Approval Resolution TOWN OF QUEENSBURY Community Development Office 742 Bay Road, Queensbury, NY 12804-5902 Town of Queensbury Planning Board RESOLUTION APPROVING SITE PLAN 34-2010 CAPITAL REGION PROPERTIES, LLC [D/B/A DUNHAM’S BAY RESORT] July 20, 2010 1. A site plan application has been made to the Queensbury Planning Board for the following: Applicant proposes a 5,650 sq. ft. outside patio banquet area with covered bar, seating and seasonal tent. Project to include stormwater controls and landscaping. Commercial Expansion in the RR zone requires Planning Board review and approval. 2. A public hearing was advertised and held on 6/15/10 tabled to 7/20/2010; and 3. This application is supported with all documentation, public comment and application material in the file of record; 4. MOTION TO APPROVE SITE PLAN NO. 34-2010 CAPITAL REGION PROPERTIES, LLC, Introduced by Gretchen Steffan who moved for its adoption, seconded by Stephen Traver: Doing business as Dunham’s Bay Resort. According to the resolution prepared by Staff. Paragraph Four A complies. Paragraph Four B, this was a Negative Declaration on an Unlisted Action. The applicant has requested waivers. The Planning Board has not approved all waivers, but will give them waivers for stormwater management, lighting plans, and traffic. a. Pursuant to relevant sections of the Town of Queensbury Zoning Code [Chapter 179-9-080]], the Planning Board has determined that this proposal complies with the requirements as stated in the Zoning Code; and b. The requirements of the State Environmental Quality Review Act have been considered and the Planning Board has adopted a SEQRA Negative Declaration; and if the application is a modification, the requirements of the State Environmental Quality Review Act have been considered, and the proposed modification[s] do not result in any new or significantly different environmental impacts, and, therefore, no further SEQRA review is necessary; and c. Final approved plans, in compliance with the Site Plan, must be submitted to the Community Development Department before any further review by the Zoning Administrator or Building and Codes personnel. The applicant must meet with Staff after approval and prior to issuance of Building Permit and/or the beginning of any site work. Subsequent issuance of further permits, including building permits is dependent on compliance with this and all other conditions of this resolution; and d. As-built plans to certify that the site plan is developed according to the approved plans to be provided prior to issuance of the certificate of occupancy; and e. If applicable, Item d to be combined with a letter of credit; and f. Waiver requests granted: stormwater mgmt., lighting plans & traffic; and g. The limits of clearing will constitute a no-cut buffer zone, orange construction fencing shall be installed around these areas and field verified by Community Development staff h. Engineering sign-off required prior to signature of Zoning Administrator. “Home of Natural Beauty… A Good Place to Live” i. If curb cuts are being added or changed a driveway permit is required. A building permit will not be issued until the approved driveway permit has been provided to the Planning Office. j. The applicant must submit a copy of the following to the Town: 1. The project NOI (Notice of Intent) for coverage under the current NYSDEC SPDES General Permit or for coverage under an individual SPDES permit prior to the start of any site work. 2. The project NOT (Notice of Termination) upon completion of the project; and k. The applicant must maintain on their project site, for review by staff: 1. The approved final that have been stamped by the Town Zoning Administrator. These plans must include the project SWPPP (Storm Water Pollution Prevention Plan) when such a plan was prepared and approved; and 2. The project NOI and proof of coverage under the current NYSDEC SPDES General Permit, or an individual SPDES permit issued for the project. l. This is approved with the following conditions: 1.That the applicant will update their SPDES permit. 2.That the applicant will satisfy engineering comments and obtain a signoff. 3.That the applicant will provide a new wastewater plan incorporating the new water saving fixture upgrades. 4.That the applicant will provide a compliant parking plan, specifically the number of spaces and locations for parking. 5.That the applicant will provide final plans incorporating all revisions to the Site Plan, including proper seating indicated, proper tent size, removal of the covered bar, quantity of the proposed plantings, patio section details that are correctly referenced. This also includes fencing details and the planting scheme. th Duly adopted this 20 day of July, 2010, by the following vote: AYES: Mr. Traver, Mr. Sipp, Mr. Krebs, Mr. Schonewolf, Mrs. Steffan, Mr. Jackoski, Mr. Hunsinger NOES: NONE CC: Jarrett Engineers; Little & O’Connor “Home of Natural Beauty… A Good Place to Live”