Stormwater Management Report - November 12, 2018STORMWATER MANAGEMENT REPORT and STORMWATER POLLUTION PREVENTION PLAN NARRATIVE NYSDEC GP-0-15-002 Prepared for: Tra Tom Developemnt 4-Lot Residential Subdivision Barringer Heights Lot 1 Subdivision Tax Map #'s 308.7-1-48 Town of Queensbury Warren County, New York Prepared by: Hutchins Engineering 169 Haviland Road Queensbury, NY 12804 November 12, 2018 CERTIFICATION STATEMENT To be signed by contractors performing the site construction. I hereby certify under penalty of law that I understand and agree to comply with the terms and conditions of the SWPPP and agree to implement any corrective actions identified by the qualified inspector during a site inspection. I also understand that the owner or operator must comply with the terms and conditions of the most current version of the New York State Pollutant Discharge Elimination System (°SPDES°) general permit for stormwater discharges from construction activities and that it is unlawful for any person to cause or contribute to a violation of water quality standards. Furthermore, I ama aware that there are significant penalties for submitting false information, that I do not believe to be true, including the possibility of fine and imprisonment for knowing violations. Name: Company: Title: Signature: Date: Each Sub -Contractor or additional Contractors completing site work must also sign below: Name: Company: Title: Area of Work & SWPPP Responsibilities: Signature: Name: Company: Title: Area of Work & SWPPP Responsibilities: Date: Signature: Date: TABLE OF CONTENTS 1.0 PROJECT DESCRIPTION ...... ........................................ 1 2.0 EXISTING SITE CONDITIONS ........................................................................ 1 3.0 PROPOSED DEVELOPMENT ......................................................................... 1 4.0 PROPOSED STORMWATER MANAGEMENT ................................................... 2 5.0 NYSDEC REQUIREMENTS ........................................................................... 2 6.0 TOWN OF QUEENSBURY REQUIREMENTS .......................................................... 2 7.0 ENDANGERED SPECIES .................................................................................... 2 8.0 ARCHAEOLOGICAL RESOURCES & HISTORIC PLACES ......................................... 2 9.0 CONSTRUCTION PHASE EROSION PRACTICES ................................................... 2 10.0 TEMPORARY EROSION & SEDIMENT CONTROL MEASURES ................................. 3 11.0 CONTROL OF LITTER, CONSTRUCTION DEBRIS & CONSTRUCTION CHEMICALS .... 3 12.0 SEQUENCE OF CONSTRUCTION ................................................................ ....... 4 13.0 MAINTENANCE OF TEMPORARY EROSION & SEDIMENT CONTROL DEVICES ......... 4 14.0 OPERATION & MAINTENANCE PLAN ................................................................... 4 15.0 PERMANENT EROSION CONTROL ...................................................................... 5 16.0 INSPECTION REQUIRMENTS ...................................................................... 5 i 1.0 PROJECT DESCRIPTION The project consists of subdividing an existing 29.03.-acre parcel into 3 new building lots and a conservation lot. Project disturbance for total project build -out totals 1.55-acres. The project site is located in the northeast corner of the Barringer Heights subdivision on the east side of Richmond Hill Drive, in the Town of Queensbury, Warren County, New York. 2.0 EXISTING SITE CONDITIONS Presently, the project site is a vacant lot that is separated by the existing subdivision road. The portion of the parcel top the west will remain undeveloped as per the original subdivision approval. The existing site drainage pattern is generally easterly towards the National Grid power lines. Site soils over the majority of the site are mapped as Elnora loamy fine sand, HSG-A. A copy of the USDA soils map is included in the appendix of this report. Site slopes over the majority of the site range from 1-3%. Existing Conditions Summary Total Project Site Area: 29.03 Acres Buildings Coverage: 0 SF Driveways: 0 SF Total Impervious: 0 SF Design Storm Events 25-year 24-hr Type -II distribution 4AN Existing Conditions Calculated Stormwater Runoff from the Site — 25-year design storm (4.4") 0.0 CFS 0.0 acre-feet 3.0 PROPOSED DEVELOPMENT Proposed Conditions Summary Total Project Site Area: 29.03 Acres Buildings Coverage: 5,130 SF Driveways: 2,617 SF Total Impervious: 7,747 SF Project Disturbance: 1.55 Acres 4.0 PROSPOSED STORMWATER MANAGEMENT The proposed stormwater management will store and treat all stormwater runoff from impermeable surfaces on each individual lot. The runoff from the proposed residential homes will be directed to an eave trench at the perimeter of the structure and will be infiltrated into the well -drained soils. The runoff from the new driveways will be pitched to a stone infiltration trench along side the driveways and infiltrate into the well -drained soils. All runoff from impervious surfaces will be captured and treated on each individual lot. 5.0 NYSDEC REQUIREMENTS The proposed development is a residential subdivision that will disturb more than 1 acre but less than 5 acres and will be for less than 5 new lots. Based on the proposed development NYS DEC only requires a NOI to be filed with an Erosion & Sediment Control Plan. 6.0 TOWN OF QUEENSBURY REQUIREMENTS The Town of Queensbury requires that for residential projects, the peak developed discharge rate and volume from the 25-year, 24-hour storm not exceed the predevelopment rate and volume. Existing 25-year peak storm volume: 0.0 AF Developed 25-year peak storm volume: 0.0 AF Existing 25-year peak storm discharge: 0.0 CFS Developed 25-year peak storm discharge: 0.0 CFS The 25-year storm calculations show that the Town's requirements are met. 7.0 ENDANGERED SPECIES In accordance with Part I.F.4 of GP-015-0-002, discharges from construction activities that adversely affect a listed or proposed to be listed endangered or threatened species are ineligible for coverage under the general permit. An inquiry was made to NYSDEC during the initial subdivision development which included this portion of the parcel. No endangered or threatened species were located within the proposed area to be developed. We have continued the no cut buffer along the east side along the power lines as requested by the planning board in the previous approval. 