GFNB Building Dept Response_sm Page 1 of 3 Date: March 4, 2024 To: Queensbury Building Department Re: Glens Falls National Bank Queensbury Renovation Permit Set Review Building Department Comments: 1. Provide the name of the company to perform the HVAC Air Balancing Testing and submit the final report. Per the documents, the HVAC air balancing and testing will be by the Contractor. 2. Submit all documentation for all geothermal work (field reports and approvals) completed in preparation for the work in the building to commence. See attached documents:  Spec Section 23 21 14 Geothermal Heat Pump Piping and Vertical Heat Exchangers, Friedman Fisher Associates  Drawing M100 Site Geothermal Plan, Friedman Fisher Associates  Drawing M601 Details, Friedman Fisher Associates  Ground Loop Design Thermal Conductivity Report – 2/23/2023, Gaia Geothermal  International Ground Source Heat Pump Association membership for David Rosick, Rosick Well Drilling. 3. Provide the name of the design professional responsible for submitting the mechanical and electrical commissioning documentation. Per the exception in paragraph C408.2 of the 2020 NYS Energy Code, this project does not require a commissioning agent. The cooling capacity is 300,000 Btu/h, which is below the 480,000 Btu/h threshold, and the heating capacity is 400,000 Btu/h, which is below the 600,000 Btu/h threshold. 4. Submit all asbestos survey and abatement documentation for the project along with the licenses for the asbestos survey company and asbestos removal contractors along with worker's compensation insurance documentation. See attached “Report of Limited Asbestos and Hazardous Materials Inspection,” dated January 8, 2024, by Alpine Environmental Services, Inc., including licenses. Asbestos removal contractor licenses, insurance, and worker’s compensation will be submitted by the contractor. 5. Review the attached Fire Marshal's Plan Review Documentation. See below. Page 2 of 3 6. Submit structural calculations for structural modifications from Ted Prime at SRA Engineers along with a letter stating that Ted Prime will be performing structural inspections for this scope of work. See attached documents:  “Structural Calculations For Renovation” by SRA Engineers  Letter from SRA Engineers 7. Please sign the building permit application. – Will do. 8. The awarded contractor will need to provide all worker's compensation insurance documentation for them and all subcontractors. The Contractor will provide this before pulling the permit. 9. On sheet A700 please add to your stair note regarding the 12" extensions that the ends of the extensions need to return on themselves, newel post or into a wall, no butt ends exposed. Note added to A-700, attached. 10. Pay building permit fee of $3279.50 (Invoice #2024-009) at the Town of Queensbury. The Contractor will pay the permit fee. Fire Marshal Comments: 1. Verify storage. Proper clearance will be provided at all MEP equipment; occupant storage is in separate spaces. 2. Verify operation of exit/emergency lights w/own breaker. The emergency lights and exit lights are not circuited to their own breaker. They are circuited to the lighting circuit serving the room where they are located to comply with NEC Article 700 Emergency Systems Part III Sources of Power: 700.12 General Requirements (F) Unit Equipment (2) Installation of Unit Equipment (3): The branch circuit feeding the unit equipment shall be the same branch circuit as that serving the normal lighting in the area and connected ahead of any local switches. 3. Verify locks/latches according to the 2020 NYSFC. All egress doors have panic hardware, as called out on A-600, door schedule. Page 3 of 3 4. Verify fire extinguisher locations. The fire extinguishers are shown on the plans A-100 and A-101, attached. 5. Verify paths of egress during construction. Paths of egress for the Contractor and Bank staff and customers are shown on PH-001, attached. 6. UL Rating on wall along stair wall. The UL rating for the cmu infill above the existing block walls at the stair will be UL no. 906. This will apply to the infill courses above the existing block walls at the stairs and the north wall of hall 211. The existing block walls of the mechanical room (south wall in hall 211) go to the deck. 7. Knox Box 3200 series needed for outside and Elevator Knox box needed next to elevator. The specific Knox Box types have been called out on A-101, attached. 8. Truss ID required. The truss ID has been called out sheet A-001, attached. 9. CO Detection required. CO detectors are indicated outside the mechanical room on each floor, shown on sheet SC-100 by Mahoney Alarms. 10. Protection of the fire alarm system during construction according to the 2020 NYSFC Chapter 33. A note calling for the protection of the fire alarm system has been added to sheet D-001, attached. 11. NFPA 72 letter of compliance. A letter of compliance will be provided by Mahoney Alarms prior to C of O. 12. Provide documents for fire alarm system for review before installation. These documents will be submitted by Mahoney Alarms. GLENS FALLS NATIONAL BANK QUEENSBURY BRANCH Oldenquist Design 23 21 14 - 1 GEOTHERMAL HEAT PUMP PIPING AND VERTICAL HEAT EXCHANGERS SECTION 232114 GEOTHERMAL HEAT PUMP PIPING AND VERTICAL HEAT EXCHANGERS PART 1 – GENERAL 1.01 SECTION INCLUDES A. Ground-coupled heat exchanger and connections to building piping system. 1.02 REFERENCE STANDARDS A. APHA (EWWW) - Standard Methods for the Examination of Water and Wastewater; 2017 (23rd Edition). B. ASTM D2683 - Standard Specification for Socket-Type Polyethylene Fittings for Outside Diameter-Controlled Polyethylene Pipe and Tubing; 2014. C. ASTM D2837 - Standard Test Method for Obtaining Hydrostatic Design Basis for Thermoplastic Pipe Materials or Pressure Design Basis for Thermoplastic Pipe Products; 2013, with Editorial Revision (2014). D. ASTM D3035 - Standard Specification for Polyethylene (PE) Plastic Pipe (DR- PR) Based on Controlled Outside Diameter; 2015. E. ASTM D3261 - Standard Specification for Butt Heat Fusion Polyethylene (PE) Plastic Fittings for Polyethylene (PE) Plastic Pipe and Tubing; 2016. F. ASTM D3350 - Standard Specification for Polyethylene Plastics Pipe and Fittings Material; 2014. G. ASTM F714 - Standard Specification for Polyethylene (PE) Plastic Pipe (DR-PR) Based on Outside Diameter; 2013 (Reapproved 2019). H. ASTM F1055 - Standard Specification for Electrofusion Type Polyethylene Fittings for Outside Diameter Controlled Polyethylene and Crosslinked Polyethylene (PEX) Pipe and Tubing; 2016a. I. IGSHPA (GROUT) - Grouting Procedures for GHP Systems; International Ground Source Heat Pump Association; 1991. J. PPI TR-4 - PPI Listing of Hydrostatic Design Basis (HDB), Hydrostatic Design Stress (HDS), Strength Design Basis (SDB), Pressure Design Basis (PDB), and Minimum Required Strength (MRS) Ratings For Thermoplastic Piping Materials or Pipe; 2017. K. ANSI/CSA/IGSHPA C448 Series-16 - Design and installation of ground source heat pump systems for commercial and residential buildings GLENS FALLS NATIONAL BANK QUEENSBURY BRANCH Oldenquist Design 23 21 14 - 2 GEOTHERMAL HEAT PUMP PIPING AND VERTICAL HEAT EXCHANGERS 1.03 ADMINISTRATIVE REQUIREMENTS A. Preinstallation Meeting: Convene one week before starting work of this section. Require attendance by all installers involved with site work and HVAC work. 1.04 SUBMITTALS A. Product Data, Polyethylene Piping: Provide manufacturer's data for piping and pipe fittings, showing compliance with specified requirements. 1. Provide manufacturer's recommendations for fusion jointing. 2. Include certification of long term hydrostatic basis, or test reports. B. Product Data, Heat Exchange Fluid: Provide data showing compliance with specified requirements. 1. Provide manufacturer's Material Data Safety Sheets. 2. Provide results of biodegradability studies conducted in accordance with APHA (EWWW): a. Statement of ecological behavior. b. Total oxygen demand, in pounds (kg) of oxygen per pound (kg) of fluid. c. Percent of fluid degraded in five days. C. Product Data, Grout and Slurry: Provide information including thermal conductivity, density, mixture, etc of proposed materials. D. Product Data, Interior Valves and fittings: Provide information on valves and fittings to be used inside the building. Refer to other Division 23 technical specifications for interior piping, valves, fitting, gauges and insulation requirements. E. Shop Drawings: Show complete piping layout, depths of excavation, final depths of piping, backfill placement, point of entrance to building, test point locations, and fittings used for all joints and connections. F. Test Reports, Piping: Indicate test method and results of hydrostatic pressure tests. G. Record Documents: Record actual locations of all underground piping installed relative to Owner's permanent structure on same property. H. Weekly Drilling Progress: Monday of each week provide a progress report of the geothermal field installation. Report drilling progress, u-bend installation depth, and pressure testing log. 1.05 QUALITY ASSURANCE A. Installer Qualifications: Company specializing in performing the work of this section with minimum five years of documented experience and accredited by IGSHPA. GLENS FALLS NATIONAL BANK QUEENSBURY BRANCH Oldenquist Design 23 21 14 - 3 GEOTHERMAL HEAT PUMP PIPING AND VERTICAL HEAT EXCHANGERS B. Well driller qualifications: Geothermal well drillers shall have a minimum of five years’ experience in the installation of geothermal well field installation and shall be licensed in the jurisdiction where the project is located. C. Heat Fusion Technician Certification: IGSHPA training and certification, certified within three years from the date of project commencement. D. During the installation, trash, soil and small animals shall be kept out of the pipe. Extra care shall be taken to avoid contamination of the loop by vandalism or other means of contamination. Ends of the pipe shall be sealed with fusion end- caps until the pipe is joined to the manifold circuit. Taped, clamped or other mechanical sealing methods of pipe ends are not acceptable. E. Contractor shall utilize appropriate mud recycling equipment to eliminate potential of flooding job site with mud and drill cuttings. F. The contractor shall lock and secure their equipment and storage areas. The Owner shall not be held responsible for loss of damage of any contractor's equipment, tools, materials or personal effects. 1.06 DELIVERY, STORAGE, AND HANDLING A. Deliver piping and fittings to project site in shipping containers with labeling in place. 1. Verify that labels on piping indicate manufacturer's name, pipe or tube size, pressure rating, relevant ASTM standards, PE cell classification number, and date of manufacture. 2. Verify that piping complies with specifications and is undamaged. B. Deliver chemicals for heat exchange fluid to project site in unopened shipping containers with labeling in place; comply with local and state regulations. C. Protect from weather, humidity and temperature variations, dirt and dust, and other environmental contaminants. Palletized bentonite grouting materials are to be protected from the weather with a protective covering, to the satisfaction of the Engineer. D. Store piping capped or plugged until time of installation. 1.07 PROJECT CONDITIONS A. Existing utilities: do not interrupt utilities serving facilities occupied by the owner or others unless permitted by the affected parties and then only after arranging to provide temporary utility services according to the requirements indicated: 1. Notify the owner not less than two days in advance of proposed utility interruptions. 2. Well drilling water: contractor shall be responsible for providing water for the drilling purpose. 3. Well driller shall be responsible for removing all drilling mud, fluid and waste material generated by drilling operations. 4. Reasonable care shall be taken to avoid damage to tree roots and canopies, especially those over 6" in diameter. GLENS FALLS NATIONAL BANK QUEENSBURY BRANCH Oldenquist Design 23 21 14 - 4 GEOTHERMAL HEAT PUMP PIPING AND VERTICAL HEAT EXCHANGERS PART 2 - PRODUCTS 2.01 WELL CASING A. Well casings: AWWA C200, single ply, steel pipe with threaded ends and threaded couplings for threaded joints. 2.02 HEAT EXCHANGER A. Install the ground-coupled heat exchanger as designed and laid out on the Contract Documents. B. Heat Exchanger Configuration: Closed system; high density polyethylene piping in vertical boreholes located as indicated on drawings. 1. Pipe Type: SDR11 High density polyethylene. 2. Pipe Diameter: 1-1/4 inch. 3. Shank Spacing: 1/8 inch. 4. Borehole Depth: 450 feet. 5. Borehole Diameter: 6 inches . 6. Borehole Spacing: 20 feet, minimum. 7. Total Number of Boreholes: 10 total bore holes. 9 new bore holes. The “10th” bore hole (A1) is existing via the thermal conductivity test conducted February 2023. 2.03 MATERIALS A. Pipe: High density polyethylene pipe, type PE4710, ASTM D 3035, DR 11. 1. Comply with ASTM D 3035 with minimum working pressure rating of 200 psi at 73 degrees F. 2. ASTM D3350 cell classification PE445574C 3. Long Term Hydrostatic Design Basis: 160 psi at 73 degrees F, when tested in accordance with ASTM D2837; appropriate listing in current edition of PPI TR-4 will constitute evidence of compliance with this requirement; otherwise, submit independent test results. 4. Joints and Fittings: Polyethylene of same type as pipe, of sizes and types suitable for the pipe being used; use only heat fusion that are quality controlled to provide a leak-free union between piping ends that is stronger than the piping itself. Do not use other barbed fittings or hose clamps. a. Electrofusion Type Fittings: Comply with ASTM F1055. b. Butt Fusion Fittings, 1-1/2” pipe and above: Comply with ASTM D3261. c. Socket Type Fittings, up to 1-1/4” pipe: Comply with ASTM D2683. d. Where threaded fittings must be used for connection to equipment or dissimilar piping, use fittings and thread sealant compatible and effective with antifreeze used. e. Provide pre manufactured, molded U-bend at bottom of vertical bore designed for geothermal application. GLENS FALLS NATIONAL BANK QUEENSBURY BRANCH Oldenquist Design 23 21 14 - 5 GEOTHERMAL HEAT PUMP PIPING AND VERTICAL HEAT EXCHANGERS B. Heat Exchange Fluid: Water and antifreeze solution, 30 percent propylene glycol by weight. C. Detectable Underground Tape: 1. Magnetic detectable conductor in 2 inch (50 mm) wide rot-resistant plastic tape or mesh, brightly colored, imprinted with "CAUTION GEOTHERMAL PIPELINE BURIED BELOW” in large letters. 2. The contractor shall provide stranded tracer wire from within the mechanical room, on one leg of each header pair (loop), to the last borehole on each header pair loop. The stranded wire shall be of sufficient overall gauge to activate by electric charge and be located by surface instrumentation at the maximum depth of the installed header piping, or at an acceptable depth as prescribed by the manufacturer. D. Grout for Vertical Boreholes: Thermally-enhanced bentonite/high-grade silica sand grouting compound with a minimum thermal conductivity value of 1.6 btu/hr-ft-°f as determined when tested in accordance to ASTM D 5334. Grout mixture shall have a maximum permeability rate of less than 1x10^-7/ cm/s as determined by ASTM D 5084. Grout mixture shall be geo-pro TGlite 1.6 or approved equal with a maximum density of 10.5 lb/gal. E. Interior piping, valves and fittings: Refer to Division 23 specification sections for interior piping, valve, fittings, gauges and accessories. F. Header pairs in the mechanical room shall include signage or tags corresponding to each header pair designation as described on the ground heat exchanger site plan (i.e., Header Pair A, Header Pair B). PART 3 - EXECUTION 3.01 EXCAVATION A. Excavate in accordance with requirements of authorities having jurisdiction. B. Remove rock as required to achieve specified depths. C. Vertical Boreholes: Drill to depths as detailed on contract drawings. 1. Provide continuous steel casing on upper portion of borehole until bedrock is reached. Casing is not required within bedrock. 2. Set casings within bores plumb and true to line. 3. Piping: Assemble heat exchanger piping and test before grouting and covering. D. Trenches: Excavate trenches for piping to lines and grades shown on drawings. 1. Excavate to accommodate grade changes. 2. Maintain trenches free of debris, material, and obstructions that may damage pipe. 3. Piping: Assemble heat exchanger piping and test before backfilling and paving parking lot. GLENS FALLS NATIONAL BANK QUEENSBURY BRANCH Oldenquist Design 23 21 14 - 6 GEOTHERMAL HEAT PUMP PIPING AND VERTICAL HEAT EXCHANGERS 3.02 POLYETHYLENE PIPING A. Join piping and fittings using heat fusion or electrofusion; do not use solvents, adhesives, or mechanical fittings. B. Provide flanges or unions to connect heat exchanger piping to equipment or piping of different type within the mechanical room where indicated; locate all transitions between piping of different types inside the building or otherwise accessible (i.e. above grade). C. Keep dirt and debris out of pipe assemblies; cap or plug open ends until connected to adjacent piping. D. Do not bend piping to shorter radius than recommended by pipe manufacturer; do not kink piping; use elbow or other fittings for sharp bends. E. Partially backfill radius bends in narrow trenches by hand to ensure that piping is properly supported and to prevent kinking. F. The loop tubes and the tremie pipe shall be installed into the vertical borehole heat exchanger the same day the vertical borehole heat exchanger is constructed. 3.03 GROUTING A. After installation and testing of piping within bore, place grout continuously, from bottom to top surface to ensure filling of annular space in one operation. B. The loop tube shall be pressurized with water during the entire grouting process to protect it against shear forces caused by the grout. The hydrostatic pressure level shall be adapted with grout density and borehole depth. C. Grout shall be placed in the borehole by pressure pumping through a tremie pipe after enough water or other drilling fluid has been circulated in the annular space to clear obstructions; D. Tremie grouting of the entire vertical borehole using the grout material specified and shall be completed within a timeframe to ensure total loop well grouting and ensure aquifer protection; E. The tremie pipe shall be lowered to the bottom of the borehole, raised slowly as the grout is introduced and should be continuously submerged in the grout. F. Once the grout has settled for a minimum of 48 h, the ground source heat pump system contractor shall ensure that the vertical borehole heat exchanger(s) are filled with grout to the top of the vertical borehole heat exchanger; and regular verification of the grout mixture shall be carried out as follows: 1. Verification of grout mix ratio, mixing procedures, grouting, and topping off of vertical borehole heat exchanger with grout shall be undertaken on an ongoing basis during ground source heat pump installation GLENS FALLS NATIONAL BANK QUEENSBURY BRANCH Oldenquist Design 23 21 14 - 7 GEOTHERMAL HEAT PUMP PIPING AND VERTICAL HEAT EXCHANGERS 2. Density and water content, or alternatively, grout thermal conductivity of the samples, shall be measured to ensure the grout mixture is in accordance with the specified grout recipe. 3.04 TESTING A. At several stages of the installation the pipe installed shall be pressure tested with result documented and turned over to owner and engineering for approval. If deficiencies are found, the point of leakage shall be found, repaired and test repeated. This procedure shall be followed until the piping systems have been proved absolutely tight. B. Caution shall be exercised to prevent direct sunlight or significant air temperature changes from affecting the results. C. The use of any chemicals, any "Stop-Leak" compounds, any mastic or any other temporary means shall not be used for repairing leaks during or subsequent to these tests. D. Pressure tests for polyethylene pipes shall be conducted in accordance with ASTM F2164, which provides information on apparatus, safety, pre-test preparation, and procedures for conducting field tests of PE pressure piping systems by filling them with a liquid and applying pressure to determine if leaks exist in the system. E. The duration of the pressure test shall be no less than 1 h after the stabilization of pressure. If no visual leakage is observed and pressure during the test phase remains steady (within 5% of the test phase pressure), a passing test is indicated. F. Loops must pass the test at the following milestone: 1. Prior to insertion of the vertical piping into the bore holes, the contractor shall assemble the "U-Bend" and piping, cap both ends, and pressure test the piping to a pressure of 100 psig. Reduce pressure to 0 psig before lowering into borehole. 2. After each runout has been assembled, including connection to the grouted vertical borehole heat exchangers and before backfilling, test piping to a pressure of 50 psig. 3. After the complete ground-heat exchanger has been installed, flushed, and purged of air and debris and before the ground heat exchanger has been filled with glycol connected to the building system, test piping to a pressure of 50 psig. G. Contractor is responsible to provide evidence of and certification of pressure testing, and acceptance of all work performed by signature of contract inspector. H. After the conclusion of the ground heat exchanger pressure test, the ground heat exchanger shall be left filled with ultimate fluid to be used in the system and be maintained under pressure until final connection to the building system. 