RESOLUTION AUTHORIZING ENGAGEMENT OF
C.T. MALE ASSOCIATES TO PROVIDE
PROFESSIONAL ENGINEERING SERVICES RELATED TO
JENKINSVILLE WELL SUPPLY INVESTIGATION
RESOLUTION NO.: ,2022
INTRODUCED BY:
WHO MOVED ITS ADOPTION
SECONDED BY:
WHEREAS, the Queensbury Town Board wishes to engage the professional environmental
engineering services of C.T. Male Associates to complete a desktop study related to a well supply
investigation for the Jenkinsville area as delineated in C.T. Male Associates' proposal dated
February 4, 2022 presented at this meeting,
NOW, THEREFORE,BE IT
RESOLVED, that the Queensbury Town Board hereby authorizes and directs engagement
of C.T. Male Associates for the provision of professional engineering services to complete a
desktop study related to a well supply investigation for the Jenkinsville area for an amount not to
exceed$2,900 as delineated in C.T. Male Associates' proposal dated February 4, 2022 presented at
this meeting, and
BE IT FURTHER,
RESOLVED,that such services shall be paid for from Consultant Account No.: 001-1440-
4720-009, and
.r
J
BE IT FURTHER,
RESOLVED, that the Town Board further authorizes and directs the Town Supervisor to
execute the proposal and/or any necessary documentation and the Town Supervisor, Water
Superintendent, Transfer Station Supervisor and/or Town Budget Officer to take all actions
necessary to effectuate the terms of this Resolution.
Duly adopted this 14`"day of February,2022, by the following vote:
AYES
NOES
ABSENT:
C.T. MALE ASSOCIATES
Engineering,Surveying,Architecture, Landscape Architecture &Geology, D.P.C. FAW,�n®
50 Century Hill Drive, Latham,NY 12110 n���JLLc�j��JJ
518.786.7400 FAX 518.786.7299 www.ctmale.com
February 4,2022
Supervisor John Strough
Town of Queensbury
742 Bay Road
Queensbury,NY 12804
Re: Proposal for Engineering Services
Jenkinsville Well Supply Investigation
Dear Supervisor Strough:
The following represents our proposal to complete a desktop study for the potential development
of a new well supply source, pumping, treatment and supply of a new public water supply for
the affected residents in the Jenkinsville area. The work would be done in accordance with our
2022 General Services Agreement.
The desktop evaluation would generally include the following tasks with the assumption that a
new well source would need to yield approximately 50 GPM for its intended purpose of serving
only the immediate Jenkinsville area:
• Review and evaluate geologic mapping and studies within the study area
• Interview local water well drillers to determine potential aquifers in relative close
proximity to Jenkinsville not influenced by the areas containing the local landfills
• Locate an appropriate watershed for installation of two new wells with a safe yield of at
least 50 GPM
• Identification of the land area that would need to be purchased for establishing the well
field with the necessary setbacks
• Develop budget level cost estimates for the following items:
➢ Completion of an initial investigation to define the subsurface conditions,installation
of monitoring wells,and for well design
➢ Drilling and installing a test well,constructed to production well standards
➢ Performing a pumping test of new well including a full Part 5 analysis plus emerging
contaminants
➢ Preparing a Hydrogeologic Report
➢ Creation of a new water district
➢ Purchase of land,securing easements as needed
➢ Engineer's design and report for approval of the system
Civil Engineering • Environmental Services • Survey Services . Land Services •Architecture .
Energy&Building Systems Services • Electrical Engineering
L
C.T. MALE ASSOCIATES
February 4,2022
Supervisor John Strough
Page-2
➢ Mechanical backup well,backup power and hydro pneumatic tank
➢ Well house,controls and treatment
➢ New water lines
➢ Residential connections as required
➢ Long term O&M and new WTP Operator
A technical memorandum will be prepared and submitted summarizing the findings and costs
described above.
We would propose to complete the study for a not-to-exceed fee of$2900. We would be prepared
to begin work immediately upon the Town's acceptance of this proposal and would be able to
complete the project within 45 days.
If you should have any questions related to our proposal,please feel free to contact Kirk Moline
or me at(518) 786-7400. We would ask that you sign the proposal below as an acknowledgment
of your acceptance. We look forward to continuing to work with the Town and your staff.
Regards,
C.T.MALE ASSOCIATES
James R. Edwards,P.E.
VP-Risk Management
C: Chris Harrington,Water&Wastewater Supt,Town of Queensbury