8.0 ARCHAEOLOGICAL RESOURCES & HISTORIC PLACES In accordance with Part I.F.8 of GP-015-0-002, discharges from construction activities that have the potential to affect historic property are ineligible for coverage under the general permit. An inquiry was made to NYSOPRHP during the initial subdivision; which included this area to be developed, and no historic property was identified within the original subdivision boundaries. 9.0 CONSTRUCTION PHASE EROSION PRACTICES Practices to be implemented during construction for erosion and sediment control include silt fencing and temporary sediment basins in various portions of the total disturbed area. Silt fencing will be placed across slopes (on the contour) in all areas downgrade of disturbed areas. Temporary sediment traps will be utilized in areas where construction phase runoff concentrates. 10.0 TEMPORARY EROSION & SEDIMENT CONTROL MEASURES Erosion and sediment control measures will be incorporated into the construction of the project. These practices will comply with the New York State Department of Environmental Conservation publication entitled "New York Guidelines for Urban and Sediment Control" (the blue book). Separate erosion and sediment controls will be installed for each phase of construction. The following temporary erosion and sediment control devices are to be utilized: Sediment Control Fence Silt Fence shall be used to control erosion from sheet flow on slopes not to exceed 1 on 3. Concentrated flows shall not be directed toward the silt fence. The silt fence must be installed parallel to the contour lines to eliminate drainage along the fence. 2. Temporary Seedina Land that is stripped of vegetation will be seeded and planted as soon as possible. Any area that will remain cleared but not under construction for five days or longer will be seeded with a ryegrass mixture and mulched to stabilize soil until construction resumes. 3. Temporary Diversion Swales Temporary diversion swales shall be constructed either to divert clean stormwater runoff from newly graded areas or to direct sediment laden runoff to a sediment trapping device. 4. Dust Control Measures for dust control during construction shall be implemented as needed. Daily water sprays will be used during dry conditions. In addition to water sprays, temporary mulching, temporary seeding and covering stockpiles with tarps shall be implemented when necessary. 5. Erosion Control Blanket Fabricated straw or biodegradable mesh blankets shall be utilized to protect and temporarily stabilize slopes of 1:3 or greater and shall be applied to graded, topsoiled, and seeded slopes. Blankets will be attached with staples or stakes in accordance with manufacturer's recommendations. Blankets on cut slopes and vegetated ditchlines will be maintained in place permanently and allowed to biodegrade. 11.0 CONTROL OF LITTER, CONSTRUCTION DEBRIS & CONSTRUCTION CHEMICALS During the course of construction, the site shall be kept clear of debris and litter which could be transported by water or wind. This material shall be picked up daily and shall be stored in waste debris containers where it will be securely held. All petroleum products or other waste contaminants which are water soluble, or could be dispersed and transported by stormwater, shall be stored in covered containers and shall be regularly removed from the site and properly and legally disposed of. All petroleum or other hazardous materials shall be stored and handled in conformance with NYSDEC spill prevention and containment requirements. 12.0 SEQUENCE OF CONSTRUCTION The project is to be undertaken in one phase, being the construction of the individual houses and the respective lot development. Prior to the start of construction, the contractor shall install the sediment control fence along the low side of each area to be disturbed in order to contain runoff from the construction site. Concurrently, the stabilized construction entrance is to be installed in the location of the proposed driveway. Topsoil is to be stripped and stockpiled for reuse over the regraded areas. Temporary vegetation is to be installed over the regraded areas which will not become driveway areas. Following the respective house construction, the final surrounding grades are to be established, driveway installed, soil restoration is to be performed, place topsoil eave trenches, stone infiltration trenches and final vegetation installed. Following the completion of all planting and the establishment of all grass areas, any collected sediment and sediment control fencing shall be removed. Any debris from the perimeter of the site shall be removed and dispose of all waste material shall be disposed of in a legal manner. 13.0 MAINTENANCE OF TEMPORARY EROSION & SEDIMENT CONTROL DEVICES The sediment basins shall be inspected at least weekly and after every rain event by the contractor. When 50% of the volume of the trap is full, the contractor shall remove collected sediment and dispose of properly. The contractor shall inspect the sediment control fence weekly and after every rain event and remove trapped sediment and maintain the devices such that they are in good working order. 14.0 OPERATION & MAINTENANCE PLAN Each respective lot owner is to provide the maintenance needed in order to ensure continuous and effective operation of the stormwater control practices on the respective lots. Maintenance includes vegetation trimming and sediment removal in the stone infiltration trench and eave trenches. Mowing and trimming should be performed as needed throughout the spring, summer and fall, typically weekly or semi -weekly. Sediment removal and inspection of the stone infiltration trench should be performed annually or as needed due to surrounding and contributing site conditions. If long-term infiltration capacity becomes reduced, the stone trench should be excavated, and new stone & filter fabric installed 15.0 PERMANENT EROSION CONTROL All pervious areas shall be graded, topsoil installed and seeded or planted as soon as practical, but in no case shall finish graded soils be exposed for more than five days. Seed beds shall be mulched with straw and plant beds shall be mulched with pine bark mulch. Seeded areas on slopes over 1:3 shall be stabilized with erosion control blankets as specified on the plans. 