3.05 FLUSHING, PURGING AND CHARGING GLENS FALLS NATIONAL BANK QUEENSBURY BRANCH Oldenquist Design 23 21 14 - 8 GEOTHERMAL HEAT PUMP PIPING AND VERTICAL HEAT EXCHANGERS A. All geothermal piping systems shall be thoroughly cleaned before placing in operation to rid the system of dirt, piping compound, mill scale, oil, and any and all other clean and balance the piping installed under his contract. B. Extreme care shall be exercised during construction to prevent all dirt and other foreign matter from entering the pipe or other parts of the system. Pipe stored on the project to have the open ends capped and equipment to have all openings fully protected. Before erection, each piece of pipe, fittings, or valve to be visually examined and all dirt removed. C. The ground heat exchanger shall be flushed with potable water by means of a flushing unit equipped with a tank for air separation, suitable filters, a water flow meter, pressure gauges and valves to reverse the flow. All flushing flow shall pass through a suitable filter until the water is observed to be clear and clean. D. Each supply and return circuit shall be flushed and purged in the forward and reverse directions with water at a minimum velocity of 2 ft/s through each piping section. A calibrated flow meter shall be used to verify the flow velocity. E. To verify the effectiveness of a purge, the valve leaving the borehole field shall be closed while monitoring the make-up water level in the purge tank. If the level does not go down, there is little air in the system. The system should be pressurized to 50 psig after purging is complete. When the borehole field is connected to the system the residual pressure will ensure that the system is intact and that no air has been introduced into the system. F. Prior to specifying water treatment and selecting an anti-freeze solution for the system, a sample of the local water shall be analyzed to identify existing local water chemistry. Where applicable and permitted by the authority having jurisdiction, the heat transfer fluid may contain chemical inhibitors to protect the biological and chemical integrity of the solution to prevent corrosion of system pipes. G. Charge system with specified glycol mixture after all testing, flushing and purging has occurred and been accepted by the owner. H. Install system label at purging valves, indicating: 1. Heat exchange fluid, including antifreeze type and concentration. 2. Service date. 3. Company name. 4. Company phone number and responsible person. 5. Geothermal Loop Served. 3.06 BACKFILLING A. Install in compliance with local authorities having jurisdiction. B. Vertical Boreholes: Backfill after pipe installation in accordance with IGSHPA (GROUT) - IGSHPA Grouting Procedures for GHP Systems. C. Trenches: GLENS FALLS NATIONAL BANK QUEENSBURY BRANCH Oldenquist Design 23 21 14 - 9 GEOTHERMAL HEAT PUMP PIPING AND VERTICAL HEAT EXCHANGERS 1. Provide minimum 5 foot cover over piping. 2. Backfill trenches after pipe has been installed and tested, using fill free of rocks and other debris. 3. Install detectable tape continuously 6 inches (150 mm) above top of all buried pipe. 4. Install Tracer wire from header in mechanical room to the last bore in the geothermal loop. 5. Backfill and compact using the procedures specified. 6. Backfill to original grades with sufficient overfill to allow for settlement. D. Protect piping from displacement. 3.07 CLEANING A. Leave adjacent paved areas broom clean. B. Clear debris, including excess backfill and excavated dirt and rock, from heat exchanger area. 3.08 PROTECTION A. Protect area during excavation from excess runoff and erosion. Ensure that mud pit will not leak or overflow into streams or wetlands. When the well is accepted, remove mud and solids in mud pit from project site and restore site to finished grade. B. Provide casings, seals, sterilizing agents, and other materials to eliminate contamination. C. Protect pipe protrusions from damage until connections to building systems are installed. 3.09 IDENTIFICATION A. Install continuous underground detectable warning tape for underground piping. Locate below finished grade, directly over piping. END OF SECTION CIRF CMF IPFCIRF CIRF IRF (Bent) CIRF (Bent) IRF IRF (Bent) IRF (Bent) Two S t o r y Bric k B u i l d i n g "G l e n s F a l l s N a t i o n a l B a n k " #69 6 G l e n S t r e e t WV WV WV WV T T T Adj o i n e r ' s B u i l d i n g Co n c . Blo c k Bld g . TV U.P. NM 30-A U.P . N M 3 0 U.P. NM 30-1 U.P. NM 1 U.P. U.P. 3-1 TV Ga s M e t e r Traffic Pole Cross Walk Signal Traffic Signal Box Traffic Signal Box LP ICV 24" Maple Access Cover Flag Pole ICV Wood Post Sign Do Not Enter Telecomm. Pedestal Tel e c o m m . Pe d e s t a l Cable TV Pedestal Telec o m m . Pede s t a l Hydrant Guar d R a i l Cable TV Pedestal Sign Sign-30 MPH Hy d r a n t CB CB CB CB LP LP Ro o f O v e r h a n g Co n c r e t e Cr o s s w a l k U.P. NM31 ICV ICV Sign Ove r h a n g Con c r e t e W a l k Co n c r e t e S i d e w a l k As p h a l t Sign Mail Box Sign-One Way Sign Sign-One Way Asp h a l t 6" Box SSAC Elec. Box CB Lands N/F of Carlo Cedrone B:1200 P:199 302.7-1-23 Lands N/F of CKT Enterprises, LLC B:5527 P:297 302.7-1-24 Lands N/F of CKT Enterprises, LLC B:5527 P:297 302.7-1-25 Lands N/F of CKT Enterprises, LLC B:1379 P:203 302.7-118 U.P. NM3 U.P. NM 30-2 SSAC SSAC HCAP Sign Blu e P i n F l a g s Gr e e n P i n F l a g s Yell o w P a i n t L i n e Yell o w P a i n t L i n e Gr e e n P i n F l a g s Ora n g e P i n F l a g s / P a i n t L i n e Ora n g e P a i n t L i n e Red P a i n t L i n e Ora n g e P a i n t L i n e Red P a i n t L i n e Re d P a i n t L i n e Red P a i n t L i n e Asp h a l t P a r k i n g Wood Post Yel l o w P a i n t L i n e TOTAL (10) BORE HOLES - PROVIDE (9) BORE HOLES: 6" DIAMETER, 450 FEET DEEP, MINIMUM 20'-0" SEPARATION, 1-1/4" VERTICAL HEAT EXCHANGERS, GROUT WITH MINIMUM 1.6 (BTU/HR*FT*°F) CONDUCTIVITY, AND A DESIGN FLOW RATE OF 8.2 GPM EACH. PROVIDE STEEL BORE CASING DOWN TO BEDROCK AT APPROXIMATELY 80'-0" 20' - 0 " M I N . (T Y P I C A L ) 20'-0" M I N . (TYPIC A L ) BORE HOLE SEPARATION RADIUS (TYPICAL) EXISTING (1) CONDUCTIVITY TEST BORE HOLE: - 450'-0" BORE DEPTH - 1-1/4" VERTICAL HX - 1.6 (BTU/HR*FT*°F) GROUT CONDUCTIVITY - THERM. COND. PER TEST = 2.0 BTU/(H*FT*°F) - THERM. DIFFUSIVITY (EST) PER TEST = 1.27 FT^2/DAY - UNDIST. GROUND TEMP PER TEST = 51.3 °F 1 A1 A2 A3 A4 A5 B1 B2 B3 B4 B5 3" GWR & 3" GWS 3" GWS & 3" GWR 3" GWS 2" GWS 1-1/2" GWS 1-1/4" GWS 1-1/4" GWR 1-1/2" GWR 2" GWR 3" GWR 2 3 REMOVE PAVED PARKING LOT TO ALLOW FOR GEOTHERMAL BORE FIELD INSTALLATION. PROVIDE NEW PAVED PARKING LOT, INCLUDING LINE PAINTING AS DIRECTED BY THE OWNER'S REPRESENTATIVE, AFTER GEOTHERMAL BORE FIELD INSTALLATION IS COMPLETE. PARKING LOT IS APPROXIMATELY 6,500 SQFT. A2203 2023-03-17 AS NOTED GEOTHERMAL WELL PACKAGE 2023-05-10 THIS DOCUMENT CONTAINS COPYRIGHTED MATERIAL BELONGING TO OLDENQUIST DESIGN. UNAUTHORIZED USE, DISSEMINATION, OR DUPLICATION OF THESE DRAWINGS MAY RESULT IN LIABILITY UNDER APPLICABLE LAWS. Glens Falls National Bank 696 Upper Glens St. Queensbury, NY Oldenquist  Design  ARCHITECTURE AND PLANNING BAR EQUALS ONE INCH WHEN DRAWING IS PRINTED TO SCALE 1" NORTH M100 SI T E G E O T H E R M A L P L A N GENERAL NOTES 1.COORDINATE UTILITY SHUT DOWNS WITH THE FACILITY. GEOTHERMAL FIELD INSTALLATION SHALL NOT EFFECT THE OPERATION OF THE FACILITY. EQUIPMENT, DEVICES, DEBRIS, MATERIALS, ETC. SHALL BE KEPT WITHIN THE BORE FIELD PARKING LOT AS ACCEPTABLE BY THE OWNER'S REPRESENTATIVE. 2.FIELD VERIFY UNDERGROUND UTILITIES AND OBSTRUCTIONS THAT MAY PROHIBIT THE GEOTHERMAL SYSTEM FROM BEING INSTALLED AS DESIGNED PRIOR TO STARTING CONSTRUCTION AND SUBMIT TO ENGINEER OF RECORD FOR REVIEW. 3.REFER TO GEOTHERMAL LOOP "B" FOR HORIZONTAL UNDERGROUND PIPE SIZES, GEOTHERMAL LOOP "A" SIMILAR. 4.THE CONTRACTOR SHALL BE RESPONSIBLE FOR MANAGING, CONTAINING, FILTERING, AND DISPOSING OF WATER/MUD/RUNOFF DUE TO THE DRILLING PROCESS. WATER/MUD/RUNOFF FROM THE DRILLING PROCESS SHALL BE CONTAINED TO THE ±6,500 SQFT PARKING LOT IN WHICH THE BORE FIELD IS BEING INSTALLED DURING THE ENTIRETY OF THE PROJECT. IN THE EVENT THERE IS ACCESS WATER/MUD/RUNOFF THAT CANNOT BE CONTAINED IN THE PARKING LOT AREA, THE CONTRACTOR SHALL BE RESPONSIBLE FOR A MEANS TO REMOVE, TRANSPORT, AND DISPOSE OF THE ACCESS WATER/MUD/RUNOFF. COMPLY WITH ALL LOCAL, STATE, AND FEDERAL LAWS AND REGULATIONS. 5.THE CONTRACTOR SHALL BE RESPONSIBLE TO PROVIDE THEIR OWN WATER SOURCE FOR DRILLING, CLEANING, ETC. PURPOSES. THE CONTRACTOR SHALL BE RESPONSIBLE TO PROVIDE THEIR OWN GENERATOR FOR ANY POWER REQUIREMENTS ASSOCIATED TO WORK COMPLETED UNDER THIS CONTRACT. SITE PLAN SCALE: 1/32" = 1'-0"1PL O T T E D : 5 / 9 / 2 0 2 3 1 0 : 2 6 : 4 5 A M SA V E D : 5 / 9 / 2 0 2 3 1 0 : 2 6 : 2 6 A M US E R : C H R I S T O P H E R S T R O M FI L E : R : \ P R O J E C T S \ 8 1 1 7 - G L E N S F A L L S N A T I O N A L B A N K U P P E R G L E N S T R E N O \ _ C A D \ 8 1 1 7 - M 1 0 0 . D W G KEYED NOTES TERMINATE THE GEOTHERMAL PIPING WITHIN THE GRASS AREA OUTSIDE THE BOUNDS OF THE PARKING LOT AND DRIVE-WAY, COORDINATE EXACT LOCATION WITH FIELD CONDITIONS AND OWNER'S REPRESENTATIVE. PRESSURE TEST THE GEOTHERMAL PIPING PRIOR TO TERMINATING PIPE ENDS. TERMINATE GEOTHERMAL PIPING ABOVE GRADE AND FUSE A CAP ON THE END OF THE PIPING TO PREVENT DIRT/DEBRIS/ETC. FROM ENTERING THE SYSTEM. PAINT THE EXPOSED GEOTHERMAL PIPING SAFETY ORANGE. PROVIDE TAG FIXED TO EACH PIPE TERMINATED ABOVE GROUND WITH THE LOOP THAT THE PIPE SERVES ("A" OR "B"). SUBMIT SCALED SHOP DRAWINGS SHOWING THE LOCATION OF FINAL PIPING LOCATIONS, WITH DIMENSIONS FROM LANDMARKS. PROVIDE UNDERGROUND TRACER WIRE ABOVE EACH GEOTHERMAL PIPE HEADER FROM THE LAST BORE HOLE IN EACH GEOTHERMAL LOOP TO THE TEMPORARY TERMINATION LOCATION SHOWN. SAFE OFF WIRING FOR FUTURE CONTINUATION INTO THE BUILDING MECHANICAL ROOM. PIPING ORIENTATION SHOWN IS DIAGRAMMATIC, REFER TO GEOTHERMAL DETAILS FOR ADDITIONAL INFORMATION. 1 2 3 NOTE: THE INTENT IS TO PROVIDE ALL WORK REQUIRED IN THE PARKING LOT AREA INCLUDING BUT NOT LIMITED TO: REMOVING THE PARKING LOT PAVEMENT AND GRADING BELOW, DRILLING THE BORE HOLES, PROVIDING THE VERTICAL GEOTHERMAL HEAT EXCHANGERS, PROVIDING THE HORIZONTAL UNDERGROUND GEOTHERMAL PIPING, PRESSURE TESTING THE GEOTHERMAL PIPING, TERMINATING THE PIPING IN AN ACCESSIBLE LOCATION NOT WITHIN THE PARKING LOT, AND PROVIDE A NEW PAVED PARKING LOT. MECHANICAL LINE TYPES LINE TYPES & ABBREVIATIONS DESCRIPTION GLYCOL GEOTHERMAL WATER SUPPLY PIPING (SIZE AS INDICATED) GLYCOL GEOTHERMAL WATER RETURN PIPING (SIZE AS INDICATED) 2" GWS 2" GWR MECHANICAL SYMBOLS LEGEND VALVES AND PIPING ACCESSORIES DIRECTION OF FLUID FLOW PIPE DOWN PIPE UP PIPE CONCENTRIC REDUCER 6"±6"± MINIMUM 1'-0" RESTORE TO EXISTING CONDITION OR AS DIRECTED BY THE OWNER AND ENGINEER UNDISTURBED MATERIAL SEPARATION BACKFILL WITH SUITABLE MATERIAL PIPE ZONE FINE BACKFILL 1/2" O.D. ± 1'-0" MIN. PIPE ZONE BEDDING 1/2" O.D. ± 8" 5'-0" MIN FOR ALL PIPING GWR MAINS GWS MAINS SLOPE TRENCH AS REQUIRED TRACER WIRE (TYP) PROVIDE 4" OF EXTRUDED POLYSTYRENE RIGID FOAM INSULATION (R-20) AT UTILITIES CROSSINGS, EXTEND 5'-0" BEYOND ON BOTH SIDES OF CROSSED UTILITIES 6" Ø BORE HOLE GROUTED WITH 1.6 BTU/HR-FT-°F THERMALLY ENHANCED GROUT 1-1/4" SDR 11 HDPE PIPING WITH A 1/8" SHANK SPACING TRANSITION FROM SAND / SILT / CLAY TO LIMESTONE APPROXIMATELY 80' BELOW GROUND LEVEL, VERIFY DEPTH IN FIELD AND EXTEND BORE CASING AS NECESSARY TO DEPTH OF TRANSITION UNDISTURBED SAND / SILT / CLAY LIMESTONE GROUND SURFACE LEVEL PARKING LOT ALL PIPE BENDS GREATER THAN MINIMUM BEND RADIUS PUBLISHED BY APPROVED PIPE MANUFACTURER EXCAVATION LEVEL BACK FILLED WITH MATERIAL AS REQUIRED FOR THE PARKING LOT ABOVE HORIZONTAL PIPE RUN MINIMUM 5'-0" BELOW GROUND LEVEL SEE TRENCH DETAIL FOR ADDITIONAL INFORMATION PRE-MANUFACTURED MOLDED GEOTHERMAL LOOP U-BEND BOTTOM OF BOREHOLE 450' BELOW SURFACE LEVEL STEEL BORE CASING A2203 2023-03-17 AS NOTED GEOTHERMAL WELL PACKAGE 2023-05-10 THIS DOCUMENT CONTAINS COPYRIGHTED MATERIAL BELONGING TO OLDENQUIST DESIGN. UNAUTHORIZED USE, DISSEMINATION, OR DUPLICATION OF THESE DRAWINGS MAY RESULT IN LIABILITY UNDER APPLICABLE LAWS. Glens Falls National Bank 696 Upper Glens St. Queensbury, NY Oldenquist  Design  ARCHITECTURE AND PLANNING M601 DE T A I L S PL O T T E D : 5 / 9 / 2 0 2 3 1 0 : 2 6 : 4 8 A M SA V E D : 5 / 9 / 2 0 2 3 1 0 : 2 4 : 4 6 A M US E R : C H R I S T O P H E R S T R O M FI L E : R : \ P R O J E C T S \ 8 1 1 7 - G L E N S F A L L S N A T I O N A L B A N K U P P E R G L E N S T R E N O \ _ C A D \ 8 1 1 7 - M 6 0 1 . D W G GEOTHERMAL PIPING TRENCH DETAIL SCALE: NOT TO SCALE1 GEOTHERMAL BORE DIAGRAM SCALE: NOT TO SCALE2 Thermal Conductivity Report - 2/23/2023 Ground Loop Design Thermal Conductivity (Btu/(h*ft*°F)) : Average Heat Flux (W/ft) : Test Duration (hr) : 2.37 17.9 Calculation Results Borehole Input Parameters Borehole Diameter (in) : Pipe Size: Grout Thermal Conductivity (Btu/(h*ft*°F)) : Drilling Method : Drilling Time (hr) : Undisturbed Ground Temperature (°F) : Depth (ft) : (Measured @ 200 feet) Thermal Diffusivity (est.) (ft^2/day) :1.27 Diffusivity Input Parameters Moisture (0-100) (%) :10 Soil/Rock Specific Heat - Dry (Btu/(°F*lbm)) :0.220 Soil/Rock Density - Dry (lb/ft^3) :160.0 Calculation Interval : Average Flow Rate (gpm) : Flow Rate Input Parameters TC Unit Model Name GeoCube Extended BH Thermal Resist (BTR) (h*ft*°F/Btu) :0.22 8.34 48 22.0 - 48.0 Hours 51.3 460.0 6.00 1 1/4 in. (32 mm) 1.60 Standard 5.0 1 / 6 Recommend using 2.0 TC for design due to potentially unsustainable groundwater impacts that may be seasonal or blinded off by grout during full borefield installation. Drill Date: TC Test Date(s):   Client: Project Name: Testing Conducted By: Aztech Geothermal, LLC John Ciovacco, CGD jciovacco@aztechgeo.com (518) 309-2000 *OHQV)DOOV1DWLRQDO%DQN 6QQFS(MFO4USFFU 2VFFOTCVSZ /: )ULHGPDQ)LVKHU$VVRFLDWHV3& $YLDWLRQ5RDG $OEDQ\, NY 12 Driller: 3PTJDL8FMM%SJMMJOH 'DYH5RVLFN URVLFNGULOOLQJ#\DKRRFRP   to  GLDTM Temperature vs Time Power vs Time Average Power 8214.8 Watts 2 / 6 Temperature vs ln(Time) Average Flow Rate 8.34 Flow Rate vs Time Calculation Interval :22.0 - 48.0 Hours Slope :2.05 3 / 6 Data Quality Temperature : Flow Rate : Slope Stability : Pass PassPower Standard Deviation :Pass Water Flow Test : Pass Pass Threshold 5.00 % 5.00 %1.50 % 25.00 % 20.00 % Power Variation :Pass 10.00 % Threshold Comments Comments 4 / 6 Borehole was stopped at ~470 feet due to excessive ground water in the formation.: 5 / 6 Thermal Conductivity Test Overview The thermal conductivity, or thermal response, test is a way to determine ground thermal properties that are critical for ground source heat pump system design. The test is performed by injecting a known and constant heat power into a borehole heat exchanger and then measuring the temperature response. A competent test can provide the undisturbed formation ground temperature, the calculated thermal conductivity, the calculated borehole thermal resistance and an estimate of the thermal diffusivity. These values, critical for the optimal design of a geothermal system, can be used in a geothermal design program to design an optimized, cost effective system. Test Procedure Recommendations The American Society of Heating, Refrigeration and Air-Conditioning Engineers (ASHRAE) offers a set of procedural recommendations for in-situ thermal conductivity/thermal response tests. These can be found in the ASHRAE 2007 HVAC Applications Handbook. Several of the key recommended procedures are as follows: A) Time between test bore installation and start of TC test: A 5 day minimum wait time is recommended. B) Undisturbed ground temperature measurement: The undisturbed ground temperature should be recorded prior to test start up. C)Test Duration: Test duration typically should be for 48 hours or longer. D) Power Quality: The power standard deviation should be equal to or less than 1.5% of the average power and the maximum power variation should be less than 10% of the average power. The average heat flux should fall within the 15 W/ft to 25 W/ft range to best simulate the expected peak loads in the borehole. Thermal Diffusivity Estimation Thermal Diffusivity may be estimated from a combination of the calculated thermal conductivity value (which is directly related to the diffusivity) in conjunction with estimates of the specific heat, density and moisture content of the test bore. The thermal diffusivity reflects the rate of conductive heat transfer in the soil and helps determine the impact of neighboring borehole interactions on the final geothermal loopfield design. Thermal Conductivity Calculation Because thermal conductivity cannot be measured directly, The Ground Loop Design Thermal Conductivity Module uses the line source heat transfer model to calculate the required results. The line source model, which assumes an infinitely thin heat source in a homogeneous medium, is very broadly-referenced in the published literature and is considered to be the standard analysis methodology. To analyze test data, the average temperature of the water entering and exiting the heat exchanger is plotted versus the natural log of time. Using regression analysis, a best-fit line is plotted to match the empirical data and the slope of the line is used to calculate the thermal conductivity of the formation. Typically, the data analysis procedure may be repeated several times for several different time intervals to ensure the closest fit between the empirical data and the derived best-fit line. In addition, approximately the first 10 hours of temperature data are not included in the analysis so as to ensure that the conductivity value is determined from steady state rather than transient heat conduction processes. 6 / 6 Undisturbed Ground Temperature Determination The undisturbed ground temperature is the constant temperature of the formation. This temperature is measured before starting the active thermal conductivity test by logging the first 10 minutes of data prior to turning on the heating elements of the GeoCube. In addition, prior to beginning the test Aztech Geothermal use a temperature probe on a long measuring tape to get a Temperature Profile (see chart below). If the TC test is initiated too soon after the installation of the test bore, the undisturbed ground temperature may be inaccurate. In general, it is recommended that the testing company waits a minimum of 3-5 days after installing the borehole before initiating the test so as to ensure that the ground has returned to its native and undisturbed temperature state. Borehole Thermal Resistance Calculation The borehole thermal resistance cannot be measured directly but can be calculated from the recorded in-situ measurements. After determining the thermal conductivity, the resultant value can be used in the line-source equation to calculate the borehole thermal resistance. Note that the calculated borehole thermal resistance is representative of the entire test bore configuration including the pipe type, pipe spacing, grout resistance and borehole diameter, etc. The empirically derived borehole thermal resistance may be entered into a design program such as Ground Loop Design for final loopfield design assuming the parameters for the boreholes in the final installation are equivalent to those in the test bore. Details pertaining to the general equation used for the calculation can be found in the research literature (Mattison, et al., 2007 for example). REPORT of LIMITED ASBESTOS and HAZARDOUS MATERIALS INSPECTION revised January 8, 2024 Location of Inspection: Glens Falls National Bank 696 Upper Glen Street Queensbury, New York 12804 Client/Building Owner: Glens Falls National Bank 250 Glen Street Glens Falls, New York 12801 Alpine Project #: 21-27316-A Material or Area Inspected: Interior of Entire Building Asbestos Materials Tested or Assumed: drywall joint compound (original construction), 9" floor tile, 12" floor tiles, mastic under carpet, tar/vapor barrier on masonry walls, fibrous electrical wire insulation.