WHEREAS, the Queensbury Town Board previously established Capital Reserve Funds
known as the Recreation Reserve No. 61 (Fund No. 61) and Capital Reserve No. 64 (Fund No. 64)
for future capital projects, and
WHEREAS, by Memorandum to the Town Board dated June 11, 2021, the Queensbury
Recreation Commission requested funding approval for proposed specific capital improvements
and certain maintenance projects at several of the Town Parks (Projects), and
WHEREAS, the Town Board wishes to authorize such Projects and the withdrawal and
expenditure of moneys from Reserve Nos. 61 and 64 in the total estimated amount of$206,000 as
follows:
Park Location Capital Proiect Cost Est. Funding Source
Pro aect No. Capital Reserve No.
Gurney Lane Rec Area 157 $98,500 64
Jenkinsville Park 138 $23,000 61
Hudson Pointe Preserve 145 $12,500 61
Rush Pond Trail 166 $42,000 64
Hudson River Park 107 $30,000 64
TOTAL PROJECT $206,000
ESTIMATES
and
WHEREAS, in accordance with New York State General Municipal Law §6(c), the Town
Board is authorized to withdraw and expend funds from Reserves #61 and #64 subject to
permissive referendum,
NOW,THEREFORE,BE IT
RESOLVED, that the Queensbury Town Board hereby finds that the withdrawal and
expenditure for the specific capital improvements and certain maintenance projects (Projects) as
delineated in the preambles of this Resolution are expenditures for specific capital projects and
certain maintenance projects for which the Reserve Accounts were established and therefore
authorizes and expenditures in the total estimated amount of$206,000 ($35,500 from Reserve #61
and$170,500 from Reserve 464), as follows:
Park Location Capital Proiect Cost Est. Funding Source
Proiect No. Capital Reserve No.
Gurney Lane Rec Area 157 $98,500 64
Jenkinsville Park 138 $23,000 61
Hudson Pointe Preserve 145 $12,500 61
Rush Pond Trail 166 $42,000 64
Hudson River Park 107 $30,000 64
TOTAL PROJECT $206,000
ESTIMATES
as set forth in the Queensbury Recreation Commission's June 11, 2021 Memorandum presented at
this meeting,and
BE IT FURTHER,
2
RESOLVED,that the Town Board hereby authorizes:
1. a transfer from Reserve No.: 61 in the amount of$35,500; and
2. a transfer from Reserve No.: 64 in the amount of$170,500;
to fund such Projects, such respective fund amounts to be placed into the respective Park
Improvement Project Funds, reopening them as may be necessary, and the Town Board further
directs that in the event there are funds remaining in such Funds after completion of the Project(s)
or in the event that the Project(s) are not undertaken, the moneys in such Funds shall be returned to
the Reserve(s), and
BE IT FURTHER,
RESOLVED, that the Town Board further authorizes and directs the Town Board Officer
to increase appropriations and estimated revenues, amend the Budget and take all actions as may
be necessary to fund such Projects as authorized, and
BE IT FURTHER,
RESOLVED, that the Town Board further authorizes and directs the Town Purchasing
Agent to publish any needed advertisement(s) for bids for capital improvements and/or items of
equipment related to the Projects funded by this Resolution as deemed applicable or required
based upon the Town's Purchasing Policy or the General Municipal Law, and
BE IT FURTHER,
RESOLVED, that the Town Board further authorizes and directs the Town Supervisor,
Parks & Recreation Director and/or Town Budget Officer to take all actions necessary to effectuate
the terms of this Resolution, and
3
BE IT FURTHER,
RESOLVED, that this Resolution is subject to a permissive referendum in accordance with
the provisions of Town Law Article 7 and the Town Board hereby authorizes and directs the Town
Clerk to publish and post such notices and take such other actions as may be required by law.
Duly adopted this 21st day of June, 2021 by the following vote:
AYES
NOES
ABSENT
4
PARKS & RECREATION
742 Bay Road,Queensbury NY 12804-9725 1 T: (618)761-8216 1 F:(518)798-3194 i http:Hrecreation.queensbury.net
TO: Queensbury Town Board
FROM: Queensbury Recreation Commission
DATE: June 11, 2021
RE: 2021 Recreation Commission Capital Projects
The Queensbury Recreation Commission has reviewed and approved the following capital
improvement projects for 2021 and is seeking funding approval from the Queensbury Town
Board. Funding for the projects listed below would be requested from both the Recreation
Reserve Fund (#61) and the Town's Capital Reserve Fund (#64).
We are requesting Town Board approval of a funding resolution at the June 21 board
meeting. In the meantime, if you have any questions or need additional information, please
do not hesitate to contact Director Lovering at your convenience.