16.0 INSPECTION REQUIREMENTS In accordance with Part IV of GP-0-15-002, the owner or operator of each construction activity shall have a trained contractor inspect the erosion and sediment control practices within the active work area on a daily basis to ensure that proper maintenance and functionality is realized for the practices. If soil disturbances upon the site have been temporarily suspended and proper stabilization methods have been implemented, the trained contractor may suspend inspections until site work is restarted. ATTACHMENTS • Soil Map • Subcatchment Map — Existing Model HydroCAD — Existing • Subcatchment Map — Proposed Model HydroCAD — Proposed • Draft NOI with NYS DEC Permit from original subdivision approval. HYDROCAD Existing & Proposed Conditions: Type -II 24 hr Rainfall = 4.4" (25-year) Existing Conditions EX EXISTING UNDEVELOPED LOT 1 EAST OF ROAD Subca Aon Link 291261 - TRA TOM - BARRINGER HTS LOT 1 SUBDIVISION - EXISTING CONDITIONS Prepared by {enter your company name here} Printed 1/17/2019 Area Listing (all nodes) Area CN Description (sq-ft) (subcatchment-numbers) 117,699 30 Woods, Good, HSG A (EX) 117,699 TOTAL AREA 291261 - TRA TOM - BARRINGER HTS LOT 1 SUBDIVISION - EXISTING CONDITIONS Prepared by {enter your company name here) Printed 1/17/2019 Soil Listing (all nodes) Area Soil Subcatchment (sq-ft) Group Numbers 117,699 HSG A EX 0 HSG B 0 HSG C 0 HSG D 0 Other 117,699 TOTAL AREA 291261 - TRA TOM - BARRINGER HTS L Type ll 24-hr 25 YR DESIGN STORM Rainfall=4.40" Prepared by {enter your company name here} Printed 1/17/2019 Time span=0.00-24.00 hrs, dt=0.05 hrs, 481 points Runoff by SCS TR-20 method, UH=SCS Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method Subcatchment EX: EXISTING Runoff Area=2.702 ac 0.00% Impervious Runoff Depth=0.00" Flow Length=200' Tc=38.1 min CN=30 Runoff=0.0 cfs 0 cf Total Runoff Area=117,699 sf Runoff Volume = 0 of Average Runoff Depth = 0.00" 100.00% Pervious=117,699 sf 0.00% Impervious = 0 sf 291261 - TRA TOM - BARRINGER HTS L Type ll 24-hr 25 YR DESIGN STORM Rainfall=4.40" Prepared by {enter your company name here} Printed 1/17/2019 Summary for Subcatchment EX: EXISTING UNDEVELOPED LOT 1 EAST OF ROAD Runoff = 0.0 cfs @ 0.00 hrs, Volume= 0 cf, Depth= 0.00" Runoff by SCS TR-20 method, UH=SCS, Time Span= 0.00-24.00 hrs, dt= 0.05 hrs Type II 24-hr 25 YR DESIGN STORM Rainfall=4.40" Area (ac) CN Description 2.702 30 Woods, Good, HSG A 2.702 100.00% Pervious Area Tc Length Slope Velocity Capacity Description 36.7 150 0.0200 0.07 Sheet Flow, SHEET FLOW Woods: Light underbrush n= 0.400 P2= 2.10" 1.4 50 0.0150 0.61 Shallow Concentrated Flow, SHALLOW CONC. FLOW Woodland Kv= 5.0 fos 38.1 200 Total Proposed Conditions HSE 2 [)VV 2$ HOUS L0T2 DRIVEI�/AY LOT 2 DW LOT 2 LA N & �`/7 HSE 3 woo T DRIVEWAY LOT 1 AT z4T OUSE LOT 3 INFI RENCH LOT DW 3 2FTX2FTX5 T ET 0T2 STONETRENC HOUSE RIVEZY LOT 3 T3 HOUSE LOT 1 ET T 3 (i� EAVETRENCH LOT 1 LAWN & WOODS IT LOT 3 TOTAL TO OFFSITE 3S LOT 3 LAWN & WOODS Su4 Aon L8 291261 - TRA TOM - BARRINGER HTS LOT 1 SUBDIVISION - PROPOSED CONDITIONS Prepared by (enter your company name here) Printed 1/17/2019 Area Listing (all nodes) Area (acres) CN Description (subcatchment-numbers) 1.105 30 Woods, Good, HSG A (1S. 2S, 3S) 1.408 39 >75% Grass cover, Good, HSG A (1 S, 2S, 3S) 0.024 98 DRIVEWAY (DW) 0.048 98 Paved parking, HSG A (DW 2, DW 3) 0.039 98 ROOF RUNOFF (HOUSE) 0.039 98 Roofs, HSG A (HSE 3) 0.039 98 Unconnected roofs, HSG A (HSE 2) 2.702 TOTAL AREA 291261 - TRA TOM - BARRINGER HTS LOT 1 SUBDIVISION - PROPOSED CONDITIONS Prepared by {enter your company name here) Printed 1/17/2019 Soil Listing (all nodes) Area Soil Subcatchment acres) Group Numbers 2.639 HSG A 1S, 2S, 3S, DW 2, DW 3, HSE 2, HSE 3 0.000 HSG B 0.000 HSG C 0.000 HSG D 0.063 Other DW, HOUSE 2.702 TOTAL AREA 291261 - TRA TOM - BARRINGER HTS LOT 1 Type 1124-hr 25 YEAR STORM Rainfall=4.40- Prepared by {enter your company name here} Printed 1/17/2019 HydroCADO 9.10 s/n 03732 C 2010 HydroCAD Software Solutions LLC Paae 4 Time span=0.00-72.00 hrs, dt=0.05 hrs, 1441 points Runoff by SCS TR-20 method, UH=SCS Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method Subcatchment 1S: LOT 1 LAWN & WOODS Runoff Area=40,570 sf 0.00% Impervious Runoff Depth=0.02" Flow Length=143' Slope=0.0315'P Tc=14.5 min CN=35 Runoff=0.0 cfs 0.0 of Subcatchment 2S: LOT 2 LAWN & WOODS Runoff Area=41,100 sf 0.00% Impervious Runoff Depth=0.02" Flow Length=80' Slope=0.0625 '/' Tc=8.7 min CN=35 Runoff=0.0 cfs 0.0 of Subcatchment 3S: LOT 3 LAWN & WOODS Runoff Area=27,786 sf 0.00% Impervious Runoff Depth=0.02" Flow Length=124' Slope=0.0440'P Tc=12.4 min CN=35 Runoff=0.0 cfs 0.0 of Subcatchment DW: DRIVEWAY LOT 1 Runoff Area=1,040 sf 100.00% Impervious Runoff Depth=4.16" Flow Length=23' Slope=0.0380'P Tc=6.0 min CN=98 Runoff=0.1 cfs 0.0 of Subcatchment DW 2: DRIVEWAY LOT 2 Runoff Area=1,040 sf 100.00% Impervious Runoff Depth=4.16" Flow Length=23' Slope=0.0380'P Tc=6.0 min CN=98 Runoff=0.1 cfs 0.0 of Subcatchment DW 3: DRIVEWAY LOT 3 Runoff Area=1,040 sf 100.00% Impervious Runoff Depth=4.16" Flow Length=23' Slope=0.0380'P Tc=6.0 min CN=98 Runoff=0.1 cfs 0.0 of Subcatchment HOUSE: HOUSE LOT 1 Runoff Area=1,711 sf 100.00% Impervious Runoff Depth=4.16" Flow Length=21' Slope=0.5000'P Tc=6.0 min CN=98 Runoff=0.2 cfs 0.0 of Subcatchment HSE 2: HOUSE LOT 2 Runoff Area=1,711 sf 100.00% Impervious Runoff Depth=4.16" Flow Length=21' Slope=0.5000'/' Tc=6.0 min CN=98 Runoff=0.2 cfs 0.0 of Subcatchment HSE 3: HOUSE LOT 3 Runoff Area=1,711 sf 100.00% Impervious Runoff Depth=4.16" Flow Length=21' Slope=0.5000'r Tc=6.0 min CN=98 Runoff=0.2 cfs 0.0 of Pond ET: EAVE TRENCH Peak EIev=0.02' Storage=0.0 of Inflow=0.2 cfs 0.0 of Discarded=0.2 cfs 0.0 of Primary--0.0 cfs 0.0 of Outflow=0.2 cfs 0.0 of Pond ET 3: ET 2 Peak EIev=0.02' Storage=0.0 of Inflow=0.2 cfs 0.0 of Discarded=0.2 cfs 0.0 of Primary--0.0 cfs 0.0 of Outflow=0.2 cfs 0.0 of Pond ET2: ET LOT 2 Peak EIev=0.02' Storage=0.0 of Inflow=0.2 cfs 0.0 of Discarded=0.2 cfs 0.0 of Primary--0.0 cfs 0.0 of Oufflow=0.2 cfs 0.0 of Pond IT: 2 FT X 2 FT X 52 FT STONE TRENCH Peak EIev=0.10' Storage=0.0 of Inflow=0.1 cfs 0.0 of Discarded=0.1 cfs 0.0 of Primary--0.0 cfs 0.0 of Outflow=0.1 cfs 0.0 of Pond IT 2: INFIL. TRENCH LOT 2 Peak EIev=0.01' Storage=0.0 of Inflow=0.1 cfs 0.0 of Discarded=0.1 cfs 0.0 of Primary--0.0 cfs 0.0 of Outflow=0.1 cfs 0.0 of Pond IT 3: IT LOT 3 Peak EIev=0.01' Storage=0.0 of Inflow=0.1 cfs 0.0 of Discarded=0.1 cfs 0.0 of Primary--0.0 cfs 0.0 of Outflow=0.1 cfs 0.0 of Link 1 L: TOTAL TO OFFSITE Inflow=0.0 cfs 0.0 of Primary--0.0 cfs 0.0 of 291261 - TRA TOM - BARRINGER HTS LOT 1 Prepared by {enter your company name here} HvdroCAD® 9.10 s/n 03732 © 2010 HvdmCAD Software Type 11 24-hr 25 YEAR STORM Rainfall=4.40" Printed 1/17/2019 Total Runoff Area = 2.702 ac Runoff Volume = 0.1 of