(observed and assumed asbestos), fire doors (assumed present and asbestos) Non-Asbestos Containing Materials Tested: drywall and joint compound (2004 construction), plaster layers, plaster patch/repair, floor leveling compound, mudded pipe fitting insulation, mudded roof drain leader fitting insulation, mudded roof drain bowl insulation, ceramic wall tile/ grout/ mortar, ceramic floor tile/ grout/ mortar, ceramic cove base/ grout/ mortar, 9" floor tile mastic, 12” floor tile, 12" floor tile mastic, carpet mastic, vinyl cove bases and mastics, 2'x4' ceiling tiles, block mortar, brick mortar, stone floor tile mortar and grout, and vinyl wall coverings and adhesives. Lead-Based Paint Found: Lead has been detected in paint samples collected from steel structural members, and plaster walls. Since construction of the building took place prior to 1978, it is assumed that all painted components that have not been tested for lead, are presumed to contain lead in paint. Contractors performing any work in areas constructed prior to 1978 should be aware that lead paint is assumed to be present. December 2021 696 Upper Glen Street Queensbury, New York Page 2 438 New Karner Road Albany, New York 12205 Phone: (518) 250-4047 Other Suspect Hazardous/Regulated Materials: fluorescent light ballasts (assumed to contain PCBs), fluorescent light tubes (assumed to contain Mercury), thermostats (assumed to contain Mercury), out of service air conditioning condensers (assumed to contain oils), batteries in emergency lighting and exit signs (assumed to contain heavy metals), smoke detectors (assumed to contain radioactive components), hydraulic oils (elevator - may to contain PCBs) Date(s) of Inspection: December 2, 2021, January 14, 2022, August 23, 2022, May 1, 2023, November 2, 2023, December 15, 2023, and December 27, 2023 Date of Initial Report: December 9, 2021 Date of Report Revision: January 8, 2024 Inspection Performed By: Alpine Environmental Services, Inc. 438 New Karner Road Albany, New York 12205 Phone (518) 250-4047 Inspector(s): Brian Gould AH 95-02582, Michael Balzano 06-02036 NYS Department of Labor Certified Asbestos Inspector(s) 1.0 Asbestos Inspection: 1.1 Scope and Purpose This report is intended to document the limited asbestos inspection of the bank building located at 696 Upper Glen Street in Queensbury, New York. “Asbestos containing materials”, as defined by the United States Environmental Protection Agency (EPA), is any material containing more than 1% asbestos as determined using the method specified in Appendix E, Subpart E, 40 CFR Part 763, Section 1, Polarized Light Microscopy. Bulk samples were collected in accordance with USEPA ASHARA protocols for number and types of samples. Materials easily crushed or pulverized by hand pressure are considered friable. Materials with a bituminous or resinous binder that are not easily crushed or pulverized by hand pressure are considered Non-friable Organically Bound (NOB). Friable and non-friable materials, excluding organically bound materials were analyzed using Polarized Light Microscopy (PLM). Non-Friable Organically Bound samples were analyzed using Transmission Electron Microscopy (TEM). All samples were analyzed by EMSL Analytical (ELAP 11506: Manhattan Lab, ELAP 12145: East Syracuse Lab, ELAP 11469: Carle Place Lab, ELAP 11506: Long Island City Lab) 1.2 Description The building inspected for the survey is a two story structure of masonry and steel construction with no basement. This building was built in or about 1963. Wall and ceiling materials observed consist of: plaster, and drywall. Ceiling materials observed consist of: 2'x4' ceiling tiles. Floor materials observed include: carpet, 12" floor tile, and 9" floor tile. December 2021 696 Upper Glen Street Queensbury, New York Page 3 438 New Karner Road Albany, New York 12205 Phone: (518) 250-4047 1.3 Limitation This inspection addresses only areas and materials at the interior of the building. Because the building was still occupied at the time of this inspection, destructive testing was kept to a minimum. No penetrations were made in existing walls or ceilings to determine the presence or absence of asbestos containing materials within wall chases or above ceilings. The electrical system within the building was energized at the time of Alpine Environmental Services’ site visit. The majority of the wire insulation visible in the building is either the newer vinyl sheathed type or the metal clad cabling. These types of wire are not considered to be suspect asbestos containing materials. There was a fibrous wire insulation observed during this inspection. This wire insulation was not sampled and must be assumed to be asbestos containing. Quantities of asbestos containing materials were estimated and the user must field verify all quantities. Any suspect materials found during demolition/renovation activities that are not listed in this report should be considered asbestos containing materials until tested and determined otherwise. 1.4 Results of Inspection Bulk samples were collected throughout the interior of the building. Samples were collected as prescribed by US EPA ASHARA protocols for the numbers and types of samples. See the sample results section for all samples collected and the results of analysis. 1.5 Conclusion and Recommendations The following asbestos containing materials were found during the limited asbestos inspection of the bank building located at 696 Upper Glen Street in Queensbury, New York: Table 1: Asbestos Containing Materials Tested or Assumed Homogeneous Material Location Substrate & Accessibility Approx. Quantity Friability Condition Walls Drywall with Asbestos Joint Compound (1A-02), (1A-07 (05012023)), (1-01, 1-02 (12272023)) Second Floor Original Drywall Walls and Ceilings Walls and Ceilings ~1,885 sf Friable Good Floors 9" Floor Tiles (9-01, 9-02) First Floor On Concrete: Much Under Other Tile ~155 sf Non-Friable Good Second Floor On Concrete: Much Under Carpet ~645 sf Non-Friable Good 12" Floor Tiles (10-01, 10-02) First Floor On Concrete: Much Under Carpet ~2,205 sf Non-Friable Good December 2021 696 Upper Glen Street Queensbury, New York Page 4 438 New Karner Road Albany, New York 12205 Phone: (518) 250-4047 Table 1 continued: Asbestos Containing Materials Tested or Assumed Homogeneous Material Location Substrate & Accessibility Approx. Quantity Friability Condition Floors continued Mastic Under Carpet (4-01, 4-02) (12272023) Second Floor: Room 218, Office adjacent SW Stairs On Concrete 235 sf Non-Friable Good Miscellaneous Fibrous Electrical Wire Insulation (Observed and Assumed Asbestos) Presumed Throughout the Building Unknown Friable Good Fire Doors (Assumed Present and Asbestos) Mechanical Rooms In Door Frames ~ 2 Doors Friable Good Tar/Vapor Barrier on Interior Surfaces of Exterior Masonry Walls (8/23/2022) (22-01, 22-02) First Floor On Interior Surfaces of Exterior Masonry Walls, Behind Plaster/ Drywall ~ 2,200 sf Non-Friable Good Second Floor ~ 2,200 sf Non-Friable Good Please note these quantities are only estimates and the user should field verify all quantities. The following materials were sampled by Alpine Environmental Services and determined not to contain asbestos. Table 2: Non-Asbestos Containing Materials Tested Non-Asbestos Material Locations Sample #’s HVAC Mudded Pipe Fitting Insulation First Floor; Rear Stairwell 4-01, 4-02, 4-03 Vibration Dampener First Floor Mechanical Room 24-01, 24-02 (05012023) Walls Drywall and Joint Compound Walls Constructed During 2004 Renovation First Floor: Waiting Area 104-Exterior Wall Waiting Area 104 - South Interior Wall, Vault Vestibule (119), Second Floor: Elevator Lobby, United Way Office West Wall at Window, Meeting Room 214 – North Wall, Corridor 207 Wall across from Storage 209/ Men’s Room Vestibule 211 - North Wall 1-01, 1-02, 1A-01, 1A-03, 1A-04, 1A-05, (5/1/2023) 1A-03, 1A-04, 1A-05, 1A-06 1-03 (12272023)) December 2021 696 Upper Glen Street Queensbury, New York Page 5 438 New Karner Road Albany, New York 12205 Phone: (518) 250-4047 Table 2 continued: Non-Asbestos Containing Materials Tested Non-Asbestos Material Locations Sample #’s Walls Continued Plaster Layers, and Patch/Repair First Floor: Vestibule Wall Second Floor: Retainer/Storage, Front Stairwell 2A-01, 2A-02, 2A-03, 2A-04, 2A-05, 2A-06, 2B-01, 2B-02, 2B-03, 2B-04, 2B-05, 2B-06, 2C-01, 2C-02, 2C-03, 2C-04, 2C-05 Ceramic Wall Tile, Grout, and Mortar Second Floor: Northwest Bathrooms (12152023): 01-01, 01-02, 02-01, 02-02, 03-01, 03-02 Floors 9" Floor Tile Mastic Rear Stairwell Landing, Second Floor: Storage/Vestibule at Men's Room 9M-01, 9M-02 12" Floor Tile Mastics First Floor: Main Lobby - Under Carpet Center Coupon Booth 10M-01, 10M-02 black) Carpet Mastic 1st Floor: North Central Room, Office 106 2nd Floor: United Way Office Lobby 12-01, 12-02, 12-03 12” Floor Tile and Mastic First Floor: Center Coupon Booth, Teller Area Office (Top Layers) Second Floor Bank Employee Lounge 11-01, 11-02, 11M-01, 11M-02 (yellow) 20-01, 20-02, 20M-01, 20M-02 (8/23/2022) 1-01, 1-02 (11022023), 2-01, 2-02, 3-01, 3-02 (12272023) Floor Leveling Compound First Floor: Main Lobby Under Carpet 3-01, 3-02 Ceramic Floor Tile, Grout, Mortar Second Floor: Retainer/Storage Bathroom, Second Floor: Northwest Bathrooms 7-01, 7-02, 7G-01, 7G-02, 7M-01, 7M-02 (12152023): 04-01, 04-02, 05-01, 05-02, 06-01, 06-02 Ceramic Cove Base, Grout, Mortar Second Floor: Retainer/Storage Bathroom 8-01, 8-02, 8G-01, 8G-02, 8M-01, 8M-02 Stone Floor Tile Mortar and Grout First Floor Vestibule 18-01, 18-02, 19-01, 19-02 Sheet Vinyl (Linoleum), and Mastic First Floor: Custodial Room 123 23-01, 23-02, 23M-01, 23M-02 (5/1/2023) Ceilings 2'x4' Ceiling Tile Second Floor: Front Stairwell, Elevator Lobby 15-01, 15-02 Miscellaneous Mudded Pipe Fitting Insulation on Roof Drain Leader Second Floor Front Stairwell 5-01, 5-02, 5-03 Mudded Insulation on Roof Drain Bowl Second Floor Front Stairwell 6-01, 6-02, 6-03 December 2021 696 Upper Glen Street Queensbury, New York Page 6 438 New Karner Road Albany, New York 12205 Phone: (518) 250-4047 Table 2 continued: Non-Asbestos Containing Materials Tested Non-Asbestos Material Locations Sample #’s Miscellaneous Continued Cove Bases and Mastics First Floor; Rear Stairwell, Second Floor: Storage/Vestibule at Men's Room 13-01, 13-02, 13M-01, 13M-02, 14-01, 14-02, 14M-01, 14M-02 Block Mortar 1st Floor: Teller Area South Wall at Office 16-01, 16-02 Brick Mortar 1st Floor: Mechanical Room at Chimney 17-01, 17-02 Vinyl Wall Covering and Adhesive 1st Floor: Teller Area South Wall (2 Layers) 2nd Floor: Stairwell West Wall 21-01, 21A-01, 21-02, 21A-02, 21-03, 21A-03 Any materials not sampled during this inspection should be considered suspect unless sampled and determined to be non-asbestos. All asbestos containing materials must be abated prior to the demolition/renovation of any part of the structure unless performed under a variance issued by the NYS Department of Labor. Disturbance/Abatement of any asbestos containing materials, as well as necessary air monitoring, must be performed by a NYS DOL licensed contractor, in accordance with state and federal regulations (NYS DOL ICR 56 and US EPA 40 CFR). 2.0 Lead-Based Paint Inspection 2.1 Description Alpine analyzed representative paint samples from the building. Surfaces tested include; steel beams, and plaster walls. The U.S. Housing and Urban Development (HUD) Guidelines for the Evaluation and Control of Lead-Based Paint in Housing (2012 Revision) define lead-based paint as having a lead content of 0.5% by weight as measured by atomic absorption spectrometry (AAS). However, OSHA considers paint with any detectable amount of lead to be lead-based paint. Alpine Environmental Services, Inc. has concluded through AAS analysis that lead above detectable limits was found in several of the areas tested. Table 3: Paint Chip Sample Results (AAS) Sample # Location Lead Concentration (% by weight) OSHA Lead Based Paint? 01 First Floor: Teller Area On Structural Beam Above Ceiling 63 % Yes 02 First Floor: Rear Stair on Plaster Wall 0.013% Yes 03 Second Floor: Rear Hall on Plaster Wall 0.091% Yes 04 Second Floor: retention Room At Window 0.089% Yes December 2021 696 Upper Glen Street Queensbury, New York Page 7 438 New Karner Road Albany, New York 12205 Phone: (518) 250-4047 2.2 Recommendations: Although Alpine collected representative paint chip samples throughout the building, if there is an area that was not represented, the area should be considered lead-based paint unless proven otherwise. OSHA requires that the employer conduct an initial exposure assessment when working with lead paint (29CFR1926.62). Until the employer performs an employee exposure assessment as required by OSHA, the employer shall provide to the employees the following; appropriate respiratory protection, personal protective clothing and equipment, change areas, hand washing facilities, biological monitoring and training. 3.0 PCB and Mercury Inspection: 3.1 Scope and Purpose An inspection was performed of the subject structure for possible PCB and mercury containing items. This inspection did not include the sampling of any electrical components for PCBs. No claims can be made as to confirm the presence or absence of PCBs in electrical components, although, professional judgment has been used in identifying potential PCB containing materials. “PCBs”, or Polychlorinated Biphenyls contaminated material, as defined by the United States Environmental Protection Agency (EPA), is any material containing greater than 50ppm by weight of PCBs. It is often less expensive to assume materials contain PCBs than to test for the substance. 3.2 Conclusion Polychlorinated Biphenyls (PCBs) Polychlorinated biphenyl (PCB) oils were commonly used as thermal insulating fluids in electrical and hydraulic equipment prior to a (approximately) 1977 manufacture date. Transformers, electrical ballasts, and hydraulic elevators are common places where PCB containing oils were used. The elevator in the building was installed in 2004 and the hydraulic oils used should not contain PCB. Polychlorinated Biphenyls (PCBs) may be present in the caulk used in windows, doorframes, masonry columns, and other masonry building materials in many buildings built or renovated between 1950 and 1978. Caulk was not sampled for PCB analysis as part of this inspection. The subject structure possessed numerous fluorescent lighting fixtures in all areas, each fixture has been assumed to contain at least one ballast. With the exception of ballasts containing a label stating “no PCBs” and newer ballasts manufactured after 1978, ballasts are assumed to contain PCB’s. During demolition/renovation, suspect PCB containing ballasts should be separated, drummed, and transported to a qualified waste center if they are not to be reused. Any disturbance or disposal of PCB containing materials should include appropriate handling and disposal procedures as required by the New York State Department of Environmental Conservation and the United States Environmental Protection Agency. Mercury Each of the fluorescent light fixtures contained from one to four fluorescent light bulbs. These bulbs usually contain mercury compounds and must be separated from the general construction debris during demolition/renovations. The typical means of disposal for the tubes is to isolate the tubes and transport the intact tubes to a recycling facility. For the purposes of this inspection, all fluorescent light bulbs, including the compact fluorescent bulbs, were assumed to contain mercury. December 2021 696 Upper Glen Street Queensbury, New York Page 8 438 New Karner Road Albany, New York 12205 Phone: (518) 250-4047 Several thermostats were observed within this building. Many of these thermostats were observed to contain elemental mercury and must be separated from the general construction debris during demolition/renovations. Disposal of any mercury containing items should include appropriate handling and disposal procedures as required by the New York State Department of Environmental Conservation and the United States Environmental Protection Agency. 4.0 Other Hazardous/Regulated Materials 4.1 Refrigerant There is one (1) decommissioned air conditioner condensing unit in the first-floor mechanical room. Due to the condition of the piping associated with the compressor, it appears the refrigerant had been captured when the unit was decommissioned. It is likely oil remains within the compressor that potentially contains PCBs based on the age of the compressor. Any other air conditioning units, portable air conditioners, water fountains, and refrigerators within the building may contain refrigerant(s). A refrigerant professional must be contracted prior to decommissioning refrigerant containing components in order to evacuate regulated substances prior to disposal. 4.2 Smoke Detectors Ionization smoke detectors contain radioactive components. Smoke detectors must be separated from the general waste stream and transported to a recycling facility. 4.3 Batteries Batteries in smoke detectors, emergency lighting, exit signs/lighting, etc. may contain heavy metals. Batteries must be separated from the general waste stream and transported to a recycling facility. If Alpine Environmental Services can be of further assistance on this matter, please contact Craig Petreikis at either (518) 250-4047 ext. 313 or craigp@alpineenv.com. Sincerely, Alpine Environmental Services, Inc. Brian Gould NYS Dept. of Labor Asbestos Inspector Enclosures: Results, NYSDOL Handling License(s), NYSDOL Handling Certificate(s), NYSDOH ELAP License(s) EMSL Analytical, Inc. 307 West 38th Street New York, NY 10018 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032121990EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Attention:Phone:Alpine Environmental Services (518) 250-4047 Fax:438 New Karner Road Received Date:Albany, NY 12205 12/03/2021 11:45 AM Analysis Date:12/06/2021 - 12/07/2021 Collected Date:12/02/2021 Project:21-27316-A/ 696 UPPER GLEN STREET / QUEENSBURY, NY Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 1-01 Description SECOND FLOOR ELEVATOR LOBBY - DRYWALL 032121990-0001 Homogeneity Homogeneous PLM NYS 198.1 Friable Brown/ Beige None Detected12/06/2021 15.00% 4.00% Cellulose Glass 55.00% 26.00% Gypsum Non-fibrous (other) PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 1-02 Description SECOND FLOOR ELEVATOR LOBBY - DRYWALL 032121990-0002 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/07/2021 10.00% 3.00% Cellulose Glass 60.00% 27.00% Gypsum Non-fibrous (other) PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 1A-01 Description SECOND FLOOR ELEVATOR LOBBY - JOINT COMPOUND 032121990-0003 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected12/06/2021 55.00% 7.00% 38.00% Ca Carbonate Mica Non-fibrous (other) PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 1A-02 Description SECOND FLOOR CORRIDOR 207 - JOINT COMPOUND 032121990-0004 Homogeneity Homogeneous PLM NYS 198.1 Friable Tan12/07/2021 None 45.00% 6.00% 46.80% Ca Carbonate Mica Non-fibrous (other) 2.20%Chrysotile PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Initial report from: 12/07/2021 14:37:00 Page 1 of 10ASB_198x_0009_0001 Printed 12/7/2021 2:37:06PM EMSL Analytical, Inc. 307 West 38th Street New York, NY 10018 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032121990EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 2A-01 Description SECOND FLOOR RETAINER / STORAGE 221 - PLASTR SUBSTRATE (SOFT GRAY/ BEIGE) 032121990-0005 Homogeneity Homogeneous PLM NYS 198.1 Friable Brown None Detected12/06/2021 2.00% Cellulose 20.00% 6.00% 12.00% 10.00% 50.00% Ca Carbonate Mica Non-fibrous (other) Perlite Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 2A-02 Description SECOND FLOOR RETAINER / STORAGE 221 - PLASTR SUBSTRATE (SOFT GRAY/ BEIGE) 032121990-0006 Homogeneity Homogeneous PLM NYS 198.1 Friable Brown None Detected12/06/2021 4.00% Cellulose 25.00% 6.00% 10.00% 10.00% 45.00% Ca Carbonate Mica Non-fibrous (other) Perlite Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 2A-03 Description SECOND FLOOR RETAINER / STORAGE 221 - PLASTR SUBSTRATE (SOFT GRAY/ BEIGE) 032121990-0007 Homogeneity Homogeneous PLM NYS 198.1 Friable Brown None Detected12/06/2021 3.00% Cellulose 25.00% 6.00% 11.00% 10.00% 45.00% Ca Carbonate Mica Non-fibrous (other) Perlite Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 2A-04 Description SECOND FLOOR RETAINER / STORAGE 221 - PLASTR SUBSTRATE (SOFT GRAY/ BEIGE) 032121990-0008 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/07/2021 25.00% 4.00% 26.00% 45.00% Ca Carbonate Mica Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Initial report from: 12/07/2021 14:37:00 Page 2 of 10ASB_198x_0009_0001 Printed 12/7/2021 2:37:06PM EMSL Analytical, Inc. 307 West 38th Street New York, NY 10018 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032121990EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 2A-05 Description SECOND FLOOR RETAINER / STORAGE 221 - PLASTR SUBSTRATE (SOFT GRAY/ BEIGE) 032121990-0009 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/07/2021 2.00%Cellulose 25.00% 4.00% 24.00% 45.00% Ca Carbonate Mica Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 2B-01 Description SECOND FLOOR RETAINER / STORAGE 221 - PLASTER SKIM COAT 032121990-0010 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected12/06/2021 45.00% 25.00% 30.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 2B-02 Description SECOND FLOOR FRONT STAIRWAY - PLASTER SKIM COAT 032121990-0011 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected12/06/2021 30.00% 50.00% 20.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 2B-03 Description SECOND FLOOR FRONT STAIRWAY - PLASTER SKIM COAT 032121990-0012 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected12/06/2021 30.00% 50.00% 20.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 2B-04 Description SECOND FLOOR FRONT STAIRWAY - PLASTER SKIM COAT 032121990-0013 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected12/07/2021 45.00% 55.00% Ca Carbonate Non-fibrous (other) PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Initial report from: 12/07/2021 14:37:00 Page 3 of 10ASB_198x_0009_0001 Printed 12/7/2021 2:37:06PM EMSL Analytical, Inc. 307 West 38th Street New York, NY 10018 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032121990EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 2B-05 Description SECOND FLOOR FRONT STAIRWAY - PLASTER SKIM COAT 032121990-0014 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected12/07/2021 50.00% 50.00% Ca Carbonate Non-fibrous (other) PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 2C-01 Description SECOND FLOOR RETAINER / STORAGE 221 - PLASTER PATCH (HARD GRAY) 032121990-0015 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/06/2021 20.00% 25.00% 55.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 2C-02 Description SECOND FLOOR RETAINER / STORAGE 221 - PLASTER PATCH (HARD GRAY) 032121990-0016 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/06/2021 30.00% 20.00% 50.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 2C-03 Description SECOND FLOOR RETAINER / STORAGE 221 - PLASTER PATCH (HARD GRAY) 032121990-0017 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/06/2021 35.00% 20.00% 45.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 2C-04 Description SECOND FLOOR RETAINER / STORAGE 221 - PLASTER PATCH (HARD GRAY) 032121990-0018 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/07/2021 20.00% 35.00% 45.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Initial report from: 12/07/2021 14:37:00 Page 4 of 10ASB_198x_0009_0001 Printed 12/7/2021 2:37:06PM EMSL Analytical, Inc. 307 West 38th Street New York, NY 10018 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032121990EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 2C-05 Description SECOND FLOOR RETAINER / STORAGE 221 - PLASTER PATCH (HARD GRAY) 032121990-0019 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/07/2021 25.00% 35.00% 40.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 3-01 Description FIRST FLOOR MAIN LOBBY UNDER CARPET - FLOOR LEVELER 032121990-0020 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected12/06/2021 3.00%Cellulose 30.00% 32.00% 35.