Signed Inspection Report (Thu Mar 4, 2021 at 348 PM)INSPECTION WORKSHEET (BINS-008704-2021)
Town of Queensbury - Building and Codes - Fire Marshal
742 Bay Road - (518) 761-8256 Building (518) 761-8206 Fire Marshal
Case Number:AST-0593-2019 Case Module:Permit
Inspection Date:Thu Mar 4, 2021 Inspection Status:Passed
Inspector:O'Brien, John Inspection Type:Building Insulation
Job Address:Parcel Number:133 Jenkinsville RD
Queensbury, NY, 12804
279.-1-21
Contact Type Company Name Name
Concrete Contractor A.J. Catalfamo Construction Co., Inc.
Architect Rucinski-Hall Architecture
Granted Permission TOWN OF QUEENSBURY REC
DEPT
Primary Owner TOWN OF QUEENSBURY REC
DEPT
Checklist Item Status
Building Inspector Notes Passed
2/3/20 Insulation Not Approved
Remaining Items:
- Remove a sheet of fire retardant plywood from each wall to verify the insulation in wall has been installed
correctly.
- Provide documentation that states that R38 insulation has been installed in ceiling and R21 has been installed in
the exterior walls as per the approved COMcheck Energy Code Compliance Report.
- Provide documentation that the windows and insulated door have the correct U value as per the approved
COMcheck Energy Code Compliance Report.
2/18/20 Insulation Partial Approval
- Insulation documentation received from manufacturer.
The installation verified and approved in accordance with the approved COMcheck.
Remaining Items:
- Provide documentation showing what the U value is for the windows and exterior doors.
- Verify perimeter of windows and doors have been sealed with sprayfoam.
- Schedule blower door test for addition.
3/4/21 Building Insulation Approved
Mar 04, 2021 Page (1)
INSPECTION WORKSHEET (BINS-008704-2021)
Checklist Item Status
- Received final approval letter from ClearVu Inspections stating the building addition is in compliance with the
IECC code section C402.5 for air leakage in lieu of a blower door test. It complies with sections C402.5.1 thru
C402.5.8.
Insulation Residential Check Commercial Check Passed
2/3/20 Insulation Not Approved
Remaining Items:
- Remove a sheet of fire retardant plywood from each wall to verify the insulation in wall has been installed
correctly.
- Provide documentation that states that R38 insulation has been installed in ceiling and R21 has been installed in
the exterior walls as per the approved COMcheck Energy Code Compliance Report.
- Provide documentation that the windows and insulated door have the correct U value as per the approved
COMcheck Energy Code Compliance Report.
2/18/20 Insulation Partial Approval
- Insulation documentation received from manufacturer.
The installation verified and approved in accordance with the approved COMcheck.
Remaining Items:
- Provide documentation showing what the U value is for the windows and exterior doors.
- Verify perimeter of windows and doors have been sealed with sprayfoam.
- Schedule blower door test for addition.
3/4/21 Building Insulation Approved
- Received final approval letter from ClearVu Inspections stating the building addition is in compliance with the
IECC code section C402.5 for air leakage in lieu of a blower door test. It complies with sections C402.5.1 thru
C402.5.8.
Mar 04, 2021 Page (2)
O'Brien, John