Average Runoff Depth = 0.31" 92.99% Pervious = 2.513 ac 7.01 % Impervious = 0.189 ac 291261 - TRA TOM - BARRINGER HTS LOT 1 Prepared by {enter your company name here} Type 11 24-hr 25 YEAR STORM Rainfall=4.40" Summary for Subcatchment 1S: LOT 1 LAWN S WOODS Runoff = 0.0 cfs @ 24.00 hrs, Volume= 0.0 af, Depth= 0.02" Runoff by SCS TR-20 method, UH=SCS, Time Span= 0.00-72.00 hrs, dt= 0.05 hrs Type II 24-hr 25 YEAR STORM Rainfall=4.40" Printed 1/17/2019 Area (sf) CN Description 17,898 30 Woods, Good, HSG A _ 22,672 39 >75% Grass cover, Good, HSG A 40,570 35 Weighted Average 40,570 100.00% Pervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 13.7 100 0.0315 0.1 Sheet Flow, SHEET FLOW Grass: Dense n= 0.240 P2= 2.40" 0.8 43 0.0315 0.9 Shallow Concentrated Flow, SHALLOW CONC FLOW Woodland Kv= 5.0 fos 14.5 143 Total Summary for Subcatchment 2S: LOT 2 LAWN & WOODS Runoff = 0.0 cfs @ 24.00 hrs, Volume= 0.0 af, Depth= 0.02" Runoff by SCS TR-20 method, UH=SCS, Time Span= 0.00-72.00 hrs, dt= 0.05 hrs Type II 24-hr 25 YEAR STORM Rainfall=4.40" Area (sf) CN Description 19,267 30 Woods, Good, HSG A _ 21,833 39 >75% Grass cover, Good, HSG A 41,100 35 Weighted Average 41,100 100.00% Pervious Area Tc Length Slope Velocity Capacity Description 8.7 80 0.0625 0.2 Sheet Flow, SHEET FLOW Grass: Dense n= 0.240 P2= 2.40" Summary for Subcatchment 3S: LOT 3 LAWN & WOODS Runoff = 0.0 cfs @ 24.00 hrs, Volume= 0.0 af, Depth= 0.02" Runoff by SCS TR-20 method, UH=SCS, Time Span= 0.00-72.00 hrs, dt= 0.05 hrs Type 11 24-hr 25 YEAR STORM Rainfall=4.40" 291261 - TRA TOM - BARRINGER HTS LOT 1 Type 1124-hr 25 YEAR STORM Rainfall=4.40" Prepared by {enter your company name here} Printed 1/17/2019 HydroCAD® 9.10 s/n 03732 02010 HvdroCAD Software Solutions LLC Page 7 Area (sf) CN Description 10,977 30 Woods, Good, HSG A 16,809 39 >75% Grass cover, Good, HSG A 27,786 35 Weighted Average 27,786 100.00% Pervious Area Tc Length Slope Velocity Capacity Description 12.0 100 0.0440 0.1 Sheet Flow, SHEET FLOW Grass: Dense n= 0.240 P2= 2.40" 0.4 24 0.0440 1.0 Shallow Concentrated Flow, SHALLOW CONC FLOW Woodland Kv= 5.0 fps 12.4 124 Total Summary for Subcatchment DW: DRIVEWAY LOT 1 Runoff = 0.1 cfs @ 11.96 hrs, Volume= 0.0 af, Depth= 4.16" Runoff by SCS TR-20 method, UH=SCS, Time Span= 0.00-72.00 hrs, dt= 0.05 hrs Type II 24-hr 25 YEAR STORM Rainfall=4.40" 1,040 100.00% Impervious Area Tc Length Slope Velocity Capacity Description 0.3 23 0.0380 1.1 Sheet Flow, SHEET FLOW Smooth surfaces n= 0.011 P2= 2.40" 0.3 Runoff = 23 Total, Increased to minimum Tc = 6.0 min Summary for Subcatchment DW 2: DRIVEWAY LOT 2 0.1 cfs @ 11.96 hrs, Volume= 0.0 af, Depth= 4.16" Runoff by SCS TR-20 method, UH=SCS, Time Span= 0.00-72.00 hrs, dt= 0.05 hrs Type II 24-hr 25 YEAR STORM Rainfall=4.40" Area (sf) CN Description 1,040 98 Paved parking, HSG A 1,040 100.00% Impervious Area Tc Length Slope Velocity Capacity Description 0.3 23 0.0380 1.1 Sheet Flow, SHEET FLOW Smooth surfaces n= 0.011 P2= 2.40" 0.3 23 Total, Increased to minimum Tc = 6.0 min 291261 - TRA TOM - BARRINGER HTS LOT 1 Prepared by {enter your company name here} Type 1124-hr 25 YEAR STORM Rainfall=4.40" Summary for Subcatchment DW 3: DRIVEWAY LOT 3 Runoff = 0.1 cfs @ 11.96 hrs, Volume= 0.0 af, Depth= 4.16" Runoff by SCS TR-20 method, UH=SCS, Time Span= 0.00-72.00 hrs, dt= 0.05 hrs Type II 24-hr 25 YEAR STORM Rainfall=4.40" Area (sf) CN Description 1,040 98 Paved parking, HSG A 1,040 100.00% Impervious Area Tc Length Slope Velocity Capacity Description Printed 1/17/2019 0.3 23 0.0380 1.1 Sheet Flow, SHEET FLOW Smooth surfaces n= 0.011 P2= 2.40" 0.3 23 Total, Increased to minimum Tc = 6.0 min Summary for Subcatchment HOUSE: HOUSE LOT 1 Runoff = 0.2 cfs @ 11.96 hrs, Volume= 0.0 af, Depth= 4.16" Runoff by SCS TR-20 method, UH=SCS, Time Span= 0.00-72.00 hrs, dt= 0.05 hrs Type II 24-hr 25 YEAR STORM Rainfall=4.40" Area (sf) CN Description 1.711 98 ROOF RUNOFF 1,711 100.00% Impervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft1ft) (ft/sec) (cfs) 0.1 21 0.5000 3.2 Sheet Flow, SHEET FLOW Smooth surfaces n= 0.011 P2= 2.40" 0.1 21 Total, Increased to minimum Tc = 6.0 min Summary for Subcatchment HSE 2: HOUSE LOT 2 Runoff = 0.2 cfs @ 11.96 hrs, Volume= 0.0 af, Depth= 4.16" Runoff by SCS TR-20 method, UH=SCS, Time Span= 0.00-72.00 hrs, dt= 0.05 hrs Type II 24-hr 25 YEAR STORM Rainfall=4.40" Area (sf) CN Description 1.711 98 Unconnected roofs. HSG A 1,711 100.00% Impervious Area 1,711 100.00% Unconnected 291261 - TRA TOM - BARRINGER HTS LOT 1 Prepared by {enter your company name here) Type 11 24-hr 25 YEAR STORM Rainfall=4.40" Tc Length Slope Velocity Capacity Description Printed 1/17/2019 0.1 21 0.5000 3.2 Sheet Flow, SHEET FLOW Smooth surfaces n= 0.011 P2= 2.40" 0.1 21 Total, Increased to minimum Tc = 6.0 min Summary for Subcatchment HSE 3: HOUSE LOT 3 Runoff = 0.2 cfs @ 11.96 hrs, Volume= 0.0 af, Depth= 4.16" Runoff by SCS TR-20 method, LIH=SCS, Time Span= 0.00-72.00 hrs, dt= 0.05 hrs Type II 24-hr 25 YEAR STORM Rainfall=4.40" Area (sf) CN Description 1,711 98 Roofs, HSG A 1,711 100.00% Impervious Area Tc Length Slope Velocity Capacity Description 0.1 21 0.5000 3.2 Sheet Flow, SHEET FLOW Smooth surfaces n= 0.011 P2= 2.40" 0.1 21 Total, Increased to minimum Tc = 6.0 min Summary for Pond ET: EAVE TRENCH Inflow Area = 0.039 ac,100.00% Impervious, Inflow Depth = 4.16" for 25 YEAR STORM event Inflow = 0.2 cfs @ 11.96 hrs, Volume= 0.0 of Outflow = 0.2 cfs @ 11.96 hrs, Volume= 0.0 af, Atten= 0%, Lag= 0.2 min Discarded = 0.2 cfs @ 11.96 hrs, Volume= 0.0 of Primary = 0.0 cfs @ 0.00 hrs, Volume= 0.0 of Routing by Stor-Ind method, Time Span= 0.00-72.00 hrs, dt= 0.05 hrs Peak Elev= 0.02' @ 11.96 hrs Surf.Area= 0.006 ac Storage= 0.0 of Plug -Flow detention time= 0.1 min calculated for 0.0 of (100% of inflow) Center -of -Mass det. time= 0.1 min ( 746.3 - 746.2 ) Volume Invert Avail.Storage Storage Description #1 0.00, 0.0 of 2.00'W x 130.001 x 2.00'H Prismatoid Z=1.0 0.0 of Overall x 40.0% Voids Device Routing Invert Outlet Devices #1 Discarded 0.00' 50.000 in/hr Exfiltration over Surface area #2 Primary 2.00' 130.0' long x 1.0' breadth Broad -Crested Rectangular Weir Head (feet) 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 2.00 2.50 3.00 Coef. (English) 2.69 2.72 2.75 2.85 2.98 3.08 3.20 3.28 3.31 3.30 3.31 3.32 291261 - TRA TOM - BARRINGER HTS LOT 1 Prepared by (enter your company name here) Type 1124-hr 25 YEAR STORM Rainfall=4.40" iscarded OutFlow Max=0.3 cfs @ 11.96 hrs HW=0.02' (Free Discharge) =Exfiltration (Exfiltration Controls 0.3 cfs) ririmary