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 3-02 Description FIRST FLOOR MAIN LOBBY UNDER CARPET - FLOOR LEVELER 032121990-0021 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected12/07/2021 35.00% 40.00% 25.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 4-01 Description FIRST FLOOR REAR STAIRWELL ON FIBERGLASS INSULATED HEAT PIPE - PIPE FITTING INSULATION 032121990-0022 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/06/2021 30.00% Min. Wool 20.00% 35.00% 15.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 4-02 Description FIRST FLOOR REAR STAIRWELL ON FIBERGLASS INSULATED HEAT PIPE - PIPE FITTING INSULATION 032121990-0023 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/06/2021 30.00% Min. Wool 30.00% 25.00% 15.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Initial report from: 12/07/2021 14:37:00 Page 5 of 10ASB_198x_0009_0001 Printed 12/7/2021 2:37:06PM EMSL Analytical, Inc. 307 West 38th Street New York, NY 10018 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032121990EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 4-03 Description FIRST FLOOR REAR STAIRWELL ON FIBERGLASS INSULATED HEAT PIPE - PIPE FITTING INSULATION 032121990-0024 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/07/2021 30.00% Min. Wool 35.00% 25.00% 10.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 5-01 Description SECOND FLOOR FRONT STAIRWELL ON FBGL INSULATED ROOF DRAIN LEADER - PIPE FITTING INSULATION 032121990-0025 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/06/2021 35.00% Min. Wool 25.00% 25.00% 15.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 5-02 Description SECOND FLOOR FRONT STAIRWELL ON FBGL INSULATED ROOF DRAIN LEADER - PIPE FITTING INSULATION 032121990-0026 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/06/2021 30.00% Min. Wool 30.00% 15.00% 25.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 5-03 Description SECOND FLOOR FRONT STAIRWELL ON FBGL INSULATED ROOF DRAIN LEADER - PIPE FITTING INSULATION 032121990-0027 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/07/2021 40.00% Min. Wool 30.00% 20.00% 10.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 6-01 Description SECOND FLOOR FRONT STAIRWELL ON ROOF DRAIN BOWL - MUDDED INSULATION 032121990-0028 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/06/2021 30.00% Min. Wool 20.00% 15.00% 15.00% 20.00% Ca Carbonate Non-fibrous (other) Perlite Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Initial report from: 12/07/2021 14:37:00 Page 6 of 10ASB_198x_0009_0001 Printed 12/7/2021 2:37:06PM EMSL Analytical, Inc. 307 West 38th Street New York, NY 10018 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032121990EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 6-02 Description SECOND FLOOR FRONT STAIRWELL ON ROOF DRAIN BOWL - MUDDED INSULATION 032121990-0029 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/06/2021 30.00%Min. Wool 25.00% 10.00% 15.00% 20.00% Ca Carbonate Non-fibrous (other) Perlite Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 6-03 Description SECOND FLOOR FRONT STAIRWELL ON ROOF DRAIN BOWL - MUDDED INSULATION 032121990-0030 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/07/2021 30.00% Min. Wool 35.00% 30.00% 5.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 7-01 Description SECOND FLOOR RETAINER / STORAGE 221 BATHROOM - CERAMIC FLOOR TILE 032121990-0031 Homogeneity Homogeneous PLM NYS 198.1 Friable Tan None Detected12/06/2021 50.00% 20.00% 30.00% Non-fibrous (other) Perlite Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 7-02 Description SECOND FLOOR RETAINER / STORAGE 221 BATHROOM - CERAMIC FLOOR TILE 032121990-0032 Homogeneity Homogeneous PLM NYS 198.1 Friable Tan None Detected12/07/2021 15.00% 75.00% 10.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 7G-01 Description SECOND FLOOR RETAINER / STORAGE 221 BATHROOM - CERAMIC FLOOR TILE GROUT 032121990-0033 Homogeneity Homogeneous PLM NYS 198.1 Friable Beige None Detected12/06/2021 55.00% 30.00% 15.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Initial report from: 12/07/2021 14:37:00 Page 7 of 10ASB_198x_0009_0001 Printed 12/7/2021 2:37:06PM EMSL Analytical, Inc. 307 West 38th Street New York, NY 10018 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032121990EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 7G-02 Description SECOND FLOOR RETAINER / STORAGE 221 BATHROOM - CERAMIC FLOOR TILE GROUT 032121990-0034 Homogeneity Homogeneous PLM NYS 198.1 Friable Tan None Detected12/07/2021 60.00% 30.00% 10.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 7M-01 Description SECOND FLOOR RETAINER / STORAGE 221 BATHROOM - CERAMIC FLOOR TILE MORTAR 032121990-0035 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected12/06/2021 15.00% 25.00% 20.00% 40.00% Ca Carbonate Non-fibrous (other) Perlite Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 7M-02 Description SECOND FLOOR RETAINER / STORAGE 221 BATHROOM - CERAMIC FLOOR TILE MORTAR 032121990-0036 Homogeneity Homogeneous PLM NYS 198.1 Friable Tan None Detected12/07/2021 55.00% 35.00% 10.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 8-01 Description SECOND FLOOR RETAINER / STORAGE 221 BATHROOM - CERAMIC COVEBASE 032121990-0037 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected12/06/2021 45.00% 25.00% 30.00% Non-fibrous (other) Perlite Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 8-02 Description SECOND FLOOR RETAINER / STORAGE 221 BATHROOM - CERAMIC COVEBASE 032121990-0038 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected12/07/2021 15.00% 70.00% 15.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Initial report from: 12/07/2021 14:37:00 Page 8 of 10ASB_198x_0009_0001 Printed 12/7/2021 2:37:06PM EMSL Analytical, Inc. 307 West 38th Street New York, NY 10018 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032121990EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 8G-01 Description SECOND FLOOR RETAINER / STORAGE 221 BATHROOM - CERAMIC COVEBASE GROUT 032121990-0039 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected12/06/2021 55.00% 25.00% 20.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 8G-02 Description SECOND FLOOR RETAINER / STORAGE 221 BATHROOM - CERAMIC COVEBASE GROUT 032121990-0040 Homogeneity Homogeneous PLM NYS 198.1 Friable Tan None Detected12/07/2021 30.00% 30.00% 40.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 8M-01 Description SECOND FLOOR RETAINER / STORAGE 221 BATHROOM - CERAMIC COVEBASE MORTAR 032121990-0041 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected12/06/2021 45.00% 20.00% 15.00% 20.00% Ca Carbonate Non-fibrous (other) Perlite Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 8M-02 Description SECOND FLOOR RETAINER / STORAGE 221 BATHROOM - CERAMIC COVEBASE MORTAR 032121990-0042 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected12/07/2021 35.00% 50.00% 15.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Initial report from: 12/07/2021 14:37:00 Page 9 of 10ASB_198x_0009_0001 Printed 12/7/2021 2:37:06PM EMSL Analytical, Inc. 307 West 38th Street New York, NY 10018 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032121990EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material The samples in this report were submitted to EMSL for analysis by Asbestos Analysis of Bulk Materials via NYS ELAP Approved Methods. The reference number for these samples is the EMSL Order ID above. Please use this reference number when calling about these samples. Report Comments: Sample Receipt Date: Analysis Completed Date:Analysis Completed Time: Sample Receipt Time:12/3/2021 11:45 AM 12/6/2021 10:22 AM Analyst(s): Angelica Serrano PLM NYS 198.1 Friable (24)Migena Shehu PLM NYS 198.1 Friable (18) Samples reviewed and approved by: Charles Johnson, Asbestos Laboratory Manager or Other Approved Signatory EMSL maintains liability limited to cost of analysis. Interpretation and use of test results are the responsibility of the client. This report relates only to the samples reported above, and may not be reproduced, except in full, without written approval by EMSL. EMSL bears no responsibility for sample collection activities or analytical method limitations. The report reflects the samples as received. Results are generated from the field sampling data (sampling volumes and areas, locations, etc.) provided by the client on the Chain of Custody. Samples are within quality control criteria and met method specifications unless otherwise noted. Estimation of uncertainty available upon request. This report is a summary of multiple methods of analysis, fully compliant reports are available upon request. All samples examined for the presence of vermiculite when analyzed via NYS 198.1. A combination of PLM and TEM analysis may be necessary to ensure consistently reliable detection of asbestos. Polarized-light microscopy is not consistently reliable in detecting asbestos in floor coverings and similar non-friable organically bound materials. This report must not be used to claim product endorsement by NVLAP of any agency or the U.S. Government . Quantitative transmission electron microscopy is currently the only method that can be used to determine if this material can be considered or treated as non-asbestos containing. NOB= Non friable organically bound; N/A= Not applicable VCM= Vermiculite containing material. Samples analyzed by EMSL Analytical, Inc. New York, NY NYS ELAP 11506, NVLAP Lab Code 101048-9 Initial report from: 12/07/2021 14:37:00 Page 10 of 10ASB_198x_0009_0001 Printed 12/7/2021 2:37:06PM OrderID: 032121990Page 1 Of 4 OrderID: 032121990Page 2 Of 4 OrderID: 032121990Page 3 Of 4 OrderID: 032121990Page 4 Of 4 EMSL Analytical, Inc. 307 West 38th Street New York, NY 10018 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032121988EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Attention:Phone:Alpine Environmental Services (518) 250-4047 Fax:438 New Karner Road Received Date:Albany, NY 12205 12/03/2021 11:40 AM Analysis Date:12/04/2021 - 12/05/2021 Collected Date:12/02/2021 Project:21-27316-A / 696 UPPER GLEN STREET / QUEENSBURY, NY Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 9M-01 Description REAR STAIRWELL LANDING - 9" FLOOR TILE MASTIC 032121988-0001 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Black Inconclusive: None Detected12/04/2021 100.00%Other TEM NYS 198.4 NOB Black None Detected12/05/2021 100.00% Other Sample ID 9M-02 Description SECOND FLOOR STORAGE / VESTIBULE AT MENS ROOM - 9" FLOOR TILE MASTIC 032121988-0002 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Black Inconclusive: None Detected12/04/2021 <1.00% Fibrous (other)100.00% Other TEM NYS 198.4 NOB Black None Detected12/05/2021 100.00% Other Sample ID 9-01 Description REAR STAIRWELL LANDING - 9" FLOOR TILE 032121988-0003 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Gray12/04/2021 None 98.30% Other 1.70% Chrysotile TEM NYS 198.4 NOB Positive Stop (Not Analyzed)12/04/2021 Sample ID 9-02 Description SECOND FLOOR STORAGE / VESTIBULE AT MENS ROOM - 9" FLOOR TILE 032121988-0004 Homogeneity PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Positive Stop (Not Analyzed)12/04/2021 TEM NYS 198.4 NOB Positive Stop (Not Analyzed)12/04/2021 Sample ID 10M-01 Description FIRST FLOOR MAIN LOBBY UNDER CARPET AND LEVELER - FLOOR TILE MASTIC 032121988-0005 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Black Inconclusive: None Detected12/04/2021 100.00% Other TEM NYS 198.4 NOB Black None Detected12/05/2021 100.00% Other Initial report from: 12/05/2021 19:19:37 Page 1 of 6ASB_198x_0009_0001 Printed 12/6/2021 12:01:06PM EMSL Analytical, Inc. 307 West 38th Street New York, NY 10018 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032121988EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 10M-02 Description FIRST FLOOR CENTER COUPON BOOTH BOTTOM LAYER - FLOOR TILE MASTIC 032121988-0006 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Black Inconclusive: None Detected12/04/2021 100.00%Other TEM NYS 198.4 NOB Black None Detected12/05/2021 100.00% Other Sample ID 10-01 Description FIRST FLOOR CENTER COUPON BOOTH BOTTOM LAYER - FLOOR TILE 032121988-0007 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Beige Inconclusive: None Detected12/04/2021 100.00% Other TEM NYS 198.4 NOB Beige12/05/2021 None 98.80% Other 1.20% Chrysotile Sample ID 10-02 Description FIRST FLOOR CENTER COUPON BOOTH BOTTOM LAYER - FLOOR TILE 032121988-0008 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Beige Inconclusive: None Detected12/04/2021 100.00% Other TEM NYS 198.4 NOB Positive Stop (Not Analyzed)12/05/2021 Sample ID 11M-01 Description FIRST FLOOR CENTER COUPON BOOTH TOP LAYER - 12" FLOOR TILE MASTIC 032121988-0009 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Yellow Inconclusive: None Detected12/04/2021 100.00% Other TEM NYS 198.4 NOB Yellow None Detected12/05/2021 100.00% Other Sample ID 11M-02 Description FIRST FLOOR CENTER COUPON BOOTH TOP LAYER - 12" FLOOR TILE MASTIC 032121988-0010 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Yellow Inconclusive: None Detected12/04/2021 100.00% Other TEM NYS 198.4 NOB Yellow None Detected12/05/2021 100.00% Other Sample ID 11-01 Description FIRST FLOOR CENTER COUPON BOOTH TOP LAYER - 12" FLOOR TILE 032121988-0011 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Beige Inconclusive: None Detected12/04/2021 100.00% Other TEM NYS 198.4 NOB Beige None Detected12/05/2021 100.00% Other Initial report from: 12/05/2021 19:19:37 Page 2 of 6ASB_198x_0009_0001 Printed 12/6/2021 12:01:06PM EMSL Analytical, Inc. 307 West 38th Street New York, NY 10018 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032121988EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 11-02 Description FIRST FLOOR CENTER COUPON BOOTH TOP LAYER - 12" FLOOR TILE 032121988-0012 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Beige Inconclusive: None Detected12/04/2021 100.00%Other TEM NYS 198.4 NOB Beige None Detected12/05/2021 100.00% Other Sample ID 12-01 Description FIRST FLOOR CENTER COUPON BOOTH - CARPET MASTIC 032121988-0013 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Yellow Inconclusive: None Detected12/04/2021 100.00% Other TEM NYS 198.4 NOB Yellow None Detected12/05/2021 100.00% Other Sample ID 12-02 Description SECOND FLOOR UNITED WAY OFFICE LOBBY - CARPET MASTIC 032121988-0014 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Yellow Inconclusive: None Detected12/04/2021 100.00% Other TEM NYS 198.4 NOB Yellow None Detected12/05/2021 100.00% Other Sample ID 13M-01 Description FIRST FLOOR REAR STAIRWELL - COVEBASE MASTIC 032121988-0015 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Beige Inconclusive: None Detected12/04/2021 100.00% Other TEM NYS 198.4 NOB Beige None Detected12/05/2021 100.00% Other Sample ID 13M-02 Description FIRST FLOOR REAR STAIRWELL - COVEBASE MASTIC 032121988-0016 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Beige Inconclusive: None Detected12/04/2021 100.00% Other TEM NYS 198.4 NOB Beige None Detected12/05/2021 100.00% Other Sample ID 13-01 Description FIRST FLOOR REAR STAIRWELL - COVEBASE 032121988-0017 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Black Inconclusive: None Detected12/04/2021 100.00% Other TEM NYS 198.4 NOB Black None Detected12/05/2021 100.00% Other Initial report from: 12/05/2021 19:19:37 Page 3 of 6ASB_198x_0009_0001 Printed 12/6/2021 12:01:06PM EMSL Analytical, Inc. 307 West 38th Street New York, NY 10018 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032121988EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 13-02 Description FIRST FLOOR REAR STAIRWELL - COVEBASE 032121988-0018 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Black Inconclusive: None Detected12/04/2021 100.00%Other TEM NYS 198.4 NOB Black None Detected12/05/2021 100.00% Other Sample ID 14M-01 Description SECOND FLOOR STORAGE / VESTIBULE AT MENS ROOM - COVEBASE MASTIC 032121988-0019 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Brown Inconclusive: None Detected12/04/2021 100.00% Other TEM NYS 198.4 NOB Brown None Detected12/05/2021 100.00% Other Sample ID 14M-02 Description SECOND FLOOR STORAGE / VESTIBULE AT MENS ROOM - COVEBASE MASTIC 032121988-0020 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Brown Inconclusive: None Detected12/04/2021 100.00% Other TEM NYS 198.4 NOB Brown/ Black None Detected12/05/2021 100.00% Other Sample ID 14-01 Description SECOND FLOOR STORAGE / VESTIBULE AT MENS ROOM - COVEBASE 032121988-0021 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Black Inconclusive: None Detected12/04/2021 100.00% Other TEM NYS 198.4 NOB Black None Detected12/05/2021 100.00% Other Sample ID 14-02 Description SECOND FLOOR STORAGE / VESTIBULE AT MENS ROOM - COVEBASE 032121988-0022 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Black Inconclusive: None Detected12/04/2021 100.00% Other TEM NYS 198.4 NOB Black None Detected12/05/2021 100.00% Other Sample ID 15-01 Description SECOND FLOOR FRONT STAIRWAY - 2X4 CEILING TILE 032121988-0023 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB White Inconclusive: None Detected12/04/2021 1.50% Min. Wool 98.50% Other TEM NYS 198.4 NOB White None Detected12/05/2021 100.00% Other Initial report from: 12/05/2021 19:19:37 Page 4 of 6ASB_198x_0009_0001 Printed 12/6/2021 12:01:06PM EMSL Analytical, Inc. 307 West 38th Street New York, NY 10018 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032121988EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 15-02 Description SECOND FLOOR ELEVATOR LOBBY - 2X4 CEILING TILE 032121988-0024 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB White Inconclusive: None Detected12/04/2021 1.40%Min. Wool 98.60% Other TEM NYS 198.4 NOB White None Detected12/05/2021 100.00% Other Initial report from: 12/05/2021 19:19:37 Page 5 of 6ASB_198x_0009_0001 Printed 12/6/2021 12:01:06PM EMSL Analytical, Inc. 307 West 38th Street New York, NY 10018 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032121988EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material The samples in this report were submitted to EMSL for analysis by Asbestos Analysis of Bulk Materials via NYS ELAP Approved Methods. The reference number for these samples is the EMSL Order ID above. Please use this reference number when calling about these samples. Report Comments: Sample Receipt Date: Analysis Completed Date:Analysis Completed Time: Sample Receipt Time:12/3/2021 11:40 AM 12/4/2021 2:20 PM Analyst(s): Christopher Cernansky PLM NYS 198.6 NOB (23)Isaac Mendez TEM NYS 198.4 NOB (15) Steven Dutter TEM NYS 198.4 NOB (6) Samples reviewed and approved by: Charles Johnson, Asbestos Laboratory Manager or Other Approved Signatory EMSL maintains liability limited to cost of analysis. Interpretation and use of test results are the responsibility of the client. This report relates only to the samples reported above, and may not be reproduced, except in full, without written approval by EMSL. EMSL bears no responsibility for sample collection activities or analytical method limitations. The report reflects the samples as received. Results are generated from the field sampling data (sampling volumes and areas, locations, etc.) provided by the client on the Chain of Custody. Samples are within quality control criteria and met method specifications unless otherwise noted. Estimation of uncertainty available upon request. This report is a summary of multiple methods of analysis, fully compliant reports are available upon request. All samples examined for the presence of vermiculite when analyzed via NYS 198.1. A combination of PLM and TEM analysis may be necessary to ensure consistently reliable detection of asbestos. Polarized-light microscopy is not consistently reliable in detecting asbestos in floor coverings and similar non-friable organically bound materials. This report must not be used to claim product endorsement by NVLAP of any agency or the U.S. Government . Quantitative transmission electron microscopy is currently the only method that can be used to determine if this material can be considered or treated as non-asbestos containing. NOB= Non friable organically bound; N/A= Not applicable VCM= Vermiculite containing material. Samples analyzed by EMSL Analytical, Inc. New York, NY NYS ELAP 11506, NVLAP Lab Code 101048-9 Initial report from: 12/05/2021 19:19:37 Page 6 of 6ASB_198x_0009_0001 Printed 12/6/2021 12:01:06PM OrderID: 032121988Page 1 Of 2 OrderID: 032121988Page 2 Of 2 EMSL Analytical, Inc. 307 West 38th Street New York, NY 10018 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032200672EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Attention:Phone:Alpine Environmental Services (518) 250-4047 Fax:438 New Karner Road Received Date:Albany, NY 12205 01/17/2022 10:30 AM Analysis Date:01/18/2022 - 01/20/2022 Collected Date:01/14/2022 Project:21-27316-A/ 696 UPPER GLEN STREET, QUEENSBURY, NEW YORK Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 1A-03 Description FIRST FLOOR: WAITING AREA 104 EXTERIOR WALL AT WINDOW - JOINT COMPOUND 032200672-0001 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected01/18/2022 50.00% 5.00% 45.00% Ca Carbonate Mica Non-fibrous (other) PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 1A-04 Description FIRST FLOOR: WAITING AREA 104 INTERIOR SOUTH WALL - JOINT COMPOUND 032200672-0002 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected01/18/2022 50.00% 50.00% Ca Carbonate Non-fibrous (other) PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 1A-05 Description SECOND FLOOR: UNITED WAY OFFICE WEST WALL ADJACENT WINDOW - JOINT COMPOUND 032200672-0003 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected01/20/2022 60.00% 7.00% 33.00% Ca Carbonate Mica Non-fibrous (other) PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 2A-06 Description FIRST FLOOR: VESTIBULE WALL - PLASTER SUBSTRATE 032200672-0004 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray/ White None Detected01/18/2022 7.00%Cellulose 5.00% 38.00% 50.00% Mica Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Initial report from: 01/20/2022 15:30:03 Page 1 of 3ASB_198x_0009_0001 Printed 1/20/2022 3:30:13PM EMSL Analytical, Inc. 307 West 38th Street New York, NY 