Additional project information has been attached regarding each of the following Recreation
Commission projects:
2021 CAPFAL PROJECTS
Park Location/Ward Total Project Cost Est. Potential Funding Source
Gurney Lane Rec. Area —Ward #1 $98,500 Capital Reserve Fund #64
Jenkinsville Park—Ward #1 $23,000 Recreation Reserve Fund #61
Hudson Pointe Preserve—Ward #4 $12,500 Recreation Reserve Fund #61
Rush Pond Trail—Ward #3 $42,000 Capital Reserve Fund #64
Hudson River Park—Ward #4 $30,000 Capital Reserve Fund #64
TOTAL PROJECT ESTIMATES $206,000
FUNDING FROM REC. RESERVE #61 $35,500 (current balance =$141,000)
FUNDING FROM REC. RESERVE#64 $170,500
b:i1LtA.;ry
'- RECREATION
742 Bay Road,Queensbury NY 12804!-972 I P(518)761-8215 1 F:(51',798-3-194 http:irl,ecraatlon.queensbunj.net
PROJECT EVALUATION PROCESS
The parks and recreation staff and the Recreation Commission continue, on a yearly basis,
to evaluate the needs prior to selecting the potential park improvement projects. Each
park's individual needs were assessed based upon a set of criteria which included the
following:
• #1 - SAFETY/MAINTENANCE: Projects meeting this criteria were identified
due to a safety concern or was part of routine maintenance in order to avoid
a more costly expense in the future.
• #2- IMPROVED/ADDED AMENITY: Projects selected under this criteria were
identified for improvement of an existing aspect of the park or to add as a new
amenity to offer park users, based on feedback received or new trends.
• #3 - AESTHETICS/FUNCTIONALITY: Projects matching this criteria were
recognized in order to improve the current appearance or to give better over-
all function.
Once each park's projects were identified, they were ranked in order of importance and
were either added to the 2021 project list (attached) or were set aside for future projects.
PROJECT TOTALS
Eleven individual improvement items were identified for 2021 in five of the Town's eleven
park locations.
❖ 2021 TOTALS BY WARD
o Ward 1: $121,500- 2 park project plans (8 improvement items)
o Ward 2: $0- No projects
o Ward 3: $42,000- 1 park project (1 improvement item)
o Ward 4: $42,500-2 park projects (2 improvement items)
❖ 2021 TOTALS BY CRITERIA (#1 -#3, as described above)
o Safety/Maintenance: $49,000-2 park locations (3 improvement items) .
o Improved/Added Amenity: $132,000—4 park locations (7 improvement items)
o Aesthetics/Functionality: $25,000— 1 park location (1 improvement item)
J-1w, lovlqLl
Z .-I Palsok prujcus
Capfflt,al Expendi-ture Keque
kj
PARKS & RECREATION
-74,2�,-.)Y QW-zGri-.3bur-,N',I,'1280ZIA7'_�F, !3-18,7-,_�,!-:32,16 F:1:31-3)
2021 (1,AP1TAt, PRWAKT PLAN
PARK: Gurney Lane Recreation Area—(Gurney La., Ward 1)
PROJECT SCOPE: All planned work include projects that meet certain project criteria (outlined below).
(1) safety/maintenance, F` Ill?n: .. . ...., _.;t:1'. .. :(; "l and iD)
• Hiking—blue trail maintenance and drainage repair work (11)
• Mtn. bike park trail maintenance and drainage repair work
• Playground improvements—fiew equipment
• Nature trail development—phase#2
• Replace 16 year old pool slide
• Park front entrance redesign —address traffic safety concerns (3)
BUDGET ESTIMATE: $98,500
PROJECT FUNDS NEEDED: $98,500
FUNDING SOURCE: Capital Improvement Fund#64-($98,500)
PARK: Jenkinsville Park— (Jenkinsville Rd., Ward 1)
PROJECT SCOPE: All planned work include projects that meet certain project criteria (outlined below).
(1) safety/maintenance, 2*1J,I—I d ( ) i oA L Y.33s� in• Seal and restripe all parking areas (1)
• Painting and outside repairs to soccer field house bldg. (1/1
BUDGET ESTIMATE: $23,000
PROJECT FUNDS NEEDED: $23,000
FUNDING SOURCE: Recreation Reserve Fund#61 -($23,000)
PROJECT CRITERIA: #1—Safety/maintenance: Based on a safety concern or part of routine maintenance
-!RV! lderltflecci to :-rnpi,ove -at" a-xisting aspa- cof 1-he park cjir add D neliv amenity
iden Ldflied in order to improve the Urrent appearance or to give better function
PARK,-N RECREATION
(N� 42? T"-1,51;3",-!f;,;-62,16 1 ;31
kw Road.Queenzi):uri
R E CR EE AT 10 f,\J 00 N11 i'A� 155 1 0 N 2 02 C'�
J �t. IV) C.)JECT
PARK: Rush Pond Trail — (West Mtn. Rd., Ward 3)
PROJECT SCOPE: All planned work include projects that meet certain project criteria (outlined below).