OutFlow Max=0.0 cfs @ 0.00 hrs HW=0.00' (Free Discharge) 2=Broad-Crested Rectangular Weir ( Controls 0.0 cfs) Summary for Pond ET 3: ET 2 Printed 1/17/2019 Inflow Area = 0.039 ac,100.00% Impervious, Inflow Depth = 4.16" for 25 YEAR STORM event Inflow = 0.2 cfs @ 11.96 hrs, Volume= 0.0 of Outflow = 0.2 cfs @ 11.96 hrs, Volume= 0.0 af, Atten= 0%, Lag= 0.2 min Discarded = 0.2 cfs @ 11.96 hrs, Volume= 0.0 of Primary = 0.0 cfs @ 0.00 hrs, Volume= 0.0 of Routing by Stor-Ind method, Time Span= 0.00-72.00 hrs, dt= 0.05 hrs Peak Elev= 0.02' @ 11.96 hrs Surf.Area= 0.006 ac Storage= 0.0 of Plug -Flow detention time= 0.1 min calculated for 0.0 of (100% of inflow) Center -of -Mass det. time= 0.1 min ( 746.3 - 746.2 ) Volume Invert Avail.Storage Storage Description #1 0.00, 0.0 of 2.00'W x 130.00'L x 2.00'H Prismatoid Z=1.0 I 0.0 of Overall x 40.0% Voids Device Routing Invert Outlet Devices #1 Discarded 0.00' 50.000 in/hr Exfiltration over Surface area #2 Primary 2.00' 130.0' long x 1.0' breadth Broad -Crested Rectangular Weir Head (feet) 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 2.00 2.50 3.00 Coef. (English) 2.69 2.72 2.75 2.85 2.98 3.08 3.20 3.28 3.31 3.30 3.31 3.32 iscarded OutFlow Max=0.3 cfs @ 11.96 hrs HW=0.02' (Free Discharge) =Exfiltration (Exfiltration Controls 0.3 cfs) Primary OutFlow Max=0.0 cfs @ 0.00 hrs HW=0.00' (Free Discharge) 2=Broad-Crested Rectangular Weir ( Controls 0.0 cfs) Summary for Pond ET2: ET LOT 2 Inflow Area = 0.039 ac,100.00% Impervious, Inflow Depth = 4.16" for 25 YEAR STORM event Inflow = 0.2 cfs @ 11.96 hrs, Volume= 0.0 of Outflow = 0.2 cfs @ 11.96 hrs, Volume= 0.0 af, Atten= 0%, Lag= 0.2 min Discarded = 0.2 cfs @ 11.96 hrs, Volume= 0.0 of Primary = 0.0 cfs @ 0.00 hrs, Volume= 0.0 of Routing by Stor-Ind method, Time Span= 0.00-72.00 hrs, dt= 0.05 hrs Peak Elev= 0.02' @ 11.96 hrs Surf.Area= 0.006 ac Storage= 0.0 of Plug -Flow detention time= 0.1 min calculated for 0.0 of (100% of inflow) 291261 - TRA TOM - BARRINGER HTS LOT 1 Prepared by (enter your company name here) Center -of -Mass det. time= 0.1 min ( 746.3 - 746.2 ) Type 1124-hr 25 YEAR STORM Rainfall=4.40" Volume Invert Avail.Storage Storage Description #1 0.00, 0.0 of 2.00'W x 130.001 x 2.00'H Prismatoid Z=1.0 0.0 of Overall x 40.0% Voids Printed 1/17/2019 Device Routing Invert Outlet Devices #1 Discarded 0.00' 50.000 inlhr Exfiltration over Surface area #2 Primary 2.00' 130.0' long x 1.0' breadth Broad -Crested Rectangular Weir Head (feet) 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 2.00 2.50 3.00 Coef. (English) 2.69 2.72 2.75 2.85 2.98 3.08 3.20 3.28 3.31 3.30 3.31 3.32 Discarded OutFlow Max=0.3 cfs @ 11.96 hrs HW=0.02' (Free Discharge) 1=Exfiltration (Exfiltration Controls 0.3 cfs) 2 ,PLrimary OutFlow Max=0.0 cfs @ 0.00 hrs HW=0.00' (Free Discharge) =Broad -Crested Rectangular Weir ( Controls 0.0 cfs) Summary for Pond IT: 2 FT X 2 FT X 52 FT STONE TRENCH Inflow Area = 0.024 ac,100.00% Impervious, Inflow Depth = 4.16" for 25 YEAR STORM event Inflow = 0.1 cfs @ 11.96 hrs, Volume= 0.0 of Outflow = 0.1 cfs @ 11.99 hrs, Volume= 0.0 af, Atten= 9%, Lag= 1.7 min Discarded = 0.1 cfs @ 11.99 hrs, Volume= 0.0 of Primary = 0.0 cfs @ 0.00 hrs, Volume= 0.0 of Routing by Stor-Ind method, Time Span= 0.00-72.00 hrs, dt= 0.05 hrs Peak Elev= 0.10' @ 11.99 hrs Surf.Area= 0.003 ac Storage= 0.0 of Plug -Flow detention time= (not calculated: outflow precedes inflow) Center -of -Mass det. time= 0.1 min ( 746.3 - 746.2 ) Volume Invert Avail.Storage Storage Description #1 0.00, 0.0 of 2.00'W x 52.00'L x 2.00'H Prismatoid Z=1.0 0.0 of Overall x 40.0% Voids Device Routing Invert Outlet Devices #1 Discarded 0.00' 50.000 in/hr Wiiltration over Surface area #2 Primary 2.00' 52.0' long (Profile 14) Broad -Crested Rectangular Weir Head (feet) 1.97 2.46 2.95 3.94 4.92 Coef. (English) 3.37 3.37 3.37 3.37 3.37 Nscarded OutFlow Max=0.1 cfs @ 11.99 hrs HW=0.09' (Free Discharge) =Exfiltration (Exfiltration Controls 0.1 cfs) tPrimary OutFlow Max=0.0 cfs @ 0.00 hrs HW=0.00' (Free Discharge) 2=Broad-Crested Rectangular Weir ( Controls 0.0 cfs) 291261 - TRA TOM - BARRINGER HTS LOT 1 Type 1124-hr 25 YEAR STORM Rainfall=4.40" Prepared by {enter your company name here) Printed 1/17/2019 HvdroCAD® 9.10 s/n 03732 ©2010 HvdroCAD Software Solutions LLC Pace 12 Summary for Pond IT 2: INFIL. TRENCH LOT 2 Inflow Area = 0.024 ac,100.00% Impervious, Inflow Depth = 4.16" for 25 YEAR STORM event Inflow = 0.1 cfs @ 11.96 hrs, Volume= 0.0 of Outflow = 0.1 cfs @ 11.96 hrs, Volume= 0.0 af, Atten= 0%, Lag= 0.2 min Discarded = 0.1 cfs @ 11.96 hrs, Volume= 0.0 of Primary = 0.0 cfs @ 0.00 hrs, Volume= 0.0 of Routing by Stor-Ind method, Time Span= 0.00-72.00 hrs, dt= 0.05 hrs Peak Elev= 0.01' @ 11.96 hrs Surf.Area= 0.006 ac Storage= 0.0 of Plug -Flow detention time= 0.1 min calculated for 0.0 of (100% of inflow) Center -of -Mass det. time= 0.1 min ( 746.3 - 746.2 ) Volume Invert Avail.Storage Storage Description #1 0.00, 0.0 of 2.00'W x 135.001 x 2.00'H Prismatoid Z=1.0 0.0 of Overall x 40.0% Voids Device Routing Invert Outlet Devices #1 Discarded 0.00' 50.000 in/hr Exfiltration over Surface area #2 Primary 2.00' 135.0' long x 1.0' breadth Broad -Crested Rectangular Weir Head (feet) 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 2.00 2.50 3.00 Coef. (English) 2.69 2.72 2.75 2.85 2.98 3.08 3.20 3.28 3.31 3.30 3.31 3.32 iscarded OutFlow Max=0.3 cfs @ 11.96 hrs HW=0.01' (Free Discharge) E-I=Exfiltration (Exfiltration Controls 0.3 cfs) P ary OutFlow Max=0.0 cfs @ 0.00 hrs HW=0.00' (Free Discharge) ttBroad-Crested Rectangular Weir ( Controls 0.0 cfs) Summary for Pond IT 3: IT LOT 3 Inflow Area = 0.024 ac,100.00% Impervious, Inflow Depth = 4.16" for 25 YEAR STORM event Inflow = 0.1 cfs @ 11.96 hrs, Volume= 0.0 of Outflow = 0.1 cfs @ 11.96 hrs, Volume= 0.0 af, Atten= 0%, Lag= 0.2 min Discarded = 0.1 cfs @ 11.96 hrs, Volume= 0.0 of Primary = 0.0 cfs @ 0.00 hrs, Volume= 0.0 of Routing by Stor-Ind method, Time Span= 0.00-72.00 hrs, dt= 0.05 hrs Peak Elev= 0.01' @ 11.96 hrs Surf.Area= 0.006 ac Storage= 0.0 of Plug -Flow detention time= 0.1 min calculated for 0.0 of (100% of inflow) Center -of -Mass det. time= 0.1 min ( 746.3 - 746.2 ) Volume Invert Avail.Storage Storage Description #1 0.00, 0.0 of 2.00'W x 135.001 x 2.00'H Prismatoid Z=1.0 0.0 of Overall x 40.0% Voids 291261 - TRA TOM - BARRINGER HTS LOT 1 Type/1 24-hr 25 YEAR STORM Rainfall=4.40" Prepared by (enter your company name here) Printed 1/17/2019 Device Routing Invert Outlet Devices #1 Discarded 0.00' 50.000 inlhr Exfiltration over Surface area #2 