10018 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032200672EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 2B-06 Description FIRST FLOOR: VESTIBULE WALL - PLASTER SKIM COAT 032200672-0005 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected01/18/2022 50.00% 50.00% Ca Carbonate Non-fibrous (other) PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 12-03 Description FIRST FLOOR: OFFICE 106 SW CORNER - CARPET MASTIC 032200672-0006 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Yellow Inconclusive: None Detected01/20/2022 100.00%Other TEM NYS 198.4 NOB Yellow None Detected01/20/2022 100.00% Other Initial report from: 01/20/2022 15:30:03 Page 2 of 3ASB_198x_0009_0001 Printed 1/20/2022 3:30:13PM EMSL Analytical, Inc. 307 West 38th Street New York, NY 10018 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032200672EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material The samples in this report were submitted to EMSL for analysis by Asbestos Analysis of Bulk Materials via NYS ELAP Approved Methods. The reference number for these samples is the EMSL Order ID above. Please use this reference number when calling about these samples. Report Comments: Sample Receipt Date: Analysis Completed Date:Analysis Completed Time: Sample Receipt Time:1/17/2022 10:30 AM 1/20/2022 12:44 PM Analyst(s): Angelica Serrano PLM NYS 198.1 Friable (1)Esteven Tineo PLM NYS 198.1 Friable (4) Angelica Serrano PLM NYS 198.6 NOB (1)Venisha Lazarus-Barnes TEM NYS 198.4 NOB (1) Samples reviewed and approved by: Charles Johnson, Asbestos Laboratory Manager or Other Approved Signatory EMSL maintains liability limited to cost of analysis. Interpretation and use of test results are the responsibility of the client. This report relates only to the samples reported above, and may not be reproduced, except in full, without written approval by EMSL. EMSL bears no responsibility for sample collection activities or analytical method limitations. The report reflects the samples as received. Results are generated from the field sampling data (sampling volumes and areas, locations, etc.) provided by the client on the Chain of Custody. Samples are within quality control criteria and met method specifications unless otherwise noted. Estimation of uncertainty available upon request. This report is a summary of multiple methods of analysis, fully compliant reports are available upon request. All samples examined for the presence of vermiculite when analyzed via NYS 198.1. A combination of PLM and TEM analysis may be necessary to ensure consistently reliable detection of asbestos. Polarized-light microscopy is not consistently reliable in detecting asbestos in floor coverings and similar non-friable organically bound materials. This report must not be used to claim product endorsement by NVLAP of any agency or the U.S. Government . Quantitative transmission electron microscopy is currently the only method that can be used to determine if this material can be considered or treated as non-asbestos containing. NOB= Non friable organically bound; N/A= Not applicable VCM= Vermiculite containing material. Samples analyzed by EMSL Analytical, Inc. New York, NY NYS ELAP 11506, NVLAP Lab Code 101048-9 Initial report from: 01/20/2022 15:30:03 Page 3 of 3ASB_198x_0009_0001 Printed 1/20/2022 3:30:13PM OrderID: 032200672Page 1 Of 1 EMSL Analytical, Inc. 528 Mineola Avenue Carle Place, NY 11514 Tel/Fax: (516) 997-7251 / (516) 997-7528 http://www.EMSL.com / carleplacelab@emsl.com 062218454EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Attention:Phone:Brian Gould (518) 250-4047 Fax:Alpine Environmental Services Received Date:438 New Karner Road 08/25/2022 10:40 AM Analysis Date:Albany, NY 12205 08/27/2022 Collected Date:08/23/2022 Project:696 Upper Glen Street, Queensbury, New York / #21-27316-A Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 16-01 Description First Floor: Teller Area - South Masonry Wall at Office - Block Mortar 062218454-0001 Homogeneity Homogeneous PLM NYS 198.1 Friable Brown/ White/ Black None Detected08/27/2022 28.00% 10.00% 62.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 16-02 Description First Floor: Teller Area - South Masonry Wall at Office - Block Mortar 062218454-0002 Homogeneity Homogeneous PLM NYS 198.1 Friable Brown/ White/ Black None Detected08/27/2022 21.00% 13.00% 66.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 17-01 Description First Floor: Mechanical Room at Chimney - Block Mortar 062218454-0003 Homogeneity Homogeneous PLM NYS 198.1 Friable Brown None Detected08/27/2022 24.00% 9.00% 67.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 17-02 Description First Floor: Mechanical Room at Chimney - Block Mortar 062218454-0004 Homogeneity Homogeneous PLM NYS 198.1 Friable Brown None Detected08/27/2022 28.00% 12.00% 60.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Initial report from: 08/29/2022 09:55:59 Page 1 of 3ASB_198x_0009_0001 Printed 8/29/2022 9:56:01AM EMSL Analytical, Inc. 528 Mineola Avenue Carle Place, NY 11514 Tel/Fax: (516) 997-7251 / (516) 997-7528 http://www.EMSL.com / carleplacelab@emsl.com 062218454EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 18-01 Description First Floor: Vesibule Floor - Floor Tile Mortar 062218454-0005 Homogeneity Homogeneous PLM NYS 198.1 Friable Brown/ Gray None Detected08/27/2022 19.00% 15.00% 66.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 18-02 Description First Floor: Vesibule Floor - Floor Tile Mortar 062218454-0006 Homogeneity Homogeneous PLM NYS 198.1 Friable Brown/ Gray None Detected08/27/2022 12.00% 18.00% 70.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 19-01 Description First Floor: Vesibule Floor - Floor Tile Grout 062218454-0007 Homogeneity Homogeneous PLM NYS 198.1 Friable Black None Detected08/27/2022 62.00% 16.00% 22.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 19-02 Description First Floor: Vesibule Floor - Floor Tile Grout 062218454-0008 Homogeneity Homogeneous PLM NYS 198.1 Friable Black None Detected08/27/2022 60.00% 12.00% 28.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Initial report from: 08/29/2022 09:55:59 Page 2 of 3ASB_198x_0009_0001 Printed 8/29/2022 9:56:01AM EMSL Analytical, Inc. 528 Mineola Avenue Carle Place, NY 11514 Tel/Fax: (516) 997-7251 / (516) 997-7528 http://www.EMSL.com / carleplacelab@emsl.com 062218454EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material The samples in this report were submitted to EMSL for analysis by Asbestos Analysis of Bulk Materials via NYS ELAP Approved Methods. The reference number for these samples is the EMSL Order ID above. Please use this reference number when calling about these samples. Report Comments: Sample Receipt Date: Analysis Completed Date:Analysis Completed Time: Sample Receipt Time:8/25/2022 10:40 AM 8/27/2022 11:08 AM Analyst(s): Michael Hartcorn PLM NYS 198.1 Friable (8) Samples reviewed and approved by: Daniel Clarke, Asbestos Laboratory Manager or Other Approved Signatory EMSL maintains liability limited to cost of analysis. Interpretation and use of test results are the responsibility of the client. This report relates only to the samples reported above, and may not be reproduced, except in full, without written approval by EMSL. EMSL bears no responsibility for sample collection activities or analytical method limitations. The report reflects the samples as received. Results are generated from the field sampling data (sampling volumes and areas, locations, etc.) provided by the client on the Chain of Custody. Samples are within quality control criteria and met method specifications unless otherwise noted. Estimation of uncertainty available upon request. This report is a summary of multiple methods of analysis, fully compliant reports are available upon request. All samples examined for the presence of vermiculite when analyzed via NYS 198.1. A combination of PLM and TEM analysis may be necessary to ensure consistently reliable detection of asbestos. Polarized-light microscopy is not consistently reliable in detecting asbestos in floor coverings and similar non-friable organically bound materials. This report must not be used to claim product endorsement by NVLAP of any agency or the U.S. Government . Quantitative transmission electron microscopy is currently the only method that can be used to determine if this material can be considered or treated as non-asbestos containing. NOB= Non friable organically bound; N/A= Not applicable VCM= Vermiculite containing material. Samples analyzed by EMSL Analytical, Inc. Carle Place, NY NYS ELAP 11469, NVLAP Lab Code 101048-10 Initial report from: 08/29/2022 09:55:59 Page 3 of 3ASB_198x_0009_0001 Printed 8/29/2022 9:56:01AM OrderID: 062218454 Page 1 Of 1 EMSL Analytical, Inc. 528 Mineola Avenue Carle Place, NY 11514 Tel/Fax: (516) 997-7251 / (516) 997-7528 http://www.EMSL.com / carleplacelab@emsl.com 062218441EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Attention:Phone:Brian Gould (518) 250-4047 Fax:Alpine Environmental Services Received Date:438 New Karner Road 08/25/2022 10:40 AM Analysis Date:Albany, NY 12205 08/27/2022 - 08/29/2022 Collected Date:08/23/2022 Project:696 Upper Glen Street, Queensbury, New York #21-27316-A Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 20M-01 Description First Floor: Teller Area Office, Floor - 12" Floor Tile Mastic 062218441-0001 Homogeneity Homogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Yellow Inconclusive: None Detected08/27/2022 100.00%Other TEM NYS 198.4 NOB Yellow None Detected08/28/2022 100.00% Other Sample ID 20M-02 Description First Floor: Teller Area Office, Floor - 12" Floor Tile Mastic 062218441-0002 Homogeneity Homogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Yellow Inconclusive: None Detected08/27/2022 100.00% Other TEM NYS 198.4 NOB Yellow None Detected08/28/2022 100.00% Other Sample ID 20-01 Description First Floor: Teller Area Office, Floor - 12" Floor Tile 062218441-0003 Homogeneity Homogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Gray Inconclusive: None Detected08/27/2022 100.00% Other TEM NYS 198.4 NOB Gray None Detected08/28/2022 100.00% Other Sample ID 20-02 Description First Floor: Teller Area Office, Floor - 12" Floor Tile 062218441-0004 Homogeneity Homogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Gray Inconclusive: None Detected08/27/2022 100.00% Other TEM NYS 198.4 NOB Gray None Detected08/28/2022 100.00% Other Sample ID 21A-01 Description First Floor: Teller Area North Wall, Top Layer - Vinyl Wall Covering Adhesive 062218441-0005 Homogeneity Homogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Beige Inconclusive: None Detected08/27/2022 100.00% Other TEM NYS 198.4 NOB Beige None Detected08/28/2022 100.00% Other Initial report from: 08/29/2022 11:51:26 Page 1 of 4ASB_198x_0009_0001 Printed 8/29/2022 11:51:30AM EMSL Analytical, Inc. 528 Mineola Avenue Carle Place, NY 11514 Tel/Fax: (516) 997-7251 / (516) 997-7528 http://www.EMSL.com / carleplacelab@emsl.com 062218441EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 21-01 Description First Floor: Teller Area North Wall, Top Layer - Vinyl Wall Covering 062218441-0006 Homogeneity PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed08/29/2022 Sample is inseparable from 21A-01. TEM NYS 198.4 NOB Not Analyzed08/28/2022 Sample ID 21A-02 Description First Floor: Teller Area North Wall, Bottom Layer - Vinyl Wall Covering Adhesive 062218441-0007 Homogeneity Homogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Beige Inconclusive: None Detected08/27/2022 100.00%Other TEM NYS 198.4 NOB Beige None Detected08/28/2022 100.00% Other Sample ID 21-02 Description First Floor: Teller Area North Wall, Bottom Layer - Vinyl Wall Covering 062218441-0008 Homogeneity PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed08/29/2022 Sample is inseparable from 21A-02. TEM NYS 198.4 NOB Not Analyzed08/28/2022 Sample ID 21A-03 Description Second Floor: Stairwell West Wall - Vinyl Wall Covering Adhesive 062218441-0009 Homogeneity Homogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Beige Inconclusive: None Detected08/27/2022 100.00% Other TEM NYS 198.4 NOB Beige None Detected08/28/2022 100.00% Other Sample ID 21-03 Description Second Floor: Stairwell West Wall - Vinyl Wall Covering 062218441-0010 Homogeneity PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed08/29/2022 Sample is inseparable from 21A-03. TEM NYS 198.4 NOB Not Analyzed08/28/2022 Sample ID 22-01 Description First Floor: Teller Area South Wall, on Masonry - Tar/Vapor Barrier 062218441-0011 Homogeneity Homogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Black08/27/2022 None 91.40% Other 8.60% Chrysotile TEM NYS 198.4 NOB Not Analyzed Initial report from: 08/29/2022 11:51:26 Page 2 of 4ASB_198x_0009_0001 Printed 8/29/2022 11:51:30AM EMSL Analytical, Inc. 528 Mineola Avenue Carle Place, NY 11514 Tel/Fax: (516) 997-7251 / (516) 997-7528 http://www.EMSL.com / carleplacelab@emsl.com 062218441EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 22-02 Description First Floor: Teller Area South Wall, on Masonry - Tar/Vapor Barrier 062218441-0012 Homogeneity PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Positive Stop (Not Analyzed)08/27/2022 TEM NYS 198.4 NOB Not Analyzed Initial report from: 08/29/2022 11:51:26 Page 3 of 4ASB_198x_0009_0001 Printed 8/29/2022 11:51:30AM EMSL Analytical, Inc. 528 Mineola Avenue Carle Place, NY 11514 Tel/Fax: (516) 997-7251 / (516) 997-7528 http://www.EMSL.com / carleplacelab@emsl.com 062218441EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material The samples in this report were submitted to EMSL for analysis by Asbestos Analysis of Bulk Materials via NYS ELAP Approved Methods. The reference number for these samples is the EMSL Order ID above. Please use this reference number when calling about these samples. Report Comments: Sample Receipt Date: Analysis Completed Date:Analysis Completed Time: Sample Receipt Time:8/25/2022 10:40 AM 8/29/2022 9:34 AM Analyst(s): Tomas Montes De Oca PLM NYS 198.6 NOB (8)Soaiful Islam TEM NYS 198.4 NOB (7) Samples reviewed and approved by: Daniel Clarke, Asbestos Laboratory Manager or Other Approved Signatory EMSL maintains liability limited to cost of analysis. Interpretation and use of test results are the responsibility of the client. This report relates only to the samples reported above, and may not be reproduced, except in full, without written approval by EMSL. EMSL bears no responsibility for sample collection activities or analytical method limitations. The report reflects the samples as received. Results are generated from the field sampling data (sampling volumes and areas, locations, etc.) provided by the client on the Chain of Custody. Samples are within quality control criteria and met method specifications unless otherwise noted. Estimation of uncertainty available upon request. This report is a summary of multiple methods of analysis, fully compliant reports are available upon request. All samples examined for the presence of vermiculite when analyzed via NYS 198.1. A combination of PLM and TEM analysis may be necessary to ensure consistently reliable detection of asbestos. Polarized-light microscopy is not consistently reliable in detecting asbestos in floor coverings and similar non-friable organically bound materials. This report must not be used to claim product endorsement by NVLAP of any agency or the U.S. Government . Quantitative transmission electron microscopy is currently the only method that can be used to determine if this material can be considered or treated as non-asbestos containing. NOB= Non friable organically bound; N/A= Not applicable VCM= Vermiculite containing material. Samples analyzed by EMSL Analytical, Inc. Carle Place, NY NYS ELAP 11469, NVLAP Lab Code 101048-10 Initial report from: 08/29/2022 11:51:26 Page 4 of 4ASB_198x_0009_0001 Printed 8/29/2022 11:51:30AM OrderID: 062218441 Page 1 Of 1 EMSL Analytical, Inc. 6838 Ellicott Dr. Suite 1A East Syracuse, NY 13057 Tel/Fax: (315) 424-3938 / (315) 424-3939 http://www.EMSL.com / syracuselab@EMSL.com 732300320EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Attention:Phone:Lab results (518) 250-4047 Fax:Alpine Environmental Services Received Date:438 New Karner Road 05/02/2023 12:54 PM Analysis Date:Albany, NY 12205 05/04/2023 - 05/05/2023 Collected Date:05/01/2023 Project:696 Upper Glen Street, Queensbury, New York, 21-27316-A Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 1A-03 Description First Floor: Vault Vestibule 119 Column/Chase adj Vault - Joint Compound 732300320-0001 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected05/05/2023 100.00% Non-fibrous (other) PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 1A-04 Description Second Floor: Meeting Room 215, North Wall - Joint Compound 732300320-0002 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected05/05/2023 100.00% Non-fibrous (other) PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 1A-05 Description Second Floor: Corridor 207, Wall across from Storage 209 - Joint Compound 732300320-0003 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected05/05/2023 100.00% Non-fibrous (other) PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 1A-06 Description Second Floor: Men's Room Vestibule 211, North Wall - Joint Compound 732300320-0004 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected05/05/2023 100.00% Non-fibrous (other) PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 1A-07 Description Second Floor: Men's Room Vestibule 211, Wall at JC 212 - Joint Compound 732300320-0005 Homogeneity Homogeneous PLM NYS 198.1 Friable Beige05/05/2023 None 96.50% Non-fibrous (other)3.50% Chrysotile PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Initial report from: 05/05/2023 15:28:53 Page 1 of 3ASB_198x_0009_0001 Printed 5/5/2023 3:28:56PM EMSL Analytical, Inc. 6838 Ellicott Dr. Suite 1A East Syracuse, NY 13057 Tel/Fax: (315) 424-3938 / (315) 424-3939 http://www.EMSL.com / syracuselab@EMSL.com 732300320EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 23M-01 Description First Floor: Custodial Room 123 - Linoleum Mastic 732300320-0006 Homogeneity Homogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Brown Inconclusive: None Detected05/04/2023 100.00% Other TEM NYS 198.4 NOB Brown None Detected05/05/2023 100.00% Other Sample ID 23M-02 Description First Floor: Custodial Room 123 - Linoleum Mastic 732300320-0007 Homogeneity Homogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Brown Inconclusive: None Detected05/04/2023 100.00% Other TEM NYS 198.4 NOB Brown None Detected05/05/2023 100.00% Other Sample ID 23-01 Description First Floor: Custodial Room 123 - Linoleum 732300320-0008 Homogeneity Homogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Beige Inconclusive: None Detected05/04/2023 100.00% Other TEM NYS 198.4 NOB Beige None Detected05/05/2023 100.00% Other Sample ID 23-02 Description First Floor: Custodial Room 123 - Linoleum 732300320-0009 Homogeneity Homogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Beige Inconclusive: None Detected05/04/2023 100.00% Other TEM NYS 198.4 NOB Beige None Detected05/05/2023 100.00% Other Sample ID 24-01 Description Second Floor; Storage/utility Room 222 - Duct Vibration Dampener 732300320-0010 Homogeneity Homogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Black Inconclusive: None Detected05/04/2023 100.00% Other TEM NYS 198.4 NOB Black05/05/2023 None 100.00% Other <1% Chrysotile Sample ID 24-02 Description Second Floor; Storage/utility Room 222 - Duct Vibration Dampener 732300320-0011 Homogeneity Homogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Black Inconclusive: None Detected05/04/2023 100.00% Other TEM NYS 198.4 NOB Black05/05/2023 None 100.00% Other <1% Chrysotile Initial report from: 05/05/2023 15:28:53 Page 2 of 3ASB_198x_0009_0001 Printed 5/5/2023 3:28:56PM EMSL Analytical, Inc. 6838 Ellicott Dr. Suite 1A East Syracuse, NY 13057 Tel/Fax: (315) 424-3938 / (315) 424-3939 http://www.EMSL.com / syracuselab@EMSL.com 732300320EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material The samples in this report were submitted to EMSL for analysis by Asbestos Analysis of Bulk Materials via NYS ELAP Approved Methods . The reference number for these samples is the EMSL Order ID above . Please use this reference number when calling about these samples. Report Comments: Sample Receipt Date: Analysis Completed Date:Analysis Completed Time: Sample Receipt Time:5/2/2023 12:54 PM 5/5/2023 11:56 AM Analyst(s): Christopher Fleming PLM NYS 198.1 Friable (5)Christopher Fleming PLM NYS 198.6 NOB (6) Christopher Fleming TEM NYS 198.4 NOB (6) Samples reviewed and approved by: Christopher Fleming, Abestos Lab Manager or Other Approved Signatory EMSL maintains liability limited to cost of analysis. Interpretation and use of test results are the responsibility of the client. This report relates only to the samples reported above, and may not be reproduced, except in full, without written approval by EMSL. EMSL bears no responsibility for sample collection activities or analytical method limitations. The report reflects the samples as received. Results are generated from the field sampling data (sampling volumes and areas, locations, etc.) provided by the client on the Chain of Custody. Samples are within quality control criteria and met method specifications unless otherwise noted. Estimation of uncertainty available upon request. This report is a summary of multiple methods of analysis, fully compliant reports are available upon request. All samples examined for the presence of vermiculite when analyzed via NYS 198.1. A combination of PLM and TEM analysis may be necessary to ensure consistently reliable detection of asbestos . Polarized-light microscopy is not consistently reliable in detecting asbestos in floor coverings and similar non-friable organically bound materials. This report must not be used to claim product endorsement by NVLAP of any agency or the U.S. Government . Quantitative transmission electron microscopy is currently the only method that can be used to determine if this material