INSPECTION WORKSHEET 03062024
INSPECTION WORKSHEET
Town of Queensbury - Building and Codes - Fire Marshal
742 Bay Road - (518) 761-8256 Building (518) 761-8206 Fire Marshal
Case Number: RC-0056-2022 Case Module:
Inspection Date: March 06, 2024 Inspection Status: Passed
Inspector: Mark Smith Inspection Type: Residential Final
Job Address: 1481 BAY RD
, Parcel Number:
Contact Type Company Name Name
Checklist Item
Status
Smoke Detectors:
PASS
Inter Connected
PASS
Guards at stairs,decks,patios 30" + above
grade
PASS
Battery backup
PASS
As Built Septic System
PASS
Basement wall insulation R- value verified
PASS
Low flow toilet 1.3 gal/flushing cycle
PASS
Basement stairs closed rise greater than
4 inches
PASS
Propane Tank: Proper Setback from Prop
Line/Struct
PASS
Basement Egress: 5s.f. window w/sill or
Bilco door
PASS
on all levels w/gas appliances (i.e.
furnace)
PASS
Guard at stairwell at 34" or more
PASS
Final Survey Plot Plan
PASS
OK to Issue C/O
PASS
Interior/Exterior Railings 34 to 38
PASS
Roof Complete / Exterior Finish Complete
complete exterior siding and trim
PASS
Jack posts in basement lagged at top and
bottom
PASS
General Comments
8/3/23 final residential inspection not approved, please address the items
listed below and call for recheck.
- provide an updated manual S & J showing the change to geo thermal
heating and cooling equipment.
- provide third party sign off for installation of geo thermal heating system
-a final inspection by the Fire Marshal for the wood burning stove is
required
-condensate line can not drain into the floor drain in basement.
-thermostat needs installed in main house.
-provide blower door test results.
-provide proof of final electrical inspection.
-basement ceiling will need to be sheet rocked or an approved thermal
barrier to cover insulation.
complete exterior trim, siding, and soffits.
complete interior trim, installation of doors, and work at upstairs
bathroom.
-ridged insulation at exterior of foundation will need to be covered or cut
below grade.
- A final inspection by Code Compliance Officer Bruce frank will be
required.
8/9/23 partial approval for final inspection.
-Approved for temporary certificate of occupancy only. complete the items
listed below for final approval
- provide a updated manual S&J showing the change to geo thermal
heating and cooling system
- Provide third party sign off of installation of geo thermal systems,
- condensate line cannot drain in to floor drain in basement.
- install thermostats in there permanent locations.
- Basement ceiling will need to be sheet rocked or have an approved 20
minute thermal barrier installed to cover the insulation.
- Complete exterior trim siding and soffits.
- complete interior trim, install doors, work in up stairs bath room, install
permanent guards at stairs and loft at second floor.
- ridged insulation at exterior foundation will need to be covered or cut
below grade.
- final approval from Code Compliance Officer Bruce Frank
2/8/24 partial approval for final residential inspection.
- provide updated manual S& J for changes at the heating system
- provided third party sign off for the geothermal heating system that was
installed by the homeowner
- final inspection and sign off from Zoning dept.
3/6/24 final inspection for single family dwelling approved.
all items listed above have been completed/received.
PASSN/O
Handrail 4 or more risers
PASS
Handrail Termination at Newell Post or
Wall
PASS
HRV or ERV Installed per Bedroom
Requirements
PASS
Grade away from foundation: 6" down,
10' out
complete site work
PASS
Carbon Monoxide Detectors:
PASS
4+ Deck Joist Ledger Connections-24"
From Ends
PASS
Wood deck: 2'+ from grade dia bracing
required
PASS
Furnace/Hot Water Heater operating
PASS
OK to Issue Temporary C/O
PASS
Not less than 3' horiz from opening of
bthrn
PASS
Arc Fault Breaker Habitable Spaces
PASS
Bathroom Fans, if no window
PASS
Outside Spigots have Air Gap
PASS
3" Plumbing Vent through roof minimum
18 inch
PASS
Duct work sealed properly
PASS
Fin Elect; Energy Saving Light Bulbs 90
Percent
common wealth
PASS
All Hot Water Systems: 3/4" or larger
piping R-3
PASS
Gas Shut-off Exposed & Regulator 12"
min abv grd
PASS
6" clearance to sill plate
PASS
Interior privacy/trim/doors/main entrance
36
PASS
Outside every bedroom area
PASS
Blower Door Test Certification
PASS
Guard at deck, porches 36" or more
PASS
Dryer Duct Max Length 35', Labeled Over
35'
PASS
Every level, Every bedroom
PASS
within 10' of all sleeping areas
PASS
Bathroom / Kitchen Watertight
complete up stairs bathroom
PASS
Relief Valve ,Heat Trap/Water Temp 110
deg or less
PASS
Fresh air supply 3' from grade
PASS
Platform at all exterior doors
PASS
Window guards req:<2' above floor/6'
above grade
PASS
Deck Ledger-Bolted per Code
PASS
4 inch Building Number Address visible
from road
PASS
Foundation insulation to floor
PASS
Plumbing fixtures
complete work at upstairs bathroom
PASS
Fresh Air Intake
PASS
Emergency egress below grade
walk out basement
PASS
Mark Smith