Primary 2.00' 135.0' long x 1.0' breadth Broad -Crested Rectangular Weir Head (feet) 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 2.00 2.50 3.00 Coef. (English) 2.69 2.72 2.75 2.85 2.98 3.08 3.20 3.28 3.31 3.30 3.31 3.32 Qiscarded OutFlow Max=0.3 cfs @ 11.96 hrs HW=0.01' (Free Discharge) 1=Exfiltration (Exfiltration Controls 0.3 cfs) tmary OutFlow Max=0.0 cfs @ 0.00 hrs HW=0.00' (Free Discharge) 2=Broad-Crested Rectangular Weir ( Controls 0.0 cfs) Summary for Link 1 L: TOTAL TO OFFSITE Inflow Area = 2.702 ac, 7.01 % Impervious, Inflow Depth = 0.02" for 25 YEAR STORM event Inflow = 0.0 cfs @ 24.00 hrs, Volume= 0.0 of Primary = 0.0 cfs @ 24.00 hrs, Volume= 0.0 af, Atten= 0%, Lag= 0.0 min Primary outflow = Inflow, Time Span= 0.00-72.00 hrs, dt= 0.05 hrs DRAFT NOI 1/1612019 NYSDEC eBusiness Portal System - View Submission NOI for coverage under Stormwater General Permit for Construction Activity version 1.18 (Submission #: 37J-919X-99F4, version 1) PRINTED ON 1/16/2019 Summary Submission 0: 37J-919X-99F4 Dab Submitted: Form: NOI for coverage under Stommater General Permit for Construction Activity stews: Applicant: thomas center Active Steps: Reference 0: Description: NOI for coverage under Stomavater General Permit for Construction Activity Notes There are otmen0y no Submission Notes. Not Submitted Draft Form Submitted https:tlnfb m-prod.dec.ny.gov/SubmissionVersion/9e37967f-dae8-ff47-eOS34Mb3865579 1/12 1/16/2019 NYSDEC aBusiness Portal System - View Submission Details Owner/Operator Information Owner/Operator Name (Company/Private Owner/Municipaltty/AgencynnstMAion, etc.) TRA TOM Owner/Operator Contact Person Last Name (NOT CONSULTANT) FARONE Owner/Operator Contact Person First Nam THOMAS Owner/Operator Mailing Address 677 NYS ROUTE 9 City GANSEVOORT State NY Zip 12831 Phone 5188858817 Email NONE PROVIDED Federal Tax to NONE PROVIDED Project Location Project/Site Name BARRINGER HEIGHTS LOT 1 SUBDIVISION Street Address (Not P.O. Box) RICHMOND HILL DRIVE Side of Street East CityRowNVillage (THAT ISSUES BUILDING PERMIT) QUEENSBURY State NY Zip 12804 County WARREN DEC Region 5 Name of Nearest Cross Street SHERMAN AVENUE Distance to Nearest Cross Street (Fast) 500 tlttasJ/Moan-0rod.dec.nv.aov/SubmissionVemfon/9e37967f-dae&fr47-e053-6868b3865579 2/12 1/16/2019 Project In Relation to Cross Street South NYSDEC eBusiness Portal System -View Submission Tax Map Numbers Section -Block -Parcel 308.7-1-48 Tax Map Numbers NONE PROVIDED 1. Coordinates Provide the Geographic Coordinates for the project site. The two methods are: - Navigate to the project location on the map (below) and dick to place a marker and obtain the XY coordinates. - The *Find Me' button will provide the Iablong for the person filling out this form. Then pan the map to the correct location and dick the map to place a marker and obtain the XY coordinates. Navigate to your location and click on the map to get the X,Y coordinates 43.310228460912235,-73.70690200004015 Project Details 2. What is the nature of this project? New Construction 3. Select the predominant land use for bath pre and post development conditions. Pre -Development Existing Landuse Single Family Subdivision Post -Development Future Land Use Single Family Subdivision (Please answer 3a) 3a. If Single Family Subdivision was selected in question 3, enter the number of subdivision lots. 4 4. In accordance with the larger common plan of development or sale, enter the total project site acreage, the acreage to be disturbed and the future impervious area (acmage)Mthin the disturbed area. — ROUND TO THE NEAREST TENTH OF AN ACRE. — Total Site Area (acres) 29.06 Total Area to be Disturbed (acres) 1.6 Existing Impervious Area to be Disturbed (acres) 0 Future Impervious Area Within Disturbed Area (acres) 0.2 5. Do you plan to disturb more than 5 acres of soil at any one time? No 6. Indicate the percentage (%) of each Hydrologic Soil Group(HSG) at the site. htlpsllnforrn-prod.dec.ny.gov/SubmissionVersion/9e37967fdae&B47.e053-m8b3665579 3/12 1/16/2019 NYSDEC e9ushiess Portal System - View Submission A (%) 100 B (%) 0 C (%) 0 D (%) 0 T. Is this a phased project? No 8. Enter the planned start and end dates of the disturbance activities. Start Date 03/01/2019 End Date 01/01/2019 9. Identify the nearest surface waterbody(ies) to which construction site runoff will discharge. UNNAMED TRIBUATRY TO CLENDON BROOK so. Type of waterbody identified in question 9? Stream/Creek Off Site Other Waterbody Type Off Site Description NONE PROVIDED 9b. If "wetland" was selected in 9A, how was the watiand identified? NONE PROVIDED 10. Has the surface waterbody(les in question 9 been identified as a 303(d) segment in Appendix E of GP-0.15.002? No 11. Is this project located in one of the Watersheds identified in Appendix C of GP-0.15.002? No 12. Is the project located in one of the watershed areas associated with AA and AAS classified waters? No If No, skip question 13. 13. Does this construction activity disturb land with no existing impervious cover and where the Soil Slope Phase is identified as an E or F on the USDA Soil Survey? No If Yes, what is the acreage to be disturbed? NONE PROVIDED 14. Will the project disturb soils within a State regulated wetland or the protected 100 foot adjacent area? No 15. Does the site runoff enter a separate storm sewer system (including roadside draimr, swales, ditches, culverts, etc)? httpsltnfom prod.dec.ny.00v/SubmissionVersiont9e37967fdaeS-ff47-0053S868b3865579 4/12 1/16/2019 NYSDEC eSusiness Portal System - View Submission No 16. What is the name of the municipality/entity that owns the separate storm sewer system? NONE PROVIDED 17. Does any runoff from the site enter a sewer classified as a Combined Sewar? No 18. Will future use of this site be an agricultural property as defined by the NYS Agriculture and Markets Law? No 19. Is this property owned by a state authority, state agency, federal government or local government? No 20. Is this a remediation project being done under a Department approved work plan? (i.e. CERCLA, RCRA, Voluntary Cleanup Agreement, etc.) No Required SWPPP Components 21. Has the required Erosion and Sediment Control component of the SWPPP been developed in conformance with the current NYS Standards and Specifications for Erosion and Sediment Control (aka Blue Book)? Yes 22. Does this construction activity require the development of a SWPPP that includes the postconstruction stormwater management practice component (i.e. Runoff Reduction, Water Quality and Quantity Control practices/techniques)? No If you answered No in question 22, skip question 23 and the Post -construction Criteria and Post -construction SMP Identification sections. 