can be considered or treated as non-asbestos containing. NOB= Non friable organically bound; N/A= Not applicable VCM= Vermiculite containing material. Samples analyzed by EMSL Analytical, Inc. East Syracuse, NY NYS ELAP 12145, NVLAP Lab Code 600283-0 Initial report from: 05/05/2023 15:28:53 Page 3 of 3ASB_198x_0009_0001 Printed 5/5/2023 3:28:56PM OrderID: 732300320 Page 1 Of 1 EMSL Analytical, Inc. 6838 Ellicott Dr. Suite 1A East Syracuse, NY 13057 Tel/Fax: (315) 424-3938 / (315) 424-3939 http://www.EMSL.com / syracuselab@EMSL.com 732300891EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Attention:Phone:Lab results (518) 250-4047 Fax:Alpine Environmental Services Received Date:438 New Karner Road 11/03/2023 11:37 AM Analysis Date:Albany, NY 12205 11/06/2023 - 11/07/2023 Collected Date:11/02/2023 Project:696 Upper Glen Street, Queensbury, New York, 21-27316-A Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 1-01 Description Second Floor: Break Room/Kitchen - 12" Floor Tile 732300891-0001 Homogeneity Homogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Beige Inconclusive: None Detected11/06/2023 100.00% Other TEM NYS 198.4 NOB Beige None Detected11/07/2023 100.00% Other Sample ID 1-02 Description Second Floor: Break Room/Kitchen - 12" Floor Tile 732300891-0002 Homogeneity Homogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Beige Inconclusive: None Detected11/06/2023 100.00% Other TEM NYS 198.4 NOB Beige None Detected11/07/2023 100.00% Other Initial report from: 11/07/2023 14:56:35 Page 1 of 2ASB_198x_0009_0001 Printed 11/7/2023 2:56:36PM EMSL Analytical, Inc. 6838 Ellicott Dr. Suite 1A East Syracuse, NY 13057 Tel/Fax: (315) 424-3938 / (315) 424-3939 http://www.EMSL.com / syracuselab@EMSL.com 732300891EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material The samples in this report were submitted to EMSL for analysis by Asbestos Analysis of Bulk Materials via NYS ELAP Approved Methods . The reference number for these samples is the EMSL Order ID above . Please use this reference number when calling about these samples. Report Comments: Sample Receipt Date: Analysis Completed Date:Analysis Completed Time: Sample Receipt Time:11/3/2023 11:37 AM 11/6/2023 9:58 AM Analyst(s): Andy Rodriguez PLM NYS 198.6 NOB (2)Christopher Fleming TEM NYS 198.4 NOB (2) Samples reviewed and approved by: Christopher Fleming, Abestos Lab Manager or Other Approved Signatory EMSL maintains liability limited to cost of analysis. Interpretation and use of test results are the responsibility of the client. This report relates only to the samples reported above, and may not be reproduced, except in full, without written approval by EMSL. EMSL bears no responsibility for sample collection activities or analytical method limitations. The report reflects the samples as received. Results are generated from the field sampling data (sampling volumes and areas, locations, etc.) provided by the client on the Chain of Custody. Samples are within quality control criteria and met method specifications unless otherwise noted. Estimation of uncertainty available upon request. This report is a summary of multiple methods of analysis, fully compliant reports are available upon request. All samples examined for the presence of vermiculite when analyzed via NYS 198.1. A combination of PLM and TEM analysis may be necessary to ensure consistently reliable detection of asbestos . Polarized-light microscopy is not consistently reliable in detecting asbestos in floor coverings and similar non-friable organically bound materials. This report must not be used to claim product endorsement by NVLAP of any agency or the U.S. Government . Quantitative transmission electron microscopy is currently the only method that can be used to determine if this material can be considered or treated as non-asbestos containing. NOB= Non friable organically bound; N/A= Not applicable VCM= Vermiculite containing material. Samples analyzed by EMSL Analytical, Inc. East Syracuse, NY NYS ELAP 12145, NVLAP Lab Code 600283-0 Initial report from: 11/07/2023 14:56:35 Page 2 of 2ASB_198x_0009_0001 Printed 11/7/2023 2:56:36PM OrderID: 732300891 Page 1 Of 1 EMSL Analytical, Inc. 10-39 45th Road Long Island City, NY 11101 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032316181EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Attention:Phone:Lab results (518) 250-4047 Fax:Alpine Environmental Services Received Date:438 New Karner Road 12/16/2023 11:54 AM Analysis Date:Albany, NY 12205 12/17/2023 Collected Date:12/15/2023 Project:21-27316-A/ Glens Falls National Bank - 696 Upper Glen Street, Queensbury, New York 12804 Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 01-01 Description 2nd Floor - Ladies Bathroom - Ceramic Wall Tile 032316181-0001 Homogeneity Homogeneous PLM NYS 198.1 Friable White/ Green None Detected12/17/2023 65.00% 35.00% Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 01-02 Description 2nd Floor - Mens Bathroom - Ceramic Wall Tile 032316181-0002 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected12/17/2023 35.00% 65.00% Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 02-01 Description 2nd Floor - Ladies Bathroom - Ceramic Wall Tile Grout 032316181-0003 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected12/17/2023 25.00% 30.00% 45.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 02-02 Description 2nd Floor - Mens Bathroom - Ceramic Wall Tile Grout 032316181-0004 Homogeneity Homogeneous PLM NYS 198.1 Friable White None Detected12/17/2023 60.00% 40.00% Ca Carbonate Non-fibrous (other) PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 03-01 Description 2nd Floor - Ladies Bathroom - Ceramic Wall Tile Mortar 032316181-0005 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/17/2023 35.00% 20.00% 45.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Initial report from: 12/17/2023 21:15:32 Page 1 of 4ASB_198x_0009_0001 Printed 12/17/2023 9:15:34PM EMSL Analytical, Inc. 10-39 45th Road Long Island City, NY 11101 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032316181EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 03-02 Description 2nd Floor - Mens Bathroom - Ceramic Wall Tile Mortar 032316181-0006 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/17/2023 35.00% 10.00% 55.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 04-01 Description 2nd Floor - Ladies Bathroom - Ceramic Wall Tile 032316181-0007 Homogeneity Homogeneous PLM NYS 198.1 Friable Green None Detected12/17/2023 75.00% 25.00% Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 04-02 Description 2nd Floor - Mens Bathroom - Ceramic Wall Tile 032316181-0008 Homogeneity Homogeneous PLM NYS 198.1 Friable Tan None Detected12/17/2023 90.00% 10.00% Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 05-01 Description 2nd Floor - Ladies Bathroom - Ceramic Wall Tile Grout 032316181-0009 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/17/2023 20.00% 30.00% 50.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 05-02 Description 2nd Floor - Mens Bathroom - Ceramic Wall Tile Grout 032316181-0010 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/17/2023 25.00% 10.00% 65.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Initial report from: 12/17/2023 21:15:32 Page 2 of 4ASB_198x_0009_0001 Printed 12/17/2023 9:15:34PM EMSL Analytical, Inc. 10-39 45th Road Long Island City, NY 11101 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032316181EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 06-01 Description 2nd Floor - Ladies Bathroom - Ceramic Wall Tile Mortar 032316181-0011 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/17/2023 30.00% 20.00% 50.00% Ca Carbonate Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 06-02 Description 2nd Floor - Mens Bathroom - Ceramic Wall Tile Mortar 032316181-0012 Homogeneity Homogeneous PLM NYS 198.1 Friable Gray None Detected12/17/2023 22.00% 3.00% 10.00% 65.00% Ca Carbonate Mica Non-fibrous (other) Quartz PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Initial report from: 12/17/2023 21:15:32 Page 3 of 4ASB_198x_0009_0001 Printed 12/17/2023 9:15:34PM EMSL Analytical, Inc. 10-39 45th Road Long Island City, NY 11101 Tel/Fax: (212) 290-0051 / (212) 290-0058 http://www.EMSL.com / manhattanlab@emsl.com 032316181EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material The samples in this report were submitted to EMSL for analysis by Asbestos Analysis of Bulk Materials via NYS ELAP Approved Methods . The reference number for these samples is the EMSL Order ID above . Please use this reference number when calling about these samples. Report Comments: Sample Receipt Date: Analysis Completed Date:Analysis Completed Time: Sample Receipt Time:12/16/2023 11:54 AM 12/17/2023 1:59 PM Analyst(s): Christopher Cernansky PLM NYS 198.1 Friable (6)Jessica Macdonald PLM NYS 198.1 Friable (6) Samples reviewed and approved by: Charles Johnson, Asbestos Laboratory Manager or Other Approved Signatory EMSL maintains liability limited to cost of analysis. Interpretation and use of test results are the responsibility of the client. This report relates only to the samples reported above, and may not be reproduced, except in full, without written approval by EMSL. EMSL bears no responsibility for sample collection activities or analytical method limitations. The report reflects the samples as received. Results are generated from the field sampling data (sampling volumes and areas, locations, etc.) provided by the client on the Chain of Custody. Samples are within quality control criteria and met method specifications unless otherwise noted. Estimation of uncertainty available upon request. This report is a summary of multiple methods of analysis, fully compliant reports are available upon request. All samples examined for the presence of vermiculite when analyzed via NYS 198.1. A combination of PLM and TEM analysis may be necessary to ensure consistently reliable detection of asbestos . Polarized-light microscopy is not consistently reliable in detecting asbestos in floor coverings and similar non-friable organically bound materials. This report must not be used to claim product endorsement by NVLAP of any agency or the U.S. Government . Quantitative transmission electron microscopy is currently the only method that can be used to determine if this material can be considered or treated as non-asbestos containing. NOB= Non friable organically bound; N/A= Not applicable VCM= Vermiculite containing material. Samples analyzed by EMSL Analytical, Inc. Long Island City, NY NYS ELAP 11506, NVLAP Lab Code 101048-9 Initial report from: 12/17/2023 21:15:32 Page 4 of 4ASB_198x_0009_0001 Printed 12/17/2023 9:15:34PM OrderID: 032316181 Page 1 Of 1 EMSL Analytical, Inc. 528 Mineola Avenue Carle Place, NY 11514 Tel/Fax: (516) 997-7251 / (516) 997-7528 http://www.EMSL.com / carleplacelab@emsl.com 062323839EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Attention:Phone:Brian Gould (518) 250-4047 Fax:Alpine Environmental Services Received Date:438 New Karner Road 12/28/2023 11:23 AM Analysis Date:Albany, NY 12205 12/30/2023 Collected Date:12/27/2023 Project:696 Upper Glen Street, Queensbury, NY Project Number: 21-27316-A Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 1-01 Description Second Floor: Office 218, North Wall - Drywall Joint Compound 062323839-0001 Homogeneity Homogeneous PLM NYS 198.1 Friable Tan12/30/2023 None 78.00% 4.00% 15.90% Ca Carbonate Mica Non-fibrous (other) 2.10% Chrysotile PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 1-02 Description Second Floor: Lobby 217, South Wall - Drywall Joint Compound 062323839-0002 Homogeneity Homogeneous PLM NYS 198.1 Friable Tan12/30/2023 None 77.00% 5.00% 15.70% Ca Carbonate Mica Non-fibrous (other) 2.30% Chrysotile PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Sample ID 1-03 Description Second Floor: Storage 209, at Window - Drywall Joint Compound 062323839-0003 Homogeneity Heterogeneous PLM NYS 198.1 Friable Gray/ White None Detected12/30/2023 3.00% Cellulose 70.00% 11.00% 7.00% 9.00% Ca Carbonate Gypsum Mica Non-fibrous (other) PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Not Analyzed TEM NYS 198.4 NOB Not Analyzed Initial report from: 01/02/2024 11:31:38 Page 1 of 2ASB_198x_0009_0001 Printed 1/2/2024 11:31:41AM EMSL Analytical, Inc. 528 Mineola Avenue Carle Place, NY 11514 Tel/Fax: (516) 997-7251 / (516) 997-7528 http://www.EMSL.com / carleplacelab@emsl.com 062323839EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material The samples in this report were submitted to EMSL for analysis by Asbestos Analysis of Bulk Materials via NYS ELAP Approved Methods . The reference number for these samples is the EMSL Order ID above . Please use this reference number when calling about these samples. Report Comments: Sample Receipt Date: Analysis Completed Date:Analysis Completed Time: Sample Receipt Time:12/29/2023 11:23 AM 12/30/2023 12:35 PM Analyst(s): Anthony Miraglia PLM NYS 198.1 Friable (3) Samples reviewed and approved by: Daniel Clarke, Asbestos Laboratory Manager or Other Approved Signatory EMSL maintains liability limited to cost of analysis. Interpretation and use of test results are the responsibility of the client. This report relates only to the samples reported above, and may not be reproduced, except in full, without written approval by EMSL. EMSL bears no responsibility for sample collection activities or analytical method limitations. The report reflects the samples as received. Results are generated from the field sampling data (sampling volumes and areas, locations, etc.) provided by the client on the Chain of Custody. Samples are within quality control criteria and met method specifications unless otherwise noted. Estimation of uncertainty available upon request. This report is a summary of multiple methods of analysis, fully compliant reports are available upon request. All samples examined for the presence of vermiculite when analyzed via NYS 198.1. A combination of PLM and TEM analysis may be necessary to ensure consistently reliable detection of asbestos . Polarized-light microscopy is not consistently reliable in detecting asbestos in floor coverings and similar non-friable organically bound materials. This report must not be used to claim product endorsement by NVLAP of any agency or the U.S. Government . Quantitative transmission electron microscopy is currently the only method that can be used to determine if this material can be considered or treated as non-asbestos containing. NOB= Non friable organically bound; N/A= Not applicable VCM= Vermiculite containing material. Samples analyzed by EMSL Analytical, Inc. Carle Place, NY NYS ELAP 11469, NVLAP Lab Code 101048-10 Initial report from: 01/02/2024 11:31:38 Page 2 of 2ASB_198x_0009_0001 Printed 1/2/2024 11:31:41AM OrderID: 062323839 Page 1 Of 1 EMSL Analytical, Inc. 528 Mineola Avenue Carle Place, NY 11514 Tel/Fax: (516) 997-7251 / (516) 997-7528 http://www.EMSL.com / carleplacelab@emsl.com 062323780EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Attention:Phone:Brian Gould (518) 250-4047 Fax:Alpine Environmental Services Received Date:438 New Karner Road 12/28/2023 11:23 AM Analysis Date:Albany, NY 12205 12/29/2023 - 12/31/2023 Collected Date:12/27/2023 Project:696 Upper Glen Street, Queensbury, New York #23-27316-A Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 2-01 Description Second Floor: Employee Lounge Under 12" Floor Tile - Mastic 062323780-0001 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Gray/ Black12/29/2023 None 100.00% Other Inconclusive : <1% Chrysotile TEM NYS 198.4 NOB Gray/ Black12/31/2023 None 100.00% Other <1% Chrysotile Sample ID 2-02 Description Second Floor: Employee Lounge Under 12" Floor Tile - Mastic 062323780-0002 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Gray/ Black12/29/2023 None 100.00% Other Inconclusive : <1% Chrysotile TEM NYS 198.4 NOB Gray/ Black12/31/2023 None 100.00% Other <1% Chrysotile Sample ID 3-01 Description Second Floor: Employee Lounge 219 - 12" Floor Tile 062323780-0003 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Gray Inconclusive: None Detected12/29/2023 100.00% Other TEM NYS 198.4 NOB Gray None Detected12/31/2023 100.00% Other Sample ID 3-02 Description Second Floor: Employee Lounge 219 - 12" Floor Tile 062323780-0004 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Gray Inconclusive: None Detected12/29/2023 100.00% Other TEM NYS 198.4 NOB Gray None Detected12/31/2023 100.00% Other Sample ID 4-01 Description Second Floor: Office 218, Under Carpet - Mastic 062323780-0005 Homogeneity Heterogeneous PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Brown/ Black12/29/2023 None 96.80% Other 3.20% Chrysotile TEM NYS 198.4 NOB Not Analyzed Initial report from: 12/31/2023 01:20:11 Page 1 of 3ASB_198x_0009_0001 Printed 1/2/2024 9:46:32AM EMSL Analytical, Inc. 528 Mineola Avenue Carle Place, NY 11514 Tel/Fax: (516) 997-7251 / (516) 997-7528 http://www.EMSL.com / carleplacelab@emsl.com 062323780EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material Test Color Analyzed Date Fibrous Non-Fibrous Asbestos Non-Asbestos Sample ID 4-02 Description Second Floor: Office 218, Under Carpet - Mastic 062323780-0006 Homogeneity PLM NYS 198.1 Friable Not Analyzed PLM NYS 198.6 VCM Not Analyzed PLM NYS 198.6 NOB Positive Stop (Not Analyzed)12/29/2023 TEM NYS 198.4 NOB Not Analyzed Initial report from: 12/31/2023 01:20:11 Page 2 of 3ASB_198x_0009_0001 Printed 1/2/2024 9:46:32AM EMSL Analytical, Inc. 528 Mineola Avenue Carle Place, NY 11514 Tel/Fax: (516) 997-7251 / (516) 997-7528 http://www.EMSL.com / carleplacelab@emsl.com 062323780EMSL Order: Customer ID: ALPI50 Customer PO: Project ID: Test Report:Asbestos Analysis of Bulk Material The samples in this report were submitted to EMSL for analysis by Asbestos Analysis of Bulk Materials via NYS ELAP Approved Methods . The reference number for these samples is the EMSL Order ID above . Please use this reference number when calling about these samples. Report Comments: Sample Receipt Date: Analysis Completed Date:Analysis Completed Time: Sample Receipt Time:12/28/2023 11:23 AM 12/29/2023 4:04 PM Analyst(s): April Schmuck PLM NYS 198.6 NOB (5)Ricky Calzolano TEM NYS 198.4 NOB (4) Samples reviewed and approved by: Daniel Clarke, Asbestos Laboratory Manager or Other Approved Signatory EMSL maintains liability limited to cost of analysis. Interpretation and use of test results are the responsibility of the client. This report relates only to the samples reported above, and may not be reproduced, except in full, without written approval by EMSL. EMSL bears no responsibility for sample collection activities or analytical method limitations. The report reflects the samples as received. Results are generated from the field sampling data (sampling volumes and areas, locations, etc.) provided by the client on the Chain of Custody. Samples are within quality control criteria and met method specifications unless otherwise noted. Estimation of uncertainty available upon request. This report is a summary of multiple methods of analysis, fully compliant reports are available upon request. All samples examined for the presence of vermiculite when analyzed via NYS 198.1. A combination of PLM and TEM analysis may be necessary to ensure consistently reliable detection of asbestos . Polarized-light microscopy is not consistently reliable in detecting asbestos in floor coverings and similar non-friable organically bound materials. This report must not be used to claim product endorsement by NVLAP of any agency or the U.S. Government . Quantitative transmission electron microscopy is currently the only method that can be used to determine if this material can be considered or treated as non-asbestos containing. NOB= Non friable organically bound; N/A= Not applicable VCM= Vermiculite containing material. Samples analyzed by EMSL Analytical, Inc. Carle Place, NY NYS ELAP 11469, NVLAP Lab Code 101048-10 Initial report from: 12/31/2023 01:20:11 Page 3 of 3ASB_198x_0009_0001 Printed 1/2/2024 9:46:32AM OrderID: 062323780 Page 1 Of 1 Client Sample Description ConcentrationLab ID Analyzed Lead Collected EMSL Analytical, Inc. 528 Mineola Avenue, Carle Place, NY 11514 Phone/Fax:(516) 997-7251 / (516) 997-7528 http://www.EMSL.com carleplacelab@emsl.com Attn:Brian Gould Alpine Environmental Services 438 New Karner Road Albany, NY 12205 Received:8/24/2022 10:17 AM 696 Upper Glen Street, Queensbury New York, #: 21-27316-A Fax: Phone:(518) 250-4047 Project: 8/23/2022Collected: Test Report: Lead in Paint Chips by Flame AAS (SW 846 3051A/7000B)* 062218327 CustomerID:ALPI50 CustomerPO: ProjectID: EMSL Order: Site: First Floor: Teller Area on Beam Above Ceiling 062218327-000101 63% wt8/24/20228/23/2022 Site: First Floor: Rear Stair on Plaster Wall 062218327-000202 0.013% wt8/24/20228/23/2022 Site: Second Floor: Rear Hall: On Plaster Hall 062218327-000303 0.091% wt8/24/20228/23/2022 Site: Second Floor: Retention Room: at Window 062218327-000404 0.089% wt8/24/20228/23/2022 Page 1 of 1 Dominique Iaccarino, Chemistry Lab Manager or other approved signatory Test Report ChmSnglePrm/nQC-7.32.3 Printed: 8/25/2022 8:23:38 AM EMSL maintains liability limited to cost of analysis. Interpretation and use of test results are the responsibility of the client. This report relates only to the samples reported above, and may not be reproduced, except in full, without written approval by EMSL. EMSL bears no responsibility for sample collection activities or analytical method limitations. The report reflects the samples as received. Results are generated from the field sampling data (sampling volumes and areas, locations, etc.) provided by the client on the Chain of Custody. Samples are within quality control criteria and met method specifications unless otherwise noted. Analysis following Lead in Paint by EMSL SOP/Determination of Environmental Lead by FLAA. Reporting limit is 0.008% wt. based on the minimum sample weight per our SOP. "<" (less than) result signifies the analyte was not detected at or above the reporting limit. Measurement of uncertainty is