Site Plan 31-2017 Robert Fulmer
Freshwater Wetlands 3-2017 54 Country Club Road/ SFR IA/MDR—Single Family Residential 1 acre/
Moderate Density Residential/Ward 1
SEQR Type II
Material Review: application, survey, elevations, revision includes photos, updated data chart,
site plan with reduced size building
Parcel History: SP 34-2007, AV 39-2007, FWW1-2007 all for 2,050 addition; AV 29-2017
Requested Action
Planning Board review and approval to construct a revised two door, 750 sq. ft. detached garage.
Resolutions
1. Planning Board decision
Prosect Description
Applicant proposes to construct a revised two door, 750 sq. ft. detached garage. Pursuant to Chapter 179-5-020
of the Zoning Ordinance, work within 100ft. of wetland shall be subject to Planning Board review and approval.
Staff Comments
• Location-Project site is at 54 County Club Rd.
• Arrangement- The revised 750 sq ft detached garage is to be located 65 +/- ft from the existing wetland
pond area and 70 ft from the wetland area on the west property line. The applicant had previously removed
an 1800 sq ft blacktop pad and the plans note the area has been seeded.
• Building, Elevation & Floor plan—The plans show the garage to have 2-garage doors and an open floor
plan. The garage is to be 20ft 4 in+/- ft in height. The applicant has indicated there will be no stairs or pull
down stairs and the rear of the building is to be the same as the front without doors. There is to be a regular
door on the south side of the building.
• Site conditions-The applicant has provided a survey with delineated wetlands on the site. The applicant has
indicated a NYSDEC permit has been applied for and received.
• Site layout and utility plan—The applicant proposes to connect electric to the garage. There is to be no
water or septic connection.
• Grading and drainage plan & Sediment and erosion control- The location of the garage is in an open area on
the lot and no clearing is anticipated. The board may discuss the use of silt fence around the pond and
wetland area during construction to minimize any potential runoff towards the pond or wetland. The
applicant has indicated runoff from the new garage will be infiltrated into the lawn area at the eaves of the
building.
• Landscape plan no new landscaping is anticipated. There is no new hard surfacing to the garage proposed
the area is to remain lawn.
• Site lighting plan—exterior lighting is not proposed. The board may request confirmation on exterior
lighting as the garage is to be connected to electric.
Pursuant to Section 179-9-050 the Planning Board may grant waivers on its own initiative or at the written
request of an applicant. The application form identified as "Requirements" outlines the items to appear on the
site plan or included as attachments. At the time of application the applicant has either requested waivers,
indicated the item not applicable or has not addressed the item/ left check box blank. This includes the follow
items listed under Requirements of the applicant's application: g. site lighting, h. signage, k. topography, n
traffic, o. commercial alterations/ construction details, p floor plans, q. soil logs, r. construction/demolition
disposal s. snow removal.
Freshwater wetland
The applicant proposes the construction of the second garage within the 100 ft buffer of the pond and wetland
area. The applicant has indicated no work is to occur in the wetland or the pond area and measures will be
implemented to minimize any runoff.
Nature of Variance
Granted 11/15/17. The applicant proposes to construct a second garage that is to be detached where there is an
existing attached garage to the existing home. Relief is requested for having two garages where only one is
allowed.
Summary
The applicant has completed a site plan application for the construction of a second garage within 100 ft of the
buffer area of a delineated wetland.
Meeting History PB: 4/25/17, 5/2/17 tabled, 7/25/17 tabled, 9/19/17 tabled; ZBA: 4/26/17 tabled, 6/21/17
tabled, 7/19/17 tabled, 9/20 tabled;