23. Has the post -construction stormwater management practice component of the SWPPP been developed in conformance with the current NYS Stormwater Management Design Manual? 24. The Stormwater Pollution Prevention Plan (SWPPP) was prepared by: Professional Engineer (PE.) SWPPP Preparer HUTCHINS ENGINEERING Contact Name (Last Space, First) CENTER, THOMAS Mailing Address 169 Haviland Road City queensbury State NY Zip 12804 Phone 5187962615 Email https://nfomvprod.dec.ny.gov/Submission VersroN9e37967f-daeB-ff47-e053-OMb3865579 5112 1/16/2019 tcenter36@gmail.mm NYSDEC eBusiness Portal System - View Submission Download SWPPP Preparer Certification Form Please take the following steps to prepare and upload your preparer certification form: 1) Click on the link below to download a blank certification form 2) The certified SWPPP preparer should sign this form 3) Scan the signed forth 4) Upload the scanned document Download SWPPP Preparer Certification Form Please upload the SWPPP Preparer Certification -Attachment NONE PROVIDED Comment: NONE PROVIDED Erosion & Sediment Control Criteria 25. Has a construction sequence schedule for the planned management practices been prepared? Yes 26. Select all of the erosion and sediment control practices that will be employed on the project site: Temporary Structural Sediment Traps Silt Fence Stabilized Construction Entrance Biotechnical Now Vegetative Measures Topsolling Permanent Structural None Other NONE PROVIDED Post -Construction Criteria . IMPORTANT. Completion of Questions 27-39 is not required if response to Question 22 is No. 27. Identify all site planning practices that were used to prepare the final she plan/layout for the project. NONE PROVIDED 27a. Indicate which of the following soil restoration criteria was used to address the requirements in Section 5.1.6("Soil Restoration") of the Design Manual (2010 version). 28. Provide the total Water Quality Volume (WQv) required for this project (based on final site plan/layout). (Acre-feet) NONE PROVIDED 29. Post -construction SMP Identification Use the Post -construction SMP Identification section to identify the RR techniques (Area Reduction), RR ledmiques(Volume Reduction) and Standard SMPs with RRv Capably that were used to reduce the Total WQv Required (#28). Identify the SMPs to be used by providing the total Impervious area that contributes runoff to each technique/prectios selected. For the Area Reduction Techniques, provide the total contributing area (Includes pervious area) and, h applicable, the total impervious area that contributes runoff to the technlquelpraWce. Note: Redevelopment projects shall use the Post -Construction SMP Identification section https:llnfdrm-prod.dec.ny.govISubmissionVersionlgs37967f-dae8-447-e053-6868b3865579 6/12 1/16/2019 NYSDEC eBusiness Portal System - View Submission to identify the SMPs used to treat and/or reduce the WQv required. If runoff reduction techniques will not be used to reduce the required WOv, skip to question 33a after identifying the SMPs. 30. Indicate the Total RRv provided by the RR techniques (Area/Volume Reduction) and Standard SMPs with RRv capacity identified in question 29. (acre-feet) NONE PROVIDED 31. Is the Total RRv provided (#30) greater than or equal to the total WQv required (#28)? If Yes, go to question 36. If No, go to question 32. 32. Provide the Minimum RRv required based on HSG. [Minimum RRv Required = (P) (0.95) (AI) / 12, Ai=(s) (Aic)] (acre -feat) NONE PROVIDED 32a. Is the Total RRv provided (#30) greater than or equal to the Minimum RRv Required (#32)? If Yes, go to question 33. Note: Use the space provided in question #39 to summarize the specific site limitations and justification for not reducing 100% of WQv required (#28). A detailed evaluation of the specific site limitations and justification for not reducing 100% of the WQv required (#28) must also be included in the SWPPP. If No, slang criteria has not been met; therefore, NOI can not be processed. SWPPP preparer must modify design to meet sizing atteria. 33. SMPs Use the Post -construction SMP Identification section to identify the Standard SMPs and, if applicable, the Alternative SMPs to be used to beat the remaining total WQv (=Total WQv Required in #28 - Total RRv Provided in #30). Also, provide the total impervious area that contributes mnolf to each practice selected. NOTE: Use the Post -construction SMP Identification section to identify the SMPs used on Redevelopment projects. 33a. Indicate the Total WQv provided (i.e. WQv treated) by the SMPs identified in question #33 and Standard SMPs with RRv Capacity identified in question 929. (acre-feet) NONE PROVIDED Note: For the standard SMPs with RRv capacity, the WQv provided by each practice = the WQv calculated using the contributing drainage area to the practice - provided by the practice. (See Table 3.5 in Design Manual) 34. Provide the sum of the Total RRv provided (930) and the WQv provided (#33a). NONE PROVIDED 35. Is the sum of the RRv provided (#30) and the WQv provided (#33a) greater than or equal to the total WQv required (#28)? If Yes, go to question 36. If No, sizing criteria has not been met; therefore, NO[ can not be processed. SWPPP preparer must modify design to meet sizing criteria. 36. Provide the total Channel Protection Storage Volume (CPv required and provided or select waiver (#36a), if applicable. CPv Required (acre-feet) NONE PROVIDED CPv Provided (acre-feet) NONE PROVIDED 36a. The need to provide channel protection has been waived because: https://nfbml-prod.dec.ny.gov/SubmissionVersion/ge37gb7f-dae84f47-eo53-6868b3865579 7/12 1 /16/2019 NYSDEC eBusiness Portal System - View Submission 37. Provide the Overbank Flood (Op) and Extreme Flood (Qf) control criteria or select waiver (#37a), if applicable. Overbank Flood Control Criteria (Qp) Pre -Development (CFS) NONE PROVIDED Poat-Uevelopment (CFS) NONE PROVIDED Total Extreme Flood Control Criteria (Cf) Pre -Development (CFS) NONE PROVIDED Post -Development (CFS) NONE PROVIDED 37a. The need to most the Qp and Of criteria has been waived because: 38. Has a long tern Operation and Maintenance Plan for the post -construction stormwater management practice(s) been developed? If Yes, Identify the entity responsible for the long term Operation and Maintenance NONE PROVIDED 39. Use this space to summarize the specific site limitations and Justification