available upon request. Definitions of modifications are available upon request. Samples analyzed by EMSL Analytical, Inc. Carle Place, NY Lab ID 102344 is accredited by AIHA LAP, LLC in the env. accreditation program for Lead in Paint, CT PH-0249, NYS ELAP 11469, CA 2339 Initial report from 08/25/2022 08:23:38 OrderID: 062218327 Page 1 Of 1 DIVISION OF SAFETY & HEALTH LICENSE AND CERTIFICATE UNIT,STATE OFFICE CAMPUS,BLDG.12,ALBANY,NY 12226 ASBESTOS HANDLING LICENSE Alpine Environmental Services, Inc. 438 New Karner Road, Albany, NY, 12205 This license has been issued in accordance with applicable provisions of Article 30 of the Labor Law of New York State and of the New York State Codes, Rules and Regulations (12 NYCRR Part 56). It is subject to suspension or revocation for a (1) serious violation of state, federal or local laws with regard to the conduct of an asbestos project, or (2) demonstrated lack of responsibility in the conduct of any job involving asbestos or asbestos material. This license is valid only for the contractor named above and this license or a photocopy must be prominently displayed at the asbestos project worksite. This license verifies that all persons employed by the licensee on an asbestos project in New York State have been issued an Asbestos Certificate, appropriate for the type of work they perform, by the New York State Department of Labor. Amy Phillips, Director For the Commissioner of Labor SH 432 (12/21) License Number: License Class: Date of Issue: Expiration Date: Duly Authorized Representative: 29095 RESTRICTED 07/19/2023 08/31/2024 Craig Petreikis is hereby APPROVED as an Environmental Laboratory for the category ENVIRONMENTAL ANALYSES SOLID AND HAZARDOUS WASTE All approved subcategories and/or analytes are listed below: CERTIFICATE OF APPROVAL FOR LABORATORY SERVICE Issued in accordance with and pursuant to section 502 Public Health Law of New York State MR. DANIEL CLARKE EMSL ANALYTICAL, INC. 528 MINEOLA AVE. CARLE PLACE, NY 11514 NY Lab Id No: 11469 NEW YORK STATE DEPARTMENT OF HEALTH WADSWORTH CENTER Expires Issued Revised 12:01 AM April 01, 2024 April 01, 2022 March 30, 2023 Miscellaneous Asbestos in Friable Material Item 198.1 of Manual EPA 600/M4/82/020 Asbestos in Non-Friable Material-PLM Item 198.6 of Manual (NOB by PLM) Asbestos in Non-Friable Material-TEM Item 198.4 of Manual Asbestos-Vermiculite-Containing MaterialItem 198.8 of Manual Lead in Dust Wipes EPA 7000B Lead in Paint EPA 7000B Sample Preparation Methods EPA 3051A Serial No.: 66399 Property of the New York State Department of Health. Certificates are valid only at the address shown and must be conspicuously posted by the laboratory. Continued accreditation depends on the laboratory's successful ongoing participation in the Program. Consumers may verify a laboratory's accreditation status online at https://apps.health.ny.gov/pubdoh/applinks/wc/elappublicweb/, by phone (518) 485-5570 or by email to elap@health.ny.gov. Page 1 of 1 is hereby APPROVED as an Environmental Laboratory for the category ENVIRONMENTAL ANALYSES SOLID AND HAZARDOUS WASTE All approved subcategories and/or analytes are listed below: CERTIFICATE OF APPROVAL FOR LABORATORY SERVICE Issued in accordance with and pursuant to section 502 Public Health Law of New York State MR. CHRISTOPHER FLEMING EMSL ANALYTICAL, INC. - SYRACUSE, NY 6838 ELLICOT DRIVE SUITE 1A EAST SYRACUSE, NY 13057 NY Lab Id No: 12145 NEW YORK STATE DEPARTMENT OF HEALTH WADSWORTH CENTER Expires Issued Revised 12:01 AM April 01, 2024 April 01, 2022 March 30, 2023 Miscellaneous Asbestos in Friable Material Item 198.1 of Manual Asbestos in Non-Friable Material-PLM Item 198.6 of Manual (NOB by PLM) Asbestos in Non-Friable Material-TEM Item 198.4 of Manual Serial No.: 66803 Property of the New York State Department of Health. Certificates are valid only at the address shown and must be conspicuously posted by the laboratory. Continued accreditation depends on the laboratory's successful ongoing participation in the Program. Consumers may verify a laboratory's accreditation status online at https://apps.health.ny.gov/pubdoh/applinks/wc/elappublicweb/, by phone (518) 485-5570 or by email to elap@health.ny.gov. Page 1 of 1 is hereby APPROVED as an Environmental Laboratory for the category ENVIRONMENTAL ANALYSES SOLID AND HAZARDOUS WASTE All approved subcategories and/or analytes are listed below: CERTIFICATE OF APPROVAL FOR LABORATORY SERVICE Issued in accordance with and pursuant to section 502 Public Health Law of New York State MR. CHARLES JOHNSON EMSL ANALYTICAL, INC 10-39 45TH ROAD LONG ISLAND CITY, NY 11101 NY Lab Id No: 11506 NEW YORK STATE DEPARTMENT OF HEALTH WADSWORTH CENTER Expires Issued Revised 12:01 AM April 01, 2024 April 01, 2022 March 30, 2023 Miscellaneous Asbestos in Friable Material Item 198.1 of Manual EPA 600/M4/82/020 Asbestos in Non-Friable Material-PLM Item 198.6 of Manual (NOB by PLM) Asbestos in Non-Friable Material-TEM Item 198.4 of Manual Asbestos-Vermiculite-Containing MaterialItem 198.8 of Manual Serial No.: 66413 Property of the New York State Department of Health. Certificates are valid only at the address shown and must be conspicuously posted by the laboratory. Continued accreditation depends on the laboratory's successful ongoing participation in the Program. Consumers may verify a laboratory's accreditation status online at https://apps.health.ny.gov/pubdoh/applinks/wc/elappublicweb/, by phone (518) 485-5570 or by email to elap@health.ny.gov. Page 1 of 1 Glens Falls National Bank Queensbury Branch Renovation Structural Calculations For Renovation Prepared By: SRA Engineers Evergreen Professional Park 453 Dixon Road, Ste. 7, Bldg. 3 Queensbury, NY 12804 Client: Oldenquist Design 15 Dixon Ct. Queensbury, NY 12804 Shaun M. Rivers, Principal NYSPE # 066587 TABLE OF CONTENTS Phase 1: Cash Box Support Pages 1 - 9 Exist. CMU Wall Removal & Brick Re-support Pages 10 - 18 Exist. Roof & Floor Joists w/ Condensers, Heat Pumps & ERVs Pages 19 - 24 Foundation Underpin @ Geothermal Pipes Page 25 John O’Brien, Director February 23rd, 2024 Town of Queensbury SRA Job # 22-028 Buildings & Code Enforcement 742 Bay Rd. Queensbury, NY 12804 RE: Glens Falls National Bank: Queensbury Branch Renovation Dear Mr. O’Brien, We have been retained by Oldenquist Design of Queensbury, NY to provide structural engineering services for the design of the renovation of the Glens Falls National Bank, Queensbury Branch located at 696 Upper Glen Street in the Town of Queensbury. As part of our services, we will perform periodic construction site visits to review the construction for conformity with the construction documents. We will also review construction inspection reports, prepared by others, for conformance with the project specifications and drawings. If you have any questions, please contact the undersigned at (518) 761-0417. Sincerely, Shaun M. Rivers, PE Ted Prime, PE Principal Lead Project Engineer 2'-10" 812" 9"9" 2'-10"2'-10" 1' - 0 " 1' - 0 " 1' - 0 " 1'-0"1'-0" 1' - 0 " 1' - 0 " 1'-0"1'-0" 1'-0" B -C D 1'-2"4'-6" 4' - 7 " 9'-2" 11" 2' - 1 1 " 9'-1112" 2' - 5 " 5' - 5 " 2'-3" A G H 3' - 1 0 " I E 3' - 0 " 3' - 0 " 2" CLR 3' - 6 " 3' - 6 " 3' - 0 " 3' - 0 " 3' - 0 " 3' - 6 " 4" T Y P 3' - 6 " 3' - 0 " 2' - 1 0 " 2' - 1 0 " 2' - 1 0 " 2' - 1 0 " 2' - 1 0 " 2' - 1 0 " 2' - 1 0 " 3' - 6 " 4' - 0 " 4" 4' - 0 " F 3' - 0 " 3' - 6 " 3' - 0 " 2" 3" 3" 212" 3" 4" 3" 214" 114" 214" 6" 512"312" 214" 512" 312" 4" 6" 114" A-700 A2203 1-30-24 AS NOTED BID SET THIS DOCUMENT CONTAINS COPYRIGHTED MATERIAL BELONGING TO OLDENQUIST DESIGN. UNAUTHORIZED USE, DISSEMINATION, OR DUPLICATION OF THESE DRAWINGS MAY RESULT IN LIABILITY UNDER APPLICABLE LAWS. RA I L I N G D E T A I L S Glens Falls National Bank 696 Upper Glen St. Queensbury, NY RAILING DEMOLITION1 -3/8" = 1'-0" RAILING PLAN2 -3/8" = 1'-0" RAILING AND GUARD RAIL ELEVATIONS4 -3/8" = 1'-0" WALL HAND RAIL ELEVATION5 -3/8" = 1'-0" PARTIAL RAILING PLAN @ 2ND FL3 -3/8" = 1'-0" ELEVATION A ELEVATION B ELEVATION C ELEVATION D ELEVATION FELEVATION E ELEVATION G ELEVATION H ELEVATION I STAINED HDWD RAILING TOP AND HANDRAILS, COORDINATE FINISH COLOR W/ ARCH, TYP STAINLESS STL HANDRAIL BRACKET AT WALLS STAINLESS STL GUARDRAIL POST, TYP STAINLESS STL HANDRAIL BRACKET AT GUARDRAIL POSTS WELD POSTS TO ATTACHMENT PLATES ATTACHMENT PLATE AT EXISTING STAIR STRINGERSTL. STL. ATTACHMENT PLATE AT FLOOR AT BOTTOM OF STAIRS MECH FASTENERS W/ STAINLESS STL CAPS, TYP MECH FASTENERS EPOXY EMBEDDED AT FLOOR, W/ ST. STL CAPS 1/4-INCH STAINLESS STEEL STRAND CABLE, TYPE 316; HOLD IN TENSION USING STAINLESS STL RECEIVERS AND SPACERS MAINTAIN LESS THAN 4-INCH SPACING BETWEEN CABLES MAINTAIN LESS THAN 6-INCH SPACE BETWEEN CABLES AND TREADS/RISERS OR STRINGER AT TOP AND BOTTOM OF STAIR FLIGHTS STAINLESS STL GUARD RAIL POST MOUNTED TO EXISTING STAIR STRINGER. RAILING DETAILS6 -1-1/2" = 1'-0" RAILING NOTES PAINT EXIST. STL. STRINGER @ WALL, TYP PAINT ALL EXPOSED SURFACES OF EXIST. STL STRINGERS AND STAIR FRAMING, TYP LINE OF FLOOR BEYOND STAINED WOOD HANDRAILS AT STAIR RUNS MOUNTED TO WALLS ON STAINLESS STL BRACKETS, TYP HANDRAIL EXTENSIONS PER ADA, TOP AND BOTTOM OF STAIR RUNS, TYP 1. GUARDRAIL FABRICATION MAY BE BY A RAILING MANUFACTURER OR SHOP FABRICATED. HOWEVER, IN BOTH CASES SUBMIT SHOP DRAWINGS THAT HAVE BEEN DESIGNED AND STAMPED BY A STRUCTURAL ENGINEER REGISTERED IN THE STATE OF NEW YORK. 2. DESIGN GUARDRAILS TO WITHSTAND LOADS OF 50 LBS/LINEAR FOOT AND CONCENTRATED LOADS OF 200 LBS. 3. GUARDRAIL POST AND HANDRAIL BRACKET SPACING IS CONCEPTUAL. ACTUAL SPACING SHALL BE DESIGNED BY RAILING FABRICATOR, WITH AN EFFORT MADE TO FOLLOW THE CONCEPTUAL SPACING SHOWN. 4. TREAD DEPTH AND RISER HEIGHT ARE EXISTING. 5. OPEN SIDES OF STAIRS WITH A TOTAL RISE OF MORE THAN 30 INCHES ABOVE THE FLOOR OR GRADE BELOW SHALL HAVE GUARDS NOT LESS THAN 42 INCHES IN HEIGHT MEASURED VERTICALLY FROM THE NOSING OF THE TREADS. 6. REQUIRED GUARDS ON OPEN SIDES OF STAIRWAYS AND RAISED FLOOR SURFACES SHALL HAVE INTERMEDIATE RAILS OR ORNAMENTAL CLOSURES THAT DO NOT ALLOW THE PASSAGE OF A SPHERE 4 INCHES OR MORE IN DIAMETER. 7. HANDRAILS SHALL BE PROVIDED ON AT LEAST ONE SIDE OF EACH STAIRWAY WITH TWO OR MORE RISERS. HANDRAIL HEIGHT, MEASURED ABOVE THE TREAD NOSINGS, SHALL BE NOT LESS THAN 34 INCHES AND NOT MORE THAN 38 INCHES. ALL REQUIRED HANDRAILS SHALL BE CONTINUOUS THE FULL LENGTH OF THE STAIRS FROM A POINT DIRECTLY ABOVE THE TOP RISER OF A FLIGHT TO A POINT DIRECTLY ABOVE THE LOWEST RISER OF THE FLIGHT. 8. EXTEND HANDRAILS HORIZONTALLY 12" BEYOND LAST RISER 12", PER ADA. ENDS OF RAILING EXTENSIONS SHALL RETURN ON THEMSELVES, A NEWEL POST, OR INTO A WALL, WITH NO EXPOSED EXTENSIONS. 9. HANDRAILS ADJACENT TO A WALL SHALL HAVE A SPACE OF NOT LESS THAN 1 1/2 INCHES BETWEEN THE WALL AND THE HANDRAIL. STAINLESS STEEL POST AND CABLE RAIL SYSTEM, MECHANICALLY FASTENED WITH STAINLESS STEEL BRACKETS TO EXISTING STEEL STAIR STRINGER, TYP STAINED WOOD GUARDRAIL CAP, TYP STAINED WOOD HANDRAILS AT STAIR RUNS, ATTACHED TO GUARDRAIL POSTS W/ STAINLESS STEEL BRACKETS, TYP LINE OF STAIRS BEYOND EXIST. STRINGER EXIST. STRINGER, TYP EXIST. STRINGER, TYP LINE OF GUARDRAIL CAP ABOVE GUARDRAIL POST ATTACHMENT PLATE 3/8" STAND-OFFS EXIST. STRINGER HANDRAIL BRACKET WOOD HANDRAIL TYP HANDRAIL TYP GUARDRAIL ABOVE HANDRAIL, DASHED FOR CLARITY EXIST. STRINGER, TYP REMOVE POSTS COMPLETELY, REPAIR/GRIND STRINGER SMOOTH REMOVE GUARDRAIL/RAILING PANELS, TYP REMOVE WALL-MOUNTED HANDRAILS, TYP GUARDRAIL AT TOP OF STAIRS, ATTACHMENT POSTS NOT SHOWN FOR CLARITY 5 5: BUILDING DEPT. RESPONSE 2-27-24 12'-0" 21 ' - 0 " 10 ' - 1 1 " 11'-6"11'-5"7'-0"11'-10" 11'-111 2" 10 ' - 8 " 10 ' - 8 " 8'-10" 4'-9" 7'-6"5'-41 2" 6' - 6 " 5' - 6 1 2" 1' - 6 " CL R 13'-31 2" 3' - 4 " 11 ' - 1 0 " 11 ' - 1 0 " 5'-61 2" 11'-01 2" 3'-4" CLR 14 ' - 0 " 6'-8" 8'-91 2" 5' - 4 1 2" 135° 135° 115A 101B 117A 114A 113A 120A 123A 122A 118A 102A 112A110A109A 108A 106A 105A 104A 103A 121A 5' - 1 0 " 5' - 1 0 " 2'-10" 119A 9' - 8 1 2" 5'-4"6'-6" 5'-4" 5' - 9 " 5' - 3 " 1' - 7 " 1 ST 1 ST OPP. HAND 4 ST 4 ST 1 ST OPP. HAND 2 ST 2 ST 3 ST ALIGN 11 ' - 8 " 101A 5 ST 5 ST 5ST ALIGN 7'-11" 125A A A A AA A A A A A C A A A C ALIGN B1 A A A A A A A1 A1 A A A A A B1 B1 B G A B1 B1 A A A 29 ' - 9 " A A 9' - 6 1 2" 1' - 4 " AL I G N E E E E E E E E1 E 1' - 6 " 12" CLR H2O 20'-0" G G G 107A WINDOW TYPE 2 WINDOW TYPE 2 WINDOW TYPE 2 WINDOW TYPE 2 WINDOW TYPE 2 WINDOW TYPE 2 WINDOW TYPE 1 WINDOW TYPE 1 WINDOW TYPE 1 WINDOW TYPE 1 WINDOW TYPE 1 WINDOW TYPE 1 115B 6' - 6 1 2" 4'-91 2" G G A A G G 1' - 1 0 " 1'-0" 19'-7"12'-11"3'-7"18'-0" 54'-0" 15 ' - 4 " 16 ' - 0 " 41 ' - 0 " 20'-3" 36 ' - 1 1 " 64'-0"10'-4" 17 ' - 0 " 1'-31 2" 1' - 1 1 " A-100 A2203 AS NOTED BID SET THIS DOCUMENT CONTAINS COPYRIGHTED MATERIAL BELONGING TO OLDENQUIST DESIGN. UNAUTHORIZED USE, DISSEMINATION, OR DUPLICATION OF THESE DRAWINGS MAY RESULT IN LIABILITY UNDER APPLICABLE LAWS. FI R S T F L O O R P L A N Glens Falls National Bank 696 Upper Glen St. Queensbury, NY FIRST FLOOR1 -1/4"=1'-0" EXISTING NIGHT DROP TO REMAIN, PROTECT DURING CONSTRUCTION NEW STEEL BEAM ABOVE CLG, SEE STRUCTURAL DRAWINGS 4 A500 8 A500 A401 PAD OUT WALL TO MATCH ADJACENT WALL THICKNESS 3/4", 8'-0" HIGH F.R. PLYWD SHEETS, CENTERED VERTICALLY AND ON ALL WALLS KEY LINE OF ETR SILL BELOW NEW SILL, TYP NEW SILL, TYP, SEE A/501 NE W S I L L NEW SILL NEW SILL NEW SILL NEW SILL NE W S I L L LOBBY 102 ATM TUBE, COORDINATE W/BANK'S VENDOR CEILING CLOUD ABOVE COPY AREA 111 TELLER LINE, SEE CASEWORK DWGS TELLER AREA 101 COUPON RM. 119 CASEWORK OPEN STORAGE 124 SOFFIT ABOVE LINE OF SOFFIT ABOVE NORTH FRAMED CHASE TO 2ND FLOOR 3/4", 8'-0" HIGH F.R. PLYWD SHEETS, CENTERED VERTICALLY ON ELEC. AREA WALLS ELEC. AREA 116 10"x10" CHASE TO ABOVE CLG RETENTION & STORAGE 107 CONFERENCE ROOM 106 STAFF LOUNGE 108 OFFICE 109 OFFICE 110 OFFICE 112 OUTER LOBBY 125 JAN. CL. 121 TOILET RM 123 TOILET RM 122 IT 120 OFFICE 114 OFFICE 113 HALL 118 MECHANICAL RM 117 REAR HALL 115 HALL 113 COUNTING 103 OFFICE 104 OFFICE 105 3 A900 10 A900 DRIVE-THOUGH CASEWORK 2 DRIVE-THOUGH CASEWORK 3 11 A900 DRIVE-THOUGH CASEWORK 1 1 A900 1 A901 2 A901 NEW RAILING 3 A901 4 A901 CASEWORK CASEWORK NE W S I L L NE W S I L L NE W S I L L 9 A500 EXISTING VAULT TYP @ ALL WINDOWS EXCEPT WEST WALL: PROVIDE 1/2" GYP BD FINISH AT WINDOW RETURNS, JAMBS AND HEAD. PATCH/REPAIR EXISTING SURFACES AS REQ., SEE SHEET A/501 CONSTRUCTION NOTES 1. PROVIDE GYP BD FINISH AT WINDOW RETURNS AND HEADS, SEE A501. PATCH/REPAIR EXISTING THE SUBSTRATE AS REQUIRED. PROVIDE LEVEL 4 FINISH AND PAINT. 2. PATCH EXISTING HOLES IN CONCRETE FLOOR WHERE RADIATOR PIPING HAS BEEN REMOVED AT PERIMETER WALLS. FINISH FLUSH WITH EXISTING FLOOR AND READY TO RECEIVE FINISH. 2. INFILL TRENCHES IN CONCRETE FLOOR, REFER TO DEMOLITION PLANS AND STRUCTURAL DRAWINGS FOR LOCATIONS. FINISH FLUSH WITH EXISTING FLOOR AND READY TO RECEIVE FINISH. 3. PREPARE EXISTING FLOORS TO A SMOOTH FINISH READY TO RECEIVE FINISHES, SEE SPECIFICATIONS FOR ADDITIONAL INFORMATION. INFILL CONSTRUCTION OPENING BELOW WINDOW, SEE DETAIL 3/A501 NEW SILLNEW SILLNEW SILLNEW SILL PAINT ETR RAILINGS, TYP ETR LADDER BANK EQUIPMENT, N.I.C., TYP TYP OF COLUMNS REPLACE ELEVATOR FLOORING TOILET ROOMS CASEWORK A700 3 A501 ETR ELEV. MACHINE ROOM, NO WORK EQUIP, N.I.C. NEW SLAB, SEE STRUCTURAL DWGS 8 A500 TYP, U.N.O. CASEWORK 12 A900 PREPARE ENTIRE WEST GYP BD. WALL AND WINDOW RETURNS TO LEVEL 4 FINISH, READY TO RECEIVE PAINT STAIR 1 218 STAIR 2 219 EXISTING WALL TO UNDERSIDE OF DECK FRAMED CHASE TO 2ND FL STANDARDS AND SHELVING FULL HT., SEE SPECS PROVIDE "KNOX ELEVATOR BOX," ALUMINUM FINSIH PROVIDE KNOX BOX "3200 SERIES," ALUMINUM FINISH, SURFACE MOUNTED 1-30-24 CONSTRUCTION DEMISING WALL BANK EMPLOYEE AND CUSTOMER ACCESS & EGRESS CONTRACTOR ACCESS AND EGRESS FIRE-RATED PARTITION MASONRY / CMU WOOD STUD FRAMING ETR CMU WALL FIRE EXTUINGISHER 5: BUILDING DEPT. RESPONSE 2-27-24 5 5 5 ADDENDUM # 4 2-26-24 4 4 209A 210A 212A 213A 214A 216A 205A 11'-2" 17 ' - 0 1 2" 10 ' - 3 " 3' - 2 " 7' - 1 " 3'-11" 4' - 1 0 " 8' - 2 " 3'-9"10'-6" 5'-5"15'-0" 9' - 5 1 2" 10 ' - 1 1 " 5' - 0 " 8'-7" AL I G N 1 ST 5'-71 2" 1'-4" A2 A2 A A A A A1 B B B1 G E E E E E E E E EE1 B B A2 11 ' - 0 1 2" 4' - 0 " C L R 204A 207A 203A 5' - 4 " ALIGN D D D D D D H2O G G 2 ST 7' - 3 " C 5 ST 1 ST 206A 11 ' - 5 " 9' - 1 12" 10'-812"10'-5" 20'-81 2" 5'-9"A2 A2 A2 A2 A C 3'-6" 202A WINDOW TYPE 4 WINDOW TYPE 4 WINDOW TYPE 4 WINDOW TYPE 4 WINDOW TYPE 4 WINDOW TYPE 4 WINDOW TYPE 4 WINDOW TYPE 5 WINDOW TYPE 5 WINDOW TYPE 5 WINDOW TYPE 5 WINDOW TYPE 5 WINDOW TYPE 5 WINDOW TYPE 6 WINDOW TYPE 6 WINDOW TYPE 6 A2 A2 DC 17'-10"3'-91 2"11'-11" 7' - 6 " 12 ' - 3 " 20'-5"11'-2" 11 ' - 6 " 20 ' - 6 " 20'-3" 35 ' - 2 " 64'-9" 4'-0" 1' - 9 " 17'-912" 56 ' - 1 0 " 13 ' - 3 " A2 G 202B A-101 A2203 1-30-24 AS NOTED BID SET THIS DOCUMENT CONTAINS COPYRIGHTED MATERIAL BELONGING TO OLDENQUIST DESIGN. UNAUTHORIZED USE, DISSEMINATION, OR DUPLICATION OF THESE DRAWINGS MAY RESULT IN LIABILITY UNDER APPLICABLE LAWS. SE C O N D F L O O R P L A N Glens Falls National Bank 696 Upper Glen St. Queensbury, NY SECOND FLOOR1 -1/4"=1'-0" 6 A400 NE W S I L L LINE OF ETR SILL BELOW NEW SILL NEW SILL, TYP, SEE 4 & 5 ON A501 NORTH 2ND FL HALL 201 OFFICE 203 OFFICE 204 COPY/STORAGE 206 12" CLR FRAMED CHASE TO ROOF MEN'S 213 JAN. CL. 214 WOMEN'S 216 STAFF LOUNGE 217 OPEN OFFICE AREA 202 OPEN OFFICE AREA 202 MECHANICAL ROOM 210 HALL 211 STORAGE 212 DATA CLOSET 209 OFFICE 207 CLOSET 215 STRIP WALL COVERING, PREPARE, & PAINT KEY CONSTRUCTION DEMISING WALL BANK EMPLOYEE AND CUSTOMER ACCESS & EGRESS CONTRACTOR ACCESS AND EGRESS FIRE-RATED PARTITION MASONRY / CMU WOOD STUD FRAMING ETR CMU WALL 5 A901 6 A901 7 A901 CASEWORK CASEWORK CASEWORK INFILL EXIST O'PG, APPROX 40"x48", SEE DETAIL 3/A501 INFILL EXIST O'PG, APPROX 40"x48", SEE DETAIL 3/A501 NEW SILLETR SILL NEW SILL NEW SILL NEW SILL NE W S I L L NEW SILL NEW SILL NEW SILL NEW SILL NEW SILL NE W S I L L NE W S I L L ET R S I L L PAINT ETR RAILINGS, TYP ETR ROOF LADDER INFILL SLAB ABOVE (ROOF) @ OBSOLETE MECHANICAL OPENING, SSD INFILL SLAB ABOVE (ROOF) @ OBSOLETE CHIMNEY OPENING, SSD A700 NE W S I L L NE W S I L L EQUIP, N.I.C. CONSTRUCTION NOTES 1. PROVIDE GYP BD FINISH AT WINDOW RETURNS AND HEADS, SEE A501. PATCH/REPAIR EXISTING THE SUBSTRATE AS REQUIRED. PROVIDE LEVEL 4 FINISH AND PAINT. 2. PATCH EXISTING HOLES IN CONCRETE FLOOR WHERE RADIATOR PIPING HAS BEEN REMOVED AT PERIMETER WALLS. FINISH FLUSH WITH EXISTING FLOOR AND READY TO RECEIVE FINISH. 2. INFILL TRENCHES IN CONCRETE FLOOR, REFER TO DEMOLITION PLANS AND STRUCTURAL DRAWINGS FOR LOCATIONS. FINISH FLUSH WITH EXISTING FLOOR AND READY TO RECEIVE FINISH. 3. PREPARE EXISTING FLOORS TO A SMOOTH FINISH READY TO RECEIVE FINISHES, SEE SPECIFICATIONS FOR ADDITIONAL INFORMATION. DUCT ENCLOSURE, SEE MECH. DWGS. PREPARE ENTIRE WEST GYP BD. WALL AND WINDOW RETURNS TO LEVEL 4 FINISH, READY TO RECEIVE PAINT CONFERENCE ROOM 205 STAIR 1 218 STAIR 2 219 ETR WALL FINISH IN STAIR NE W S I L L EXISTING CMU WALL TERMINATES BELOW EXISTING DECK; INFILL WALL WITH CMU BLOCK AND FIRESAFING, SEE DETAIL 8/A500 EXIST. WALL TO UNDERSIDE OF DECK FRAMED CHASE TO ROOF HANGAR ROD AND SHELF, SEE SPECS STANDARDS AND SHELVING FULL HT., SEE SPECS FIRE EXTUINGISHER 5: BUILDING DEPT. RESPONSE 2-27-24 5 5 5 24'-7"11'-2"10'-5" 3'-6" 13 ' - 7 " 29'-31 2" 7' - 0 " 10 ' - 1 " 6'-101 2" TYPE 3 20 ' - 2 " REF. TYPE 3 20 ' - 2 " 21 ' - 0 " 5' - 0 " 5'-0" 3'-4" 5' - 9 " PH-001 A2203 1-30-24 AS NOTED BID SET THIS DOCUMENT CONTAINS COPYRIGHTED MATERIAL BELONGING TO OLDENQUIST DESIGN. UNAUTHORIZED USE, DISSEMINATION, OR DUPLICATION OF THESE DRAWINGS MAY RESULT IN LIABILITY UNDER APPLICABLE LAWS. CO N S T R U C T I O N P H A S E S : ON E A N D T W O Glens Falls National Bank 696 Upper Glen St. Queensbury, NY 1. ABATEMENT AND DEMOLITION OF ENTIRE SECOND FLOOR. 2. CMU WALLS EXISTING TO REMAIN UNLESS NOTED OTHERWISE. 3. EXISTING I.T. REMAINS IN PLACE THIS PHASE. 4. LEAVE EXISTING TOILET ROOM NEAR BACK STAIR AND EXISTING LOUNGE COUNTER W/SINK IN PLACE TEMPORARILY FOR STAFF USE. 5. ELEVATOR REMOVALS, LOCK AT SECOND FLOOR DURING THIS PHASE. 6. REFER TO COMPLETE DEMOLITION PLAN D100. 1. CONSTRUCT SECOND FLOOR TEMPORARY BANK FACILITIES, SEE PH-002 FOR CASEWORK DRAWINGS 2. PROVIDE CONSTRUCTION DEMISING WALL. 3. INVILL BLOCK WALLS @ REAR STAIR TO DECK. 4. MAINTAIN 2ND FLOOR ACCESS TO REAR STAIRS. 5. PROVIDE TEMPORARY HEAT AND A/C TO SECOND FLOOR. 6. COORDINATE WITH AND PROVIDE ACCESS FOR OWNER'S I.T. AND SECURITY CONTRACTORS. ·SECOND FLOOR CLOSED TO THE PUBLIC ·NO WORK ON FIRST FLOOR DURING PHASE ONE.PHASE ONE STORAGEOFFICE CONFERENCE ROOM MECHANICAL AND I.T. LOBBY 4 3 2 1 COPY AREA 1. DEMO ALL OF 1ST FLOOR EXCEPT DRIVE-THROUGH, CASH ROOM, AND FRONT LOBBY. 2. MAINTAIN OPEN PATH FROM 2ND FLOOR VIA BACK STAIRS TO DRIVE-THROUGH AND VAULT. 3. PROVIDE DEMISING WALL AT DRIVE-THROUGH AND AND VAULT ACCESS. PHASE TWO VAULT DRIVE-THROUGH EXISTING COUNTING RM. MECHANICAL ·FIRST FLOOR CLOSED TO THE PUBLIC, BANK STAFF REMAIN AT DRIVE-THROUGH; MAINTAIN VAULT ACCESS ·SECOND FLOOR TEMPORARY BANK OPEN TO THE PUBLIC, ACCESS VIA LOBBY STAIRS OR ELEVATOR. MEN'S WOMEN'S JAN. CL. OFFICEOFFICE COUNTING CONF. ROOMSTORAGE LOUNGE FLEX OFFICE LOBBY COPY AREA OFFICE OFFICE OFFICE ENTRANCE LOBBY VAULT DRIVE-THROUGH EXISTING COUNTING MECHANICAL TEMP. NIGHT DROP 1. RENOVATE REMAINING AREA OF 2ND FLOOR; CONSTRUCT 2ND FLOOR BATHROOMS NEAR THE BEGINNING OF THE PHASE. 2. MAINTAIN OPEN PATH FROM 2ND FLOOR VIA BACK STAIRS TO DRIVE-THROUGH AND VAULT. 3. SEE FINISH PLANS AND RCPS FOR COMPLETE 2ND FLOOR WORK. 1. CONSTRUCT NEW FIRST FLOOR, SEE COMPLETE DRAWINGS AND SPECIFICATIONS. ENTRANCE LOBBY TEMP. NIGHT DROP CONTRACTOR ACCESS KEY CONSTRUCTION DEMISING WALL BANK EMPLOYEE AND CUSTOMER ACCESS & EGRESS CONTRACTOR ACCESS AND EGRESS FIRE-RATED PARTITION TEMPORARY CONTRACTOR ACCESS DOOR AT EXIST. WINDOW. REINSTALL WINDOW AND REPAIR WITH MATCHING BRICK AT CONCLUSION OF PHASE TEMPORARY DEMISING WALL 1, VERIFY EXACT LOCATION THE FIELD EXISTING CMU WALL TEMPORARY CONSTRUCTION WALL ELEV. MACH. RM. ELEV. MACH. RM. REMOVE CMU WALL ETR CMU WALL ETR CMU WALLS ETR CMU WALL ETR CMU WALL 2ND FLOOR DEMOLITION1 -3/32" = 1'-0" 2ND FLOOR WORK2 -3/32" = 1'-0" 2ND FLOOR RCP4 -3/32" = 1'-0" 2ND FLOOR WORK5 -3/32" = 1'-0" 1ST FLOOR DEMOLITION6 -3/32" = 1'-0" 1ST FLOOR WORK7 -3/32" = 1'-0" REMOVE ELEVATOR FLOORING TEMPORARY LOUNGE PROVIDE TEMP DRTEMPORARY DEMISING WALL 2, FOR NEXT PHASE 2ND FLOOR FINISH PLAN3 -3/32" = 1'-0" 1 PH002 8 PH-002 OFFICE OFFICE CASEWORK CASEWORK REFER TO SHEETS A100, A101 AND A500 FOR WALL TYPES AND DETAILS A2 A2 A2 A2 7ST 220A 221A 220 TELLER AREA 221 CASH BANK EQUIPMENT, N.I.C. BANK EQUIPMENT, N.I.C. 1. REFER TO SHEET A800 FOR FINISH INFORMATION. 