1-25
Company Name NameContact Type
Applicant FOOTHILLS BUILDERS, LLC
Architect Rucinski Hall Architecture
Contractor FOOTHILLS BUILDERS, LLC
Granted Permission FOOTHILLS BUILDERS, LLC
Primary Owner 78-80 Main Street LLC
Checklist Item CommentsPassed
Building Inspector Notes False 11/15/23 partial approval for rough plumbing.
- 5 roof drains at the east side of building pressure tested and
approved.
11/16/23 partial approval for rough plumbing:
- Remaining 5 roof drains pressure tested and approved.
12/11/23 partial approval for rough plumbing.
- sanitary drains and vents approved for rooms 308 thru 312
half of rooms 306 & 307 are included.
12/20/23 partial approval for rough plumbing.
- remaining plumbing for sanitary drain and vents at the 3rd floor
approved.
- Domestic water supply at 3rd floor approved.
- Main water line supplying 3rd floor approved.
1/2/24 partial approval for rough plumbing.
- plumbing for domestic water supply at second floor approved.
- main supply plumbing from first floor to second floor verified.
1/18/24 partial approval for rough plumbing.
- Sanitary drains and vents at second floor approved.
- Domestic water supply at second floor approved.
- Sanitary drains and vents at laundry room approved.
- Domestic water supply for laundry room approved.
Pressure Test True
Pressure Test True
3" Vent Through Roof - 18" min True
Washing Machine Drain 2 inch minimum True
All Return Air Hard Duct Work False
5 psi or 10 ft. above highest conn. for 15 minutes True third floor only
Rough Plumbing / Nail Plates True
Duct Testing Outside Conditioned Space False
Shower liner test (2" of water)False
Water Supply Piping True third floor only
Duct Insulation - if required in unheated spaces False
Duct work sealed properly False
January 18, 2024 Page 1 of 2
INSPECTION WORKSHEET (RPLUM-000286-2024)
Checklist Item CommentsPassed
Cleanout every 100 feet change of direction False
Plumbing Vent Vents in Place True
Air Test Gas Piping 10 psi for 10 Minutes False
Washing Machine Trap: 18"-42" discharge False
Air Head True
Air Head True
50 P.S.I for 15 minutes True
1 ½ inch minimum Drain Size True
Drain Vent True
Permit Card Visible From Road False
January 18, 2024 Page 2 of 2