for not reducing 100% of WQv required (#28). (See question #32a) This space can also be used for other pertinent project information. NONE PROVIDED Post -Construction SMP IdentWication Runoff Reduction (RR) Techniques, Standard Stornwater Management Practices (SMPs) and Alternative SMPs Identify the Post -construction SMPs to be used by providing the total impervious area that contributes nmalf to each technique/practice selected. For the Area Reduction Techniques, provide the total contributing area (includes pervious area) and, if applicable, the total impervious area that contributes runoff to the technique/practice. RR Techniques (Area Reduction) Round to the nearest tenth Total Contributing Acres for Conservation of Natural Area (RR-1) NONE PROVIDED Total Contributing Impervious Acres for Conservation of Natural Area (RR-1) NONE PROVIDED Total Contributing Acres for Sheatnow to Riparian Bufferaffilker Strips (RR-2) NONE PROVIDED Total Contributing Impervious Acres for Sheetflow to Riparian Buffers/Filter Strips (RR-2) NONE PROVIDED Total Contributing Acres for Tree PlantinglTree Pit (RR-3) NONE PROVIDED https:l/ntonn-prod.dec.ny.gav/SubmissionVersionl9e37967f-daeB-ff47-eO53-686Bb3865579 8/12 f/16/2019 NYSDEC eBusiness Portal System - View Submission Total Contributing Impervious Acres for Tree Plaming(Tree Pit (RR-3) NONE PROVIDED Total Contributing Acres for Disconnection of Rooftop Runoff (RR-4) NONE PROVIDED RR Techniques (Volume Reduction) Total Contributing Impervious Acres for Disconnection of Rooftop Runoff (RR-4) NONE PROVIDED Total Contributing Impervious Acres for Vegetated Swale (RR-5) NONE PROVIDED Total Contributing Impervious Acres for Rain Garden (RR-6) NONE PROVIDED Total Contributing Impervious Acres for Stormwater Planter (RR-7) NONE PROVIDED Total Contributing Impervious Acres for Rain Bartel/Cistern (RR-6) NONE PROVIDED Total Contributing Impervious Acres for Porous Pavement (RR-9) NONE PROVIDED Total Contributing Impervious Acres for Green Roof (RR-10) NONE PROVIDED Standard S(ulPs with RRv Capacity Total Contributing Impervious Acres for Infiltration Trench (1.1) NONE PROVIDED Total Contributing Impervious Acres for Infiltration Basin (1-2) NONE PROVIDED Total Contributing Impervious Acres for Dry Well (1.3) NONE PROVIDED Total Contributing Impervious Acres for Underground Infiltration System (Id) NONE PROVIDED Total Contributing Impervious Acres for Bioretention (FS) NONE PROVIDED Total Contributing Impervious Acres for Dry Swale (0-1) NONE PROVIDED Standard SMPs Total Contributing Impervious Acres for Micropool Extended Detention (P-1) NONE PROVIDED Total Contributing Impervious Acres for Wet Pond (P-2) NONE PROVIDED Total Contributing Impervious Acres for Wet Extended Detention (Pa) https://nform-prod.dec.ny.gov/SubmissionVersion/9e37967f-dae8-if47-e053-6868b3865579 9/12 1/16/2019 NYSDEC sBusmess Portal System - View Submission NONE PROVIDED Total Contributing Impervious Acres for Multiple Pond System (P-4) NONE PROVIDED Total Contributing Impervious Acres for Pocket Pond (P5) NONE PROVIDED Total Contributing Impervious Acres for Surface Sand Filter (F-1) NONE PROVIDED Total Contributing Impervious Acres for Underground Sand Filter (F-2) NONE PROVIDED Total Contributing Impervious Acres for Perimeter Sand Filter (F41) NONE PROVIDED Total Contributing Impervious Acres for Organic Filter (Fri) NONE PROVIDED Total Contributing Impervious Acres for Shallow Wetland (W-1) NONE PROVIDED Total Contributing Impervious Acres for Extended Detention Wetland (W-2) NONE PROVIDED Total Contributing Impervious Acres for PondlWetland System (W-3) NONE PROVIDED Total Contributing Impervious Acres for Pocket Wetland (W-4) NONE PROVIDED Total Contributing Impervious Acres for Wet Swale (0.2) NONE PROVIDED Alternative SMPs (DO NOT INCLUDE PRACTICES BEING USED FOR PRETREATMENT ONLY) Total Contributing Impervious Area for Hydrodynamic NONE PROVIDED Total Contributing Impervious Area for Wet Vault NONE PROVIDED Total Contributing Impervious Area for Media Filter NONE PROVIDED "Other Alternative SMP? NONE PROVIDED Total Contributing Impervious Area for "Other' NONE PROVIDED Provide the name and manufaturer of the alternative SMPs (i.e. proprietary pracgce(s)) being used for WQv treatment. Note: Redevelopment projects which do not use RR techniques, shall use questions 28, 29, 33 and 33a to provide SMPS used, total WQv required and total WQv provided for the project. Manufacturer of Alternative SMP NONEPROVIDED Name of Alternative SMP https:/hdonn-prod.dec.nv.gov/SubmissbnVersbn/9e37967f-0ae&tf47-9053.6868b3865579 10112 1/16/2019 NYSDEC eBusiness Portal System - View Submission NONE PROVIDED Other Permits 40. Identify other DEC permits, existing and new, that are required for this projecVbcility. None If SPDES Muhi,%ctor GP, than give permit ID NONE PROVIDED If Other, then identify NONE PROVIDED 41. Does this project require a US Army Corps of Engineers Wetland Permit? No If "Yes," then indicate Size of Impact, in acres, to the nearest tenth NONE PROVIDED 42. If this Not is being submitted for the purpose of continuing or transferring coverage under a general permit for stormwater ronoff from construction activities, plea" indicate the former SPDES number assigned. NONE PROVIDED MS4 SWPPP Acceptance 43. Is this project subject to the requirements of a regulated, traditional land use control MS4? Yes - Please attach the MS4 Acceptance form below If No, skip question 44 44. Has the "MS4 SWPPP Acceptance" form been signed by the principal executive officer or ranking elected official and submitted along with this NOI? MS4 SWPPP Acceptance Form Download Download form from the link below. Complete, sign, and upload. MS4 SWPPP Acceptance Form MS4 Acceptance Form Upload -Attachment NONE PROVIDED Comment NONE PROVIDED Owner/Operator Certification Owner/Operator Certification Forth Download Download the certification form by clicking the link below. Complete, sign, scan, and upload the form. Owner/Operator Certification Form (PDF, 45KB) Upload Owner/Operator Certification Form • -Attachment NONE PROVIDED Comment: NONE PROVIDED Attachments Dab Attachment Name Context https://nfbrm-prod.dec.nygov/SubmissionVersion/9e37967f-dae&tM7-9053-6M8b3865579 11/12 1/16/2019 NYSDEC eBusiness Portal System - View Submission Status History Dote Uwr Pro ing Shuts None Processing Steps Step Name Assigned TolComplehd By Form Submitted Deemed Complete Toni Cioffi Data Completed https://nfomrprod.dec.ny.gov/SubmissionVenuont9e37967f-daeB-fr47.e053.6866b3865579 12112