2. EXTEND FLOOR FINISHES UNDER CASEWORK. 3. PROVIDE NEW ELEVATOR FLOORING, OTHER FINISHES BY SEPARATE CONTRACTOR. CASEWORK, N.I.C. CASEWORK, N.I.C. 1. REFER TO ELECTRICAL DRAWINGS FOR LIGHTING AND POWER SCOPE OF WORK. 2. PARTITION WALLS TERMINATE BELOW CEILING IN OPEN OFFICE AREA. ETR I.T. PANEL, THIS PHASE, PROTECT FROM DAMAGE F F F F F F 1ST FL VIGNETTE1.1 -3/32" = 1'-0" NOTES: 1. REAR STAIR AND HALL ARE PART OF PHASE ONE. 2. REFER TO SHEETS A100 FOR WALL TYPES AND DETAILS. 3. REFER TO SECOND FLOOR PLAN FOR OTHER DOOR NUMBERS. ETR IN PHASE 1&2 COUNTER AND SINK, PROTECT DURING DEMOLITION ETR IN PHASE 1&2 TOILET ROOM AND SINK, PROTECT DURING DEMOLITION TEMPORARY HEATING AND COOLING 1. TEMPORARY HEATING AND COOLING WILL BE REQUIRED DURING CERTAIN PHASES OF CONSTRUCTION. 2.PHASE 1: ALL THE SECOND-FLOOR MECHANICAL DUCTWORK WILL BE REMOVED AS PART OF DEMOLITION. TEMPORARY SECOND FLOOR HEATING AND COOLING AT CONTRACTOR'S DISCRETION. 3. THE EXISTING FIRST-FLOOR HEATING AND COOLING WILL REMAIN OPERATIONAL. PROVIDE TEMPORARY DUCTED FRESH AIR IN THE FIRST-FLOOR MECHANICAL ROOM TO THE EXISTING AIR-HANDLING UNIT DURING THIS PHASE. 4.PHASE 2: ON THE FINISHED/CUSTOMER SIDE OF THE SECOND-FLOOR CONSTRUCTION DEMISING WALL, CONTRACTOR MUST PROVIDE TEMPORARY ELECTRIC HEATING AND COOLING TO MAINTAIN THE AREA AT 70 DEGREES. 5. TEMPORARY HEATING AND COOLING UNITS MUST BE AS QUIET AS POSSIBLE AND PLACED SO THE SECOND-FLOOR BANK LOBBY, TELLER AREA, AND OFFICES MAINTAIN A PROFESSIONAL LOOK. 6. SALAMANDER HEATING UNITS IN THIS AREA ARE NOT ACCEPTABLE. 7. EXISTING WINDOWS MAY BE TEMPORARILY REMOVED TO ACCOMMODATE COOLING (“MOVE AND COOL”) UNITS. AT WINDOWS WITH AIR-CONDITIONER EXHAUST VENTS, PROVIDE FINISHED, PAINTED, WEATHER-TIGHT PANELS. 8. STAFF AND CUSTOMER CIRCULATION CANNOT BE COMPROMISED BY THE PLACEMENT OF TEMPORARY UNITS. 9. TEMPORARY FLEX-DUCT ABOVE THE SECOND-FLOOR CEILING TO DIFFUSORS IN THE FINISHED SPACES IS ACCEPTABLE. 10. TEMPORARY HEATING AND COOLING ON THE CONSTRUCTION SIDE OF THE SECOND-FLOOR DEMISING WALL AT THE CONTRACTOR'S DISCRETION. NOTE: REFER TO SHEETS A100, A101, AND A500 FOR WALL INFORMATION NOT SHOWN HERE CONTRACTOR ACCESS 5: BUILDING DEPT. RESPONSE 2-26-24 5 5 5 5 5 H2O H2O 3'-6" A-001 A2203 1-30-24 AS NOTED BID SET THIS DOCUMENT CONTAINS COPYRIGHTED MATERIAL BELONGING TO OLDENQUIST DESIGN. UNAUTHORIZED USE, DISSEMINATION, OR DUPLICATION OF THESE DRAWINGS MAY RESULT IN LIABILITY UNDER APPLICABLE LAWS. CO D E S U M M A R Y A N D N O T E S EG R E S S P L A N S Glens Falls National Bank 696 Upper Glen St. Queensbury, NY 2020 INTERNATIONAL BUILDING CODE ADOPTED BY NEW YORK STATE OCCUPANCY TYPE B BUSINESS EXISTING OCCUPANCY: B NO CHANGE OF OCCUPANCY CHAPTER 6 TYPES OF CONSTRUCTION CONSTRUCTION TYPE TABLE 601 EXISTING: TYPE IIIB BUILDING ELEMENT REQUIRED FIRE RESISTANCE PRIMARY STRUCTURAL FRAME 0 HOURS EXTERIOR BEARING WALLS 2 HOURS NON-BEARING EXTERIOR WALLS 0 HOURS BASED ON SEPARATION INTERIOR BEARING WALLS 0 HOURS INTERIOR NON-BEARING WALLS 0 HOURS FLOOR 0 HOURS ROOF 0 HOURS 1020.1 CORRIDOR WALLS EXCEPTION 4: ONLY ONE EXIT REQ. 0 HOURS DEAD END CORRIDORS NONE HEIGHTS AND AREAS - NON-SPRINKLERED, CONSTRUCTION TYPE IIIB 504.3 ALLOWABLE BUILDING HEIGHT: 55 FEET EXISTING: 30 FEET 504.4 ALLOWABLE STORIES ABOVE GRADE: THREE EXISTING: TWO 506.2 ALLOWABLE AREA:19,000 SF EXISTING: 9,420 GSF OCCUPANT LOAD AND EGRESS CAPACITY TABLE 1004.1.2 BUSINESS: 150 GSF/PERSON (NY SUPPLEMENT) BUILDING OCCUPANT LOAD: FIRST FLOOR: 4927 GSF / 150 = 33 PERSON OCCUPANT LOAD SECOND FLOOR: 4443 GSF / 150 = 30 PERSON OCCUPANT LOAD 1005.3.1 STAIRWAYS: 30 PERSON OCCUPANT LOAD @ 2ND FLOOR X 0.3" = 9 INCHES EGRESS STAIR CAPACITY PROVIDED: 4'-0" WIDTH 1005.3.2 EGRESS WIDTH: 63 TOTAL OCCUPANT LOAD X 0.2" = 12.6 INCHES EGRESS DOORS NOT LESS THAN 32 INCHES, CAPACITY PROVIDED: 6'-6" CORRIDOR: NOT LESS THAN 36 INCHES IF OCCUPANT LOAD <50; 42 INCHES PROVIDED MINIMUM NUMBER OF EXITS 1006.3.1 OCCUPANT LOAD 1-500: TWO ACTUAL: TWO FROM BUILDING 1006.2.1 - TABLE 1006.2.1 SPACES WITH ONE EXIT OR EXIT ACCESS: LOBBY MAX OCCUPANT LOAD: 49 LOBBY OCCUPANT LOAD = 15 MAX EGRESS PATH, NO SPRK'LR: 100' ACTUAL: 75 FEET SECTION 1009 - ACCESSIBLE MEANS OF EGRESS PROVIDED EXIT ACCESS TRAVEL DISTANCE 1017.2, OCCUPANCY B, NON-SPRINKLERED: 200 FEET COMPLIES CORRIDORS SECTION 1020 - EXCEPTION: NO FIRE-RESISTANCE RATING IS REQUIRED FOR CORRIDORS IN OCCUPANCY GROUP B SPACES REQUIRING ONE EXIT. TABLE 1020.2: MIN. WIDTH FOR OCCUPANT LOAD LESS THAN 50, @ EACH FLOOR REQUIRED: 36 INCHES ACTUAL: 40 INCHES MINIMUM PLUMBING CODE OCCUPANCY B WATER CLOSETS: MALE/FEMALE 1 PER 25 FOR FIRST 50 OCCUPANTS LAVATORIES 1 PER 40 FOR FIRST 80 OCCUPANTS BATHROOM FOR EMPLOYEE USE ONLY, NO PUBLIC USE FIRST FLOOR: EMPLOYEE AREA OCCUPANT LOAD: 13 PEOPLE, ONE WC AND ONE LAV REQ. 2 UNISEX TOILET ROOMS PROVIDED, ONE IS ADA COMPLIANT ONE SERVICE SINK REQUIRED: PROVIDED WATER DISPENSER PROVIDED IN LIEU OF DRINKING FOUNTAIN SECOND FLOOR: EMPLOYEE AREA OCCUPANT LOAD: 19 PEOPLE, ONE WC AND ONE LAV REQ. WOMEN'S ROOM: 2 WC, ONE ADA COMPLIANT, TWO LAVS MEN'S ROOM: 1 ADA COMPLIANT WC, 1 URINAL, TWO LAVS ONE SERVICE SINK REQUIRED: PROVIDED WATER DISPENSER PROVIDED IN LIEU OF DRINKING FOUNTAIN 2020 ENERGY CONSERVATION CONSTRUCTION CODE OF NEW YORK STATE SECTION 907 ENERGY CONSERVATION 907.1 MINIMUM REQUIREMENTS LEVEL 3 ALTERATIONS TO EXISTING BUILDINGS ARE PERMITTED WITHOUT REQUIRING THE ENTIRE BUILDING TO COMPLY WITH THE ENERGY REQUIREMENTS OF THE ENERGY CONSERVATION CONSTRUCTION CODE OF NEW YORK STATE. WHERE BUILDING ENVELOPE IS MODIFIED AT REAR EXIT: SECTION C503 ALTERATIONS, BUILDING ENVELOPE COMPLY WITH TABLE C402.1.3 CLIMATE ZONE 6 WALLS: R13 + 7.5 c.i. SLAB ON GRADE: EXISTING CEILING BELOW 2ND FLOOR: R10 TABLE C402.1.4 THERMAL ENVELOPE REQUIREMENTS - PRESCRIPTIVE OPAQUE DOORS, SWINGING DOOR: U0.37 PROVIDE THERMAL BREAK IN SLAB BETWEEN INTERIOR AND EXTERIOR, SEE DETAILS REFERENCED CODES REFERENCED CODES: 2020 EXISTING BUILDING CODE ADOPTED BY NEW YORK STATE 2020 INTERNATIONAL BUILDING CODE ADOPTED BY NEW YORK STATE 2020 FIRE CODE OF NEW YORK STATE 2020 INTERNATIONAL PLUMBING CODE 2020 ENERGY CONSERVATION CONSTRUCTION CODE OF NEW YORK STATE OTHER CODES IN FORCE: INTERNATIONAL FUEL GAS CODE INTERNATIONAL MECHANICAL CODE INTERNATIONAL PROPERTY MAINTENANCE CODE INTERNATIONAL FIRE CODE SECTION 903 NO SPRINKLER REQUIRED FIRE ALARM AND DETECTION PROVIDED CLASS A FIRE EXTINGUISHER LOCATION SPACING LESS THAN 75', COMPLIES SECTION 915 - CARBON MONOXIDE DETECTION AND NOTIFICATION - YES EXISTING BUILDING CODE SECTION 604 WORK EXCEEDS 50 PERCENT OF THE BUILDING AREA - LEVEL 3 ALTERATION COMPLY WITH PROVISION OF CHAPTERS 7, 8, AND 9 OF THE EXISTING BUILDING CODE, THE BUILDING CODE OF NEW YORK STATE EXCEPT WHERE EXCEPTIONS APPLY; THE FIRE CODE OF NEW YORK STATE. ELEVATOR - EXISTING, FINISH WORK ONLY 903.1 EXISTING SHAFTS AND VERTICAL OPENINGS EXISTING STAIRWAYS THAT ARE PART OF THE MEANS OF EGRESS SHALL BE ENCLOSED BY 1 HOUR ASSEMBLY. GENERAL NOTES 1. LIVING SPACES SHALL BE PROVIDED WITH HEATING FACILITIES CAPABLE OF MAINTAINING A MINIMUM ROOM TEMPERATURE OF 68°F AT A POINT 3 FEET ABOVE THE FLOOR AND 2 FEET FROM EXTERIOR WALLS IN HABITABLE ROOMS AT THE DESIGN TEMPERATURE. 2. ALL CO AND SMOKE ALARMS, IF REQUIRED, SHALL BE INTERCONNECTED. ALARMS SHALL BE CONNECTED TO THE PRIMARY BUILDING POWER SOURCE AND SHALL CONTAIN BATTERY BACK-UP. 3. ALL FOAM PLASTIC OR FOAM PLASTIC CORES OF MANUFACTURED ASSEMBLIES SHALL BE COVERED WITH MINIMUM 1/2 INCH GYPSUM BOARD WHICH IS MECHANICALLY FASTENED TO SUPPORT STRUCTURE. 4. IN ALL FRAMED WALLS, FLOORS, AND ROOF/CEILINGS COMPRISING ELEMENTS OF THE BUILDING THERMAL ENVELOPE, A 4-MIL POLY VAPOR RETARDER SHALL BE INSTALLED ON THE WARM SIDE OF INSULATION. 4.1. SEPARATE VAPOR RETARDER IS NOT REQUIRED WITH THE USE OF CLOSED CELL SPRAY-FOAM INSULATION. 5.VERIFY VERIFY VERIFY FIREBLOCKING SHALL BE INSTALLED TO CUT OFF ALL CONCEALED DRAFT OPENINGS BOTH VERTICAL AND HORIZONTAL BETWEEN BUILDING STORIES. BLOCKING SHALL BE INSTALLED VERTICALLY AT CEILING AND FLOOR LEVELS, AND IN ALL VERTICAL OR HORIZONTAL CAVITIES EXCEEDING 10 FT IN LENGTH OR HEIGHT AT INTERVALS NOT TO EXCEED 10 FEET. BATTS OR BLANKETS OF MINERAL OR GLASS FIBER INSULATION OR SOLID WOOD BLOCKING SHALL BE USED FOR FIREBLOCKING. REFER TO R302.11 FOR ADDITIONAL REQUIREMENTS. ARCHITECTURAL GENERAL NOTES 1. CONTRACTOR SHALL SECURE AND PAY FOR ALL REQUIRED PERMITS. 2. COORDINATE STAGING AND WORK HOURS WITH THE OWNER, SEE SPECIFICATION SECTION FOR OTHER PRE-CONSTRUCTION COORDINATION. 3. COMMENCE WORK IMMEDIATELY UPON AWARD OF THE CONTRACT AND PROCEED DILIGENTLY AND CONTINUOUSLY TO COMPLETION. 4. DO NOT INTERRUPT EXISTING UTILITY SERVICE WITHOUT AUTHORIZATION FROM THE OWNER. PROVIDE TEMPORARY SERVICE DURING INTERRUPTIONS UNLESS OTHERWISE DIRECTED BY THE OWNER'S REPRESENTATIVE. 5. PERFORM WORK IN A MATTER WHICH MINIMIZES NOISE. SCHEDULE OPERATIONS AS DIRECTED BY THE OWNER. 6. CONTRACTOR SHALL PROVIDE ALL LABOR AND MATERIALS REQUIRED TO COMPLETE THE WORK. 7. PROVIDE ALL MATERIALS AND PERFORM ALL WORK IN ACCORDANCE WITH RECOGNIZED GOOD STANDARD PRACTICES. 8. ALL ITEMS WHICH ARE NOT SPECIFICALLY REFERRED TO ON THESE DRAWINGS ARE TO BE SELECTED BY THE ARCHITECT OR OWNER FROM THE MANUFACTURER'S STANDARD SAMPLES SHOWING FULL RANGE OF TEXTURES AND COLORS. 9. FOLLOW MANUFACTURER'S SPECIFICATIONS AND INSTRUCTIONS FOR INSTALLATION OF ALL MATERIALS. 10. THE WORDS "PROVIDE" OR "SUPPLY" SHALL INCLUDE BOTH FURNISHING AND INSTALLING THE SPECIFIED OR DETAILED ITEM, IN PLACE AND READY FOR OPERATION AND USE. 11. FIELD VERIFY ALL EXISTING CONDITIONS PRIOR TO BEGINNING WORK. COMMENCEMENT OF WORK SIGNALS ACCEPTANCE OF FIELD CONDITIONS. 12. ALL DIMENSIONS SHALL BE FIELD VERIFIED. 13. MINOR ITEMS OF WORK SUCH AS CUTTING, BLOCKING, ETC. SHALL BE PERFORMED AS REQUIRED TO MAKE THE WORK COMPLETE, WHETHER SHOWN OR NOTED ON THE CONTRACT DOCUMENTS OR NOT. 14. PROVIDE TEMPORARY AND REMOVABLE PROTECTION FOR INSTALLED PRODUCTS. CONTROL ACTIVITY IN IMMEDIATE WORK AREA TO MINIMIZE DAMAGE. 15. PROVIDE PROTECTIVE COVERINGS AT WALLS, PROJECTIONS, JAMBS, SILLS, SOFFITS AND OPENINGS NOT AFFECTED BY CONSTRUCTION. 16. PROTECT FINISHED FLOORS AND OTHER SURFACES WITH DURABLE SHEET MATERIALS. FLOOR TO BE PROTECTED FROM TRAFFIC, DIRT, WEAR, DAMAGE, OR MOVEMENT OF HEAVY OBJECTS. 17. USE SUITABLE METHODS TO LIMIT DUST AND DIRT FROM ADJACENT AREAS. 18. CONTROL ACCUMULATION OF WASTE MATERIALS AND RUBBISH DURING CONSTRUCTION. LEAVE PROJECT AREA BROOM CLEAN AT THE END OF EACH DAY. REMOVE ALL DEBRIS FROM THE SITE IN ACCORDANCE WITH STATE AND LOCAL CODES. COORDINATE REMOVAL WITH OWNER. 19. ALL WORK SHALL COMPLY WITH ALL APPLICABLE GOVERNMENT CODES, RULES, AND REGULATIONS INCLUDING, BUT NOT LIMITED TO, THE "CODES, RULES, AND REGULATIONS OF NEW YORK STATE," "NEW YORK STATE ENERGY CONSERVATION CODE," OSHA, ANSI, AND NFPA. 20. THE CONTRACTOR SHALL COMPLY WITH ALL LAWS, RULES, AND ORDINANCES AND ORDERS OF ANY PUBLIC AUTHORITY BEARING ON THE PERFORMANCE OF WORK. 21. THE CONTRACTOR IS SOLELY RESPONSIBLE FOR ALL CONSTRUCTION MEANS, METHODS, TECHNIQUES, SEQUENCES, AND PROCEDURES, AND FOR COORDINATING ALL PORTIONS OF THE WORK. CONSTRUCTION NOTES 1. DO NOT SCALE DRAWINGS. INDICATED DIMENSIONS ARE TO THE CENTER LINE OF STEEL, FACE OF STUDS AT NEW PARTITIONS, FACE OF EXISTING WALL, OR FACE OF CONCRETE. 2. CONTRACTOR TO COORDINATE LOCATION OF ALL PARTITIONS ENCLOSING EQUIPMENT WITH ARCHITECT PRIOR TO BEGINNING ERECTION OF PARTITIONS. 3. CONTRACTOR SHALL INITIATE AND BE PRESENT FOR ALL INSPECTIONS REQUIRED BY LOCAL JURISDICTION, SUCH AS PLUMBING, ELECTRICAL, ETC., DURING THE COURSE OF CONSTRUCTION. 4. PARTITION CONSTRUCTION IS INDICATED BY WALL TYPE, DRAWINGS NOTES, AND/OR ROOM FINISH SCHEDULE. 5. STUD PARTITIONS SHALL HAVE DOUBLE STUDS AT ALL DOOR JAMB OPENINGS AND TRIPLE STUDS @ CORNERS; PROVIDE HEADERS / BOX HEADERS AS REQUIRED FOR OPENING. 6. WHERE METAL STUDS EXTEND TO DECK OR TRUSSES ABOVE PROVIDE SLIP TRACK TO ACCOMMODATE DEFLECTION. PROVIDE FIRESTOP TRACK AT RATED WALLS. 7. FIRE STOP ALL RATED ASSEMBLIES AT CONNECTIONS/TRANSITIONS. PENETRATIONS OF ANY FIRE/SMOKE BARRIER SHALL BE FILLED WITH MATERIAL CAPABLE OF MAINTAINING FIRE/SMOKE RESISTANCE OR PROTECTED BY APPROVED DEVICES PER IBC 2020. 8. EXTEND ALL PARTITIONS FULL HEIGHT TO STRUCTURE ABOVE, UNLESS OTHERWISE NOTED. 9. PROVIDE MOISTURE RESISTANT GYPSUM BD AT ALL PLUMBING LOCATIONS. 10. WHERE PARTITIONS ARE NOT FULL HEIGHT, EXTEND PARTITIONS 6 INCHES ABOVE CEILING MINIMUM; BRACE HORIZONTALLY TO STRUCTURE ABOVE AT 4'-0" O.C., STAGGERED EACH SIDE OF WALL. 11. PROVIDE 3/4 INCH PLYWOOD BLOCKING OR 6 INCH HIGH X 18 GA. STEEL SHEET BLOCKING IN PARTITIONS AT ALL LOCATIONS WITH SURFACED MOUNTED EQUIPMENT OR ACCESSORIES, SUCH AS HANDRAILS, TOILET ACCESSORIES, WALL BUMPERS, WALL MOUNTED DOOR STOPS, AND SUPPORT FOR WALL CABINETS, SHELVES, EQUIPMENT, ETC. 12. CONFIRM CHASE WALL DIMENSIONS WITH PLUMBING CONTRACTOR. NOTIFY ARCHITECT OF ANY DISCREPANCIES. 13. PREPARE WALLS WHERE VINYL COVERING HAS BEEN REMOVED FOR LEVEL 4 FINISH. 14. RESTORE DAMAGED AND EXPOSED FINISHES OR PATCHED AREAS IN A MANNER WHICH ELIMINATES EVIDENCE OF PATCHING AND REFINISHING. 15. LOCATE HINGE SIDE OF DOOR FRAMES 6 INCHES FROM PERPENDICULAR WALL UNLESS OTHERWISE NOTED. 16. PAINT ALL EXPOSED INTERIOR AND EXTERIOR PIPING, CONDUITS, ETC. TO MATCH ADJACENT WALL SURFACE, UNLESS OTHERWISE NOTED. 17. ALL NEW DOOR HARDWARE SHALL BE ADA COMPLIANT, COORDINATE SELECTION AND KEYING WITH OWNER. 18. FIRE EXTINGUISHER CABINETS SHALL BE INSTALLED 48 INCHES TO TOP OF CABINET. 19. PREPARE EXISTING FLOORS PRIOR TO INSTALLING FLOOR FINISHES. PROVIDE FLAT AND LEVEL FINISH AS RECOMMENDED BY NEW FLOORING MANUFACTURER. SEE SPECIFICATIONS. 20. COORDINATE ROOF WORK WITH EXISTING ROOF MANUFACTURER, COMPLY WITH MANUFACTURER RECOMMENDATIONS SO AS TO MAINTAIN ROOF WARRANTY. 21. PROVIDE WALL RATING SIGNS ABOVE CEILING AT RATED PARTITION WALLS. 22. PROVIDE TRUSS ID STICKERS ON EVERY EXTERIOR DOOR. STAIR AND LANDING NOTES 1. STAIRWAY SHALL NOT BE LESS THAN 36 INCHES WIDE IN CLEAR WIDTH AT ALL POINTS ABOVE THE PERMITTED HANDRAIL HEIGHT AND BELOW THE REQUIRED HEADROOM HEIGHT. HANDRAILS SHALL NOT PROJECT MORE THAN 4 1/2 INCHES ON EITHER SIDE OF THE STAIRWAY AND THE MINIMUM CLEAR WIDTH OF THE STAIRWAY AT AND BELOW THE HANDRAIL HEIGHT, INCLUDING TREADS AND LANDINGS, SHALL NOT BE LESS THAN 31 1/2 INCHES WHERE THE HANDRAIL IN INSTALLED ON ONE SIDE AND 27 INCHES WHERE THE HANDRAILS ARE PROVIDED ON BOTH SIDES. 2. THE MAXIMUM RISER HEIGHT SHALL BE 8 INCHES AND THE MINIMUM TREAD DEPTH SHALL BE 9 INCHES. 3. THE MINIMUM HEADROOM IN ALL PARTS OF THE STAIRWAY SHALL NOT BE LESS THAN 6'-8" MEASURED VERTICALLY FROM THE SLOPED PLANE ADJOINING THE TREAD NOSING OR FROM THE FLOOR SURFACE OF THE LANDING OR PLATFORM. 4. PORCHES, BALCONIES, OR RAISED FLOOR SURFACES LOCATED MORE THAN 30 INCHES ABOVE THE FLOOR OR GRADE BELOW SHALL HAVE GUARDS NOT LESS THAN 42 INCHES IN HEIGHT. OPEN SIDES OF STAIRS WITH A TOTAL RISE OF MORE THAN 30 INCHES ABOVE THE FLOOR OR GRADE BELOW SHALL HAVE GUARDS NOT LESS THAN 42 INCHES IN HEIGHT MEASURED VERTICALLY FROM THE NOSING OF THE TREADS. 5. REQUIRED GUARDS ON OPEN SIDES OF STAIRWAYS, RAISED FLOOR SURFACES, BALCONIES, AND PROCHES SHALL HAVE INTERMEDIATE RAILS OR ORNAMENTAL CLOSURES THAT DO NOT ALLOW THE PASSAGE OF A SPHERE 4 INCHES OR MORE IN DIAMETER. 6. HANDRAILS SHALL BE PROVIDED ON AT LEAST ONE SIDE OF EACH STAIRWAY WITH TWO OR MORE RISERS. HANDRAIL HEIGHT, MEASURED ABOVE THE TREAD NOSINGS, SHALL BE NOT LESS THAN 34 INCHES AND NOT MORE THAN 38 INCHES. ALL REQUIRED HANDRAILS SHALL BE CONTINUOUS THE FULL LENGTH OF THE STAIRS FROM A POINT DIRECTLY ABOVE THE TOP RISER OF A FLIGHT TO A POINT DIRECTLY ABOVE THE LOWEST RISER OF THE FLIGHT. 7. HANDRAILS ADJACENT TO A WALL SHALL HAVE A SPACE OF NOT LESS THAN 1 1/2 INCHES BETWEEN THE WALL AND THE HANDRAIL. 8. ENCLOSED ACCESSIBLE SPACE BENEATH STAIRWAYS SHALL HAVE WALLS AND UNDER STAIR SURFACE ON THE ENCLOSED SIDE WITH A 1/2 INCH GYPSUM COVERING. 9. REQUIRED EXTERIOR EGRESS DOORS SHALL HAVE A LANDING OR FLOOR ON EACH SIDE OF THE DOORWAY. THE LANDING OR FLOOR AREA EACH SIDE SHALL BE MINIMUM 3'-0" X 3'-0". THE LANDING OR FLOOR SHALL BE MAXIMUM 1-1/2" BELOW THE DOOR THRESHOLD ON THE SIDE UNDER THE DOOR SWING, AND MAXIMUM 8 1/4" BELOW THE THRESHOLD WHEN THE DOOR DOES NOT SWING OVER THE FLOOR OR LANDING. 10. ALL EXTERIOR DOORS, OTHER THAN ANY REQUIRED EGRESS DOOR, SHALL HAVE A LANDING OR FLOOR ON EACH SIDE OF THE DOORWAY. THE LANDING OR FLOOR AREA EACH SIDE SHALL BE MINIMUM 3'-0" X 3'-0". THE LANDING OR FLOOR SHALL BE MAXIMUM 7 3/4" BELOW THE DOOR THRESHOLD ON EACH SIDE. A TOP LANDING IS NOT REQUIRED WHERE A STAIRWAY OF NOT MORE THAN TWO RISERS IS LOCATED ON THE EXTERIOR SIDE OF THE DOOR, PROVIDED THAT THE DOOR DOES NOT SWING OVER THE STAIRWAY. KEY BANK EMPLOYEE AND CUSTOMER ACCESS & EGRESS FIRE-RATED PARTITION LIFE SAFETY PLANS: TRAVEL DISTANCE FIRST FLOOR NTS 48'-6" 40'-2" 67'-0" SECOND FLOOR NTS 52'-7" 79'-6" 87'-0" OFC OFC OFC OFC OFC OFC MTG. RM. CONF. RM. STORAGE LOUNGE COPY AREA ENTRANCE LOBBY LOBBY VAULT C'PON I.T. JAN. TELLER AREA MECH. RM. COUNT'G EXIT EXIT OPEN OFC. AREA STORAGE MECHANICAL RM. CL. CONF. RM. STORAGE LOUNGE OFC OFC OFC MEN'S WOMEN'S CL. UPPER LOBBY JAN. CMU WALL 37'-2" 24 " 14 ' - 7 " 37'-0" 6'-0" 2' - 0 " 16'-0" 16'-0" 2' - 0 " 14 ' - 0 " D-001 A2203 1-30-24 AS NOTED BID SET THIS DOCUMENT CONTAINS COPYRIGHTED MATERIAL BELONGING TO OLDENQUIST DESIGN. UNAUTHORIZED USE, DISSEMINATION, OR DUPLICATION OF THESE DRAWINGS MAY RESULT IN LIABILITY UNDER APPLICABLE LAWS. DE M O L I T I O N P L A N S Glens Falls National Bank 696 Upper Glen St. Queensbury, NY FIRST FLOOR DEMOLITION1 -3/16"=1'-0" NORTH SECOND FLOOR DEMOLITION2 -3/16"=1'-0" NORTH GENERAL DEMOLITION NOTES: 1. THIS PLAN REPRESENTS ALL REMOVALS, REFER TO THE PHASING PLANS FOR THE REMOVALS ASSOCIATED WITH EACH PHASE. 2. REFER TO ABATEMENT DRAWINGS FOR EXTENT AND SCOPE OF HAZARDOUS MATERIALS REMOVALS. 3. REFER TO MEP DRAWINGS FOR ADDITIONAL SCOPE DESCRIPTION AND TIMING OF MECHANICAL, ELECTRICAL, AND PLUMBING REMOVALS. 4. REFER TO SITE PLAN FOR SCOPE DESCRIPTION AND TIMING OF SITE DEMOLITION. 5. DASHED LINES INDICATE ITEMS AND ELEMENTS TO BE REMOVED. 6. THE BUILDING WILL BE OCCUPIED DURING CONSTRUCTION. ALL ACTIVITIES SHALL BE CONFINED TO THE AREA OF WORK. COORDINATE ANY PLUMBING, ELECTRICAL, OR MECHANICAL WORK THAT IMPACTS OTHER AREAS OF THE BUILDING WITH THE OWNER. 7. DO NOT BLOCK ANY EGRESS FROM OCCUPIED PARTS OF THE BUILDING. NO WORK: 1. EXISTING GYP BD AT EXTERIOR WALLS TO REMAIN UNLESS NOTED OTHERWISE. 2. EXISTING WINDOWS TO REMAIN, UNLESS NOTED OTHERWISE. 3. EXISTING WINDOW SILLS TO REMAIN, UNLESS NOTED OTHERWISE. 4. ELEVATOR MACHINE ROOM N.I.C., PROTECT FROM DAMAGE DURING CONSTRUCTION. 5. MAINTAIN ELEVATOR SERVICE THROUGHOUT WORK. PROTECT EXISTING & NEW FINISHES. 6. PROTECT DRIVE THROUGH TUBES AND DRAWER DURING DEMOLITION. 7. EXISTING TOILET ROOM PLUMBING WALLS TO REMAIN. 8. EXISTING CMU WALLS TO REMAIN, UNLESS NOTED OTHERWISE. 9. STRUCTURAL ELEMENTS TO REMAIN, UNLESS NOTED OTHERWISE. 10. NIGHT DROP BOX TO REMAIN, PROTECT DURING DEMOLITION. GENERAL REMOVALS: 1. INTERIOR PARTITIONS, TYP. SEE DEMO PLANS FOR LOCATION OF CMU WALLS SECTIONS TO BE REMOVED. 2. INTERIOR DOORS AND FRAMES. 3. BORROWED LITES. 4. FLOOR FINISHES AND BASE THROUGHOUT, U.N.O., INCLUDING CARPET AND TILE, DOWN TO SUB-FLOOR. 5. MARBLE THRESHOLDS AT BATHROOMS. 6. ACOUSTICAL CEILING TILES AND GRID. 7. LIGHT FIXTURES, GRILLES, AND OTHER CEILING FIXTURES. 8. GYP BOARD CEILINGS AND SOFFITS. 9. ALL OBSOLETE DATA, PHONE, & SECURITY WIRING. CURRENTLY ACTIVE DATA CABLES ABOVE THE CEILING AND ELSEWHERE IS PINK, DO NOT REMOVE. 10. TOILET ROOM FIXTURES; CAP WATER LINES AS REQUIRED. 11. ALL CASEWORK. 12. WINDOW TREATMENTS. 13. REFER TO MECHANICAL, ELECTRICAL, AND PLUMBING DRAWINGS FOR REMOVALS IN THOSE TRADES. DEMOLITION KEY NOTES: REFER TO PHASING PLAN FOR SEQUENCING A. REMOVE MASONRY CHIMNEY, SEE STRUCTURAL DWGS, PATCH ROOF IN A WATER-TIGHT MANNER THAT MAINTAINS ROOF WARRANTY. B. REMOVE TELLER LINE. C. REMOVE WORK TABLE. D. REMOVE VINYL WALL COVERING AT ETR WALLS AND WINDOW RETURNS. EXIST WALL COVERING CAN REMAIN WHERE ETR WALLS RECEIVE NEW GYP BD, WALL TYPES E & G, SEE PLANS. E. REMOVE SOFFIT. F. CMU REMOVAL. G. REMOVE GUARD RAILS AND HAND RAILS, SEE SHEET A700 H. REMOVE SECTIONS OF CONCRETE SLAB. I. REMOVE WALL TILE. J. REMOVE WOOD AND GLASS PARTITION WALL ETR VAULT MASONRY / CMU STUD FRAMING A A B C D E F F F G G G G G CP T VC T CPT VCT VC T CP T O V E R V C T VCT CPT OVER VCT VCT CPT VCT TILE DRIVE-THROUGH DRAWER TO REMAIN, PROTECT DURING CONSTRUCTION DRIVE-THROUGH TUBES TO REMAIN DURING FIRST TWO PHASES OF WORK, PROTECT DURING CONSTRUCTION. ATM TUBE TO REMAIN DURING FIRST TWO PHASES OF WORK, PROTECT DURING CONSTRUCTION. REMOVE EXISTING CMU BEARING WALL, COORDINATE REMOVAL OF THIS SECTION OF WALL WITH PLACEMENT OF NEW STEEL BEAM, SEE STRUCTURAL DRAWINGS F ETR NIGHT DROP BOX REMOVE FLOOR FINISHES THROUGHOUT, TYP ETR PLUMBING WALL COLUMN, TYP KEY: ETR CMU WALL REMOVE CONCRETE SLAB REMOVE CONC. SLAB TO EXTEND CHASE WALL REMOVE CONC. SLAB TO EXPOSE EXISTING WASTE LINE H HH CUT TRENCH FOR DATA, POWER, FLOOR BOX IN NEW CONF. ROOM D I I I I I I I D TYP @ WEST WALL TYP @ WEST WALL I I I J REMOVE AND REPLACE SLAB TO ACCOMMODATE GEOTHERMAL PIPING, SEE MEP AND STRUCTURAL DRAWINGS H F F F F F F ETR ROOF LADDERETR ROOF LADDER VCT VCT LINE OF WALL BELOW SILL, TYP ETR COLUMN APPROXIMATE LINE OF EXISTING FOOTINGS, DO NOT REMOVE OR DAMAGE LINE OF WALL BELOW SILL, TYP BATHROOM AND SINK TO REMAIN UNTIL SECOND FLOOR BATHROOMS ARE COMPLETE IN PHASE 2 KITCHEN SINK AND COUNTER TO REMAIN UNTIL THE CONCLUSION OF PHASE 3