i
(1) safetv./maintenance, and (3)
0 Begin phase#2 Design, layout and install of bike trails along the Rush Pond Trail corridor
0 Develop a new neighborhood trailhead and connection trail to Indian Ridge (3)
BUDGET ESTIMATE: $42,000
PROJECT FUNDS NEEDED: $42,000
FUNDING SOURCE: Capital Improvement Fund#64-($42,000)
PARK: Hudson Pointe Preserve— (Hudson Pointe Blvd., Ward 4)
PROJECT SCOPE: All planned work include projects that meet certain project criteria (outlined below).
(1) safety/maintenance, (2.) and (31
0 Complete a .4 mile trail loop, and floating bridge maintenance and repairs
BUDGET ESTIMATE: $12,500
PROJECT FUNDS NEEDED: $12,500
FUNDING SOURCE: Recreation Reserve Fund#61 -($12,500)
PARK: Hudson River Park— (Big Boom Rd., Ward 4)
PROJECT SCOPE:All planned work include projects that meet,
certain project criteria (outlined below).
and
(1) safety/maintenance, in, ;:.-,j i1H .
• Design and build a "paddle park" offering upgraded kayak docks, secure storage and improved
shoreline (walkway, benches, etc.)
BUDGET ESTIMATE: $30,000
PROJECT FUNDS NEEDED: $30,000
FUNDING SOURCE: Capital Improvement Fund#64-($30,000)
PROJECT CRITERIA: #1—.5afeti//Maintenance: Based on a safety concern or part of routine maintenance
Jlnorovad/ Cd n "o i� IV8 :l�" Hng :�pe�:t of therk LAd A , pa o to new
i
Gurney Lane Recreation Area - Ward #1
Potential Selection
2021 PROJECT ITEM
Cost Criteria
Walking/hiking trail development and maintenace(blue trail) $14,000 2
Mtn. bike park trail development and maintenace $10,000 2
Playground improvements-additional equip+rplc.Swings $18,000 2
Replace 15 yr.old pool slide $26,000 1/2
Nature trail-phase 2,educational&wayward signage(design&install) $5,500 2
Redesign front entrance-eliminate roadside parking due to safety concerns $25,000 3
PROJECT TOTALS $98,500
Jenkinsville Athletic Fields - Ward #1
2021 PROJECT ITEM Potential Selection
Cost Criteria
Sealcoating of parking areas $18,000 1
Painting+exterior repairs on soccer field house bldg. $5,000 1
PROJECT TOTALS $23,000
Rush Pond Trail - Ward #3
Potential Selection
2021 PROJECT ITEM Cost Criteria
Begin phase#2 of bike trail development along the walk way corridor of Rush Pond-reduce trail conflict
between walkers. Develop Farr Ln.neighborhood entrance $42,000 2
PROJECT TOTALS $42,000
Hudson Pointe Preserve - Ward #4
Potential Selection
2021 PROJECT ITEM Cost Criteria
Complete a.4 mile trail loop+marshland trail and bridge repair/maintenace issues $12,500 2
PROJECT TOTALS $12,500
Hudson River Park - Ward #4
2021 PROJECT ITEM Potential Selection
Cost Criteria
Creation of a dedicated "paddle park"-upgraded, handicap accessible kayak docks, secure storage
lockers for kayaks, shoreline improvements (walkway, benches,etc.) $30,000 2
PROJECT TOTALS $30,000
22. TOTAL PROPOSE b CAPITAL IMPROVEMENTS
There were no funding requests recommended for 2021 at the following parks: Nleadowbrook
Preserve, Feeder Canal Park, .Hovey Pored, GL Boat Launch 8< West End .Park
20201 PARK PROJECTS EST. COSTS
Gurney Lane $98,500
Jenkinsville $23,000
Hudson Pointe Preserve $12,500
Hudson River Park $30,000
Rush Pond Trail $42,000
Meadowbrook Preserve $0
Feeder Canal Park $0
Hovey Pond Park $0
Glen Lake Boat Launch $0
West End Park $0
TOTALS $206,000
CRITERIA: All projects identified fall into one of three different categories
1 -Safety/Maintenance:The project was identified due to a safety concern or was part of routine maintenace
in order to avoid become a safety concern.
2- Improved/Added Amenity:The project was identified to improve an exisitng aspect of the park or to add a
new amenity based on user feedback or new trends.
3 -Aesthetics/Functionality: the project was identified in order